Common use of Synchronization, Commissioning and Commercial Operation Clause in Contracts

Synchronization, Commissioning and Commercial Operation. 5.1.1 The HPD shall give the concerned RLDC/SLDC and Buyer at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the HPD to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the HPD at its generation facility of the Power Project at its own cost. The HPD shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substation/Grid System and checking/verification is made by the concerned authorities of the Grid System. 5.1.4 The HPD shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the HPD will inject in-firm power to grid time to time to carry out operational/ functional test prior to commercial operation 5.1.5 The HPD shall commission the Project within eighteen (18) Months from the date of issuance of LOA.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

AutoNDA by SimpleDocs

Synchronization, Commissioning and Commercial Operation. 5.1.1 The HPD WPD shall give the concerned RLDC/SLDC and Buyer at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the HPD WPD to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the HPD WPD at its generation facility of the Power Project at its own cost. The HPD WPD shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substation/Grid System and checking/verification is made by the concerned authorities of the Grid System. 5.1.4 The HPD WPD shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the HPD WPD will inject in-firm power to grid time to time to carry out operational/ functional test prior to commercial operation 5.1.5 The HPD WPD shall commission the Project within eighteen (18) Months from the date Effective Date of issuance of LOAthis Agreement.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The HPD WPD shall give the concerned RLDC/SLDC and Buyer at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the HPD WPD to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the HPD WPD at its generation facility of the Power Project at its own cost. The HPD WPD shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substationsub- station/Grid System and checking/verification is made by the concerned authorities of the Grid System. 5.1.4 The HPD WPD shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the HPD WPD will inject in-firm power to grid time to time to carry out operational/ functional test prior to commercial operation 5.1.5 The HPD WPD shall commission the Project within eighteen (18) Months from the date of issuance of LOALOA by SECI to WPD.

Appears in 2 contracts

Samples: Power Purchase Agreement, Power Purchase Agreement

Synchronization, Commissioning and Commercial Operation. 5.1.1 The HPD SPD shall give the concerned RLDC/BBMB/ Concerned Authority (SLDC and Buyer and/or RLDC as applicable) at least sixty (60) days days’ advanced preliminary written notice and at least thirty (30) days days’ advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the HPD SPD to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the HPD SPD at its generation facility of the Power Project at its own cost. The HPD SPD shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substation/Grid System and checking/verification is made by the concerned authorities of the Grid System. 5.1.4 The HPD SPD shall immediately after each synchronization/tripping of generator, inform SLDC/RLDC and the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid CodeCode under intimate]on to BBMB. In addition, the HPD SPD will inject in-firm power to grid time to time to carry out operational/ functional test prior to commercial operation 5.1.5 The HPD shall commission . For avoidance of doubt, it is clarified that Synchronization / Connectivity of the Project within eighteen (18) Months from with the date grid shall not to be considered as Commissioning of issuance of LOAthe Project.

Appears in 1 contract

Samples: Power Purchase Agreement

AutoNDA by SimpleDocs

Synchronization, Commissioning and Commercial Operation. 5.1.1 The HPD WPD shall give the concerned RLDC/SLDC and Buyer at least sixty (60) days advanced preliminary written notice and at least thirty (30) days advanced final written notice, of the date on which it intends to synchronize the Power Project to the Grid System. 5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the HPD WPD to the Grid System when it meets all the connection conditions prescribed in applicable Grid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 5.1.3 The synchronization equipment and all necessary arrangements / equipment including RTU Remote Terminal Unit (RTU) for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the HPD WPD at its generation facility of the Power Project at its own cost. The HPD WPD shall synchronize its system with the Grid System only after the approval of synchronization scheme is granted by the head of the concerned substationsub-station/Grid System and checking/verification is made by the concerned authorities of the Grid System. 5.1.4 The HPD WPD shall immediately after each synchronization/tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. In addition, the HPD WPD will inject in-firm power to grid time to time to carry out operational/ functional test prior to commercial operation 5.1.5 The HPD WPD shall commission the Project within eighteen Twelve (1812) Months from the date of issuance of LOALOA by REMCL to WPD.

Appears in 1 contract

Samples: Power Purchase Agreement