Time and Materials Adjustments to the Agreement Price Sample Clauses

Time and Materials Adjustments to the Agreement Price. 9.12.1. If Owner has issued a Directive Letter to Contractor to proceed with the work, then Contractor shall be paid for the costs as set forth herein associated with the work defined in the Directive Letter on a time and materials basis provided that such costs are: (i) reasonably and properly incurred by Contractor; (ii) reasonably documented; (iii) those costs that would not have been incurred but for the change in the work or, in the case of Contractor’s Proposed Change Order claims under Article 9.5 above, the events or circumstances for which Contractor is entitled to relief in accordance with the provisions of said Article 9.5 above.
AutoNDA by SimpleDocs
Time and Materials Adjustments to the Agreement Price. 9.11.1. If Owner has issued a Directive Letter to Contractor to proceed with the work, then Contractor shall be paid for the costs as set forth herein associated with the work defined in the Directive Letter on a time and materials basis provided that such costs are:

Related to Time and Materials Adjustments to the Agreement Price

  • Contingent Price Adjustment It is the policy of the State of Oregon that unprocessed timber shall not be exported from lands owned or managed by the STATE or any of its political subdivisions or agencies, in accordance with the terms of current federal law and the Constitution and the laws of the State of Oregon. PURCHASER specifically agrees that Section 1 is a material term of this contract and is part of the consideration offered to STATE in return for STATE's performance. In the event that any federal law or state constitutional provision or law or any provision of this contract concerning export of unprocessed timber is declared invalid by any court or administrative tribunal, PURCHASER agrees to pay to STATE a contingent price in the amount of the difference between the purchase price set forth in this section and the price obtained by PURCHASER for the exported unprocessed timber. The default provisions of OAR 629-032-0000 through 629-032-0070 shall not apply to exported unprocessed timber. In the event that timber made available under this contract is exported in violation of this contract, PURCHASER shall be in material breach of the contract. STATE shall be entitled to cease performance of the contract and recover, in addition to the adjusted price set out above, a further sum estimated to compensate for administrative expense and the economic impact of the violation upon the State and its citizens. In no case shall this additional amount be less than $10,000 per incident.

  • Price Schedule, Payment Terms and Billing, and Price Adjustments (a) Price Schedule: Price Schedule under this Contract is set forth in Exhibit B.

  • Construction Cost Adjustment Contracting Officer, as provided in B5.21, B5.212, B5.251, B5.252, and B5.253, shall adjust Specified Road construction cost estimates in the Schedule of Items and show the adjustments as credits or debits to Timber Sale Account in the month when the road segment is accepted.

  • Contract Term Adjustment “Contract Term Adjustment” means adjustment only as provided for in the three circumstances described in this Subsection. Under these circumstances, the contract term shall be adjusted in writing to include additional calendar days in one or more Normal Operating Seasons equal to the actual time lost, except as limited by paragraph (b) in this Subsection. To qualify for such adjustment, Purchaser shall give written notice of the lost time not later than 30 days after end of Normal Operating Season in which time was lost and at least 10 days before Termination Date. Contracting Officer shall make prompt written acknowledgment of such notice, indicating concurrence with the number of days in the notice or the number of days Forest Service considers as qualifying for the adjustment. Lost portions of days shall be disregarded in computing time lost. The three circumstances qualifying for a Contract Term Adjustment are:

  • Rental Rates and Wage Rates for Change Orders As soon as is practical, but prior to the completion of the Construction Preparation Period and in any event prior to the commencement of any Work on the Site, the Contractor shall submit in accordance with the style and format of a specimen to be furnished by the Owner for consideration of the Owner the following: (1) a proposal for rental rates on heavy construction equipment that shall apply in the event Change Order Work is performed, and (2) a proposal for wage rates for the types of project labor that shall apply in the event of the execution of any Change Order Work. Under penalty of false swearing, a principal of the contracting firm shall certify that the proposal for rental rates and proposal for wage rates do not exceed current costs for like services. The Owner will in no event consider a rental rate in excess of eighty percent of the rate set forth in the latest edition of the "Compilation of Nationally Averaged Rental Rates for Construction Equipment" of the Associated Equipment Distributors unless the rates proposed in excess of eighty percent are supported by proof satisfactory to the Owner that the excess rates are reasonable. If the equipment is owned by the Contractor the costs shall be charged at a maximum of eighty percent of market monthly rental rates for the amount of time used. If applicable, transportation costs may be included. The decision of the Owner shall be final, binding and conclusive on all parties. Rental rates shall be payable only for the actual time the equipment is required on the Site.

  • CLOSING COSTS AND ADJUSTMENTS All adjustments are made as of settlement date.

  • Price Adjustments for OGS Centralized Contracts Periodic price adjustments will occur no more than twice per year on a schedule to be established solely by OGS. Pricing offered shall be fixed for the first twelve (12) months of the Contract term. Such price increases will only apply to the OGS Centralized Contracts and shall not be applied retroactively to Authorized User Agreements or any Mini-bids already submitted to an Authorized User. Price Decreases Price decreases may be made at any time. Additionally, some price decreases shall be calculated in accordance with Appendix B, section 17, Pricing.

  • Cost Adjustments Both parties agree that contracted prices shall be fixed for the first 12 months of this Contract. Contractor must submit to District any proposed cost adjustments at least 60 days before the proposed effective date of such increases with a detailed explanation for each adjustment. District alone reserves the right to reject any changes to this Contract it deems unacceptable.

  • Contract Price Adjustment The basis upon which the Contract Price shall be adjusted is as set out in paragraph 9.2 of Schedule IVB.

  • CPI Adjustment In this Agreement, “CPI-Adjusted” in reference to an amount means that amount is adjusted under the following formula: N  C  (1 CPIn  CPIc ) CPIc where: ”N” is the new amount being calculated; and “C” is the current amount being adjusted; and