Staircase. Staircase shall be built with minimum 4-inch Waist Slab using 20mm downgraded aggregates in M 20 (1:1.5:3) and Reinforcement as per Structural Drawings. Steps shall be build using Good Quality Masonry (Regular Red Bricks) in 9 inch thick.
Staircase. The Staircase railings would be of MS with Wooden/PVC handrails as per the design & specification of the Architect.
Staircase. Tenant shall have the right, subject to specific location, manner of installation, to the terms of this Article and the approval of Landlord’s structural engineer, to construct an internal staircase within the Premises between the 17th floor of the Premises and the 18th floor of the Premises, between the 22nd floor of the Premises and the 23rd floor of the Premises and between the 23rd floor of the Premises and the 24th floor of the Premises and between any other contiguous floors of the Building which Tenant leases pursuant to Article 38.
Staircase. The stair cases of the building the stair headroom. 4.Lifts: As given.
Staircase. Stair will be finished with Marble WINDOWS : Aluminium sliding window with outside grill.
Staircase. Landlord to install center staircase between floors 4 and 5.
Staircase. Staircase of precast reinforced concrete complete with polished stainless steel handrail. The stairs are fitted with solid ash strings and skirtings with clear varnish finish to match remainder of accommodation. ELECTRICAL INSTALLATION Lighting is provided as follows:- Ground Floor Office: 19 No. Recessed fluorescent luminaires (1200mm x 600mm). Ground Floor Toilet 5 No. Recessed compact fluorescent downlights. Accommodation Concealed fluorescent bxxxxx luminaires above mirrors and WC’s. Kitchenette & Lobby: 2 No. Circular recessed fluorescent fittings with prism louvres. Production Area: 9 No. Sodium boxed downlighters. Disabled Toilets: 1 No. Shallow dome, wall mounted fluorescent fitting. Staircase & 4 No. Recessed, compact, fluorescent downlights. Associated Lobbies: 3 No. Wall mounted, feature, fluorescent fittings. 3 No. Recessed, circular, fluorescent luminaires. First Floor Toilet 3 No. Compact fluorescent downlights Accommodation: 2 No. Concealed fluorescent bxxxxx luminaires above WC’s. First Floor Office: 22 No. 1200mm x 600mm recessed fluorescent luminaires with V cross blade low brightness louvres.
Staircase. 9No pictures and frames
Staircase. Steel staircases finished with commercial quality carpet tiles complete with aluminium nosings with non-slip inserts. Polished stainless steel handrails and balustrading.
Staircase. Landlord acknowledges that pursuant to one or more Change Orders requested by Tenant, the base building plans and specifications will be modified to require construction of a monumental staircase (the "Staircase") between floors one and two in the Premises. Provided that Tenant has delivered to Landlord the required design criteria to Landlord by a deadline hereafter established by written notice to Tenant, and provided that Landlord approves such design criteria, Landlord agrees to design and construct, all at Tenant's sole cost and expense, such approved Staircase, a floor opening for the Staircase, different lobby finishes (including stone work and wood work), and other changes to the Base Building relating to such Staircase as reflected in the approved modified base building plans and specifications (the aggregate costs incurred by Landlord relating thereto, both hard costs and soft costs, which shall be established pursuant to the provisions of Appendix C, are herein collectively referred to as the "Staircase Costs"), subject to the following additional terms and conditions: