Common use of Temporary Electrical Service Clause in Contracts

Temporary Electrical Service. Owner shall secure electrical service to supply a minimum 750 KW of 3-phase, 480/277 volt electrical power during construction. Owner shall procure, install, and maintain temporary service to up to three 3-phase, 480/277 volt temporary service transformers located throughout the site. The transformer sizing, locations, and underground electrical feed routing layout are to be determined jointly by the Owner, the Design-Builder and the energy supplier. Design-Builder shall pay energy demand and usage charges up to Substantial Completion.

Appears in 10 contracts

Samples: Master Agreement (US BioEnergy CORP), Build Expansion Agreement (Golden Grain Energy), License Agreement (Highwater Ethanol LLC)

AutoNDA by SimpleDocs

Temporary Electrical Service. Owner shall secure electrical service to supply a minimum 750 KW of 3-3 phase, 480/277 volt electrical power during construction. Owner shall procure, install, and maintain temporary service to up to three 3-3 phase, 480/277 volt temporary service transformers located throughout the site. The transformer sizing, locations, and underground electrical feed routing layout are to be determined jointly by the Owner, the Design-Builder and the energy supplier. Design-Builder shall pay energy demand and usage charges up to Substantial Completion.

Appears in 3 contracts

Samples: License Agreement (Millennium Ethanol, LLC), License Agreement (Advanced BioEnergy, LLC), Lump Sum Design Build Contract (Advanced BioEnergy, LLC)

Temporary Electrical Service. Owner shall secure electrical service to supply a minimum 750 KW of 3-phase, 480/277 volt electrical power during construction. Owner shall procure, install, and maintain temporary service to up to three 3-phase, 480/277 volt temporary service transformers and one 1-Phase, 240/120 Volt temporary service transformer located throughout the site. The transformer sizing, locations, and underground electrical feed routing layout are to be determined jointly by the Owner, the Design-Builder and the energy supplier. Design-Builder shall pay energy demand and usage charges up to Substantial Completion.

Appears in 2 contracts

Samples: License Agreement (One Earth Energy LLC), License Agreement (Homeland Energy Solutions LLC)

Temporary Electrical Service. Owner shall secure electrical service to supply a minimum 750 KW of 3-phase, 480/277 volt electrical power during construction. Owner shall procure, install, and maintain temporary service to up to three 3-phase, 480/277 volt temporary service transformers and one 1-Phase, 240/120 volt temporary service transformer located throughout the site. The transformer sizing, locations, and underground electrical feed routing layout are to be determined jointly by the Owner, the Design-Builder and the energy supplier. Design-Builder shall pay energy demand and usage charges up to Substantial Completion.

Appears in 2 contracts

Samples: License Agreement (Advanced BioEnergy, LLC), License Agreement (Advanced BioEnergy, LLC)

AutoNDA by SimpleDocs

Temporary Electrical Service. Owner shall secure electrical service to supply a minimum 750 KW of 3-phase, 480/277 volt electrical power during construction. Owner shall procure, install, and maintain temporary service to up to three 3-phase, 480/277 volt temporary service transformers located throughout the site. The transformer sizing, locations, and underground electrical feed routing layout are to be determined jointly by the Owner, the Design-Builder and the energy supplier. Design-Builder shall pay energy demand and usage charges up to Substantial Completion.

Appears in 1 contract

Samples: License Agreement (US BioEnergy CORP)

Temporary Electrical Service. Owner shall secure electrical service to supply a minimum of 750 KW of 3-phase, 480/277 volt electrical power during construction. Owner shall procure, install, and maintain temporary service to up to three 3-phase, 480/277 volt temporary service transformers and one 1-Phase, 240/120 Volt temporary service transformer located throughout the site. The transformer sizing, locations, and underground electrical feed routing layout are to be determined jointly by the Owner, the Design-Builder and the energy supplier. Design-Builder shall pay energy demand and usage charges up to Substantial Completion.

Appears in 1 contract

Samples: License Agreement (Cardinal Ethanol LLC)