Transmission System Operator’s Obligations Sample Clauses

Transmission System Operator’s Obligations. ‌ Subject to articles 2 and 4 of the present section, articles 9, 10, 12, 13 and 14 of the General Terms and the limitations provided for in this article, the TSO undertakes to: o take off, on any Day whatsoever, the Scheduled Daily Quantities supplied by the Shipper at the Entry Points and at the PEG, on the same day o deliver to the Shipper, on the same Day, the Scheduled Daily Quantities to the Exit Points, Network Interconnection Points, Transport Storage Interface Delivery Points and PEG.‌
AutoNDA by SimpleDocs
Transmission System Operator’s Obligations. Subject to articles 2 and 4 of the present section, articles 9, 10, 12, 13 and 14 of the General Terms and the limitations provided for in this article, the TSO undertakes to: o take off, on any Day whatsoever, the Scheduled Daily Quantities supplied by the Shipper at the Entry Points and at the PEG, on the same day o deliver to the Shipper, on the same Day, the Scheduled Daily Quantities to the Exit Points, Network Interconnection Points, Transport Storage Interface Delivery Points and PEG. 6.1.1 LIMITATIONS RELATING TO DAILY CAPACITIES AND TO HOURLY CAPACITIES As the case may be, the Daily and Hourly Capacities covered by this article may be reduced by the TSO in the circumstances referred to at articles 9, 10, 12, 13 and 14 of the General Terms, in accordance with the procedures provided in the Operating Conditions. i. At the PITTE, PITPE and PITSE, at the PITTL and PITSL

Related to Transmission System Operator’s Obligations

  • Interconnection Customer Provided Services The services provided by Interconnection Customer under this LGIA are set forth in Article 9.6 and Article 13.5. 1. Interconnection Customer shall be paid for such services in accordance with Article 11.6.

  • System Upgrade Facilities and System Deliverability Upgrades Connecting Transmission Owner shall design, procure, construct, install, and own the System Upgrade Facilities and System Deliverability Upgrades described in Appendix A hereto. The responsibility of the Developer for costs related to System Upgrade Facilities and System Deliverability Upgrades shall be determined in accordance with the provisions of Attachment S to the NYISO OATT.

  • Transportation Services i) In the event that transportation services for a student served by CONTRACTOR pursuant to an Individual Services Agreement are to be provided by a party other than CONTRACTOR or the LEA or its transportation providers, such services shall be reflected in a separate agreement signed by the parties hereto, and provided to the LEA and SELPA Director by the CONTRACTOR. Except as provided below, CONTRACTOR shall compensate the transportation provider directly for such services, and shall charge the LEA for such services at the actual and reasonable rates billed by the transportation provider, plus a ten percent (.

  • Cost Responsibility for Interconnection Facilities and Distribution Upgrades 4.1 Interconnection Facilities 4.2 Distribution Upgrades

  • Interconnection Customer Authority Consistent with Good Utility Practice, this LGIA, and the CAISO Tariff, the Interconnection Customer may take actions or inactions with regard to the Large Generating Facility or the Interconnection Customer’s Interconnection Facilities during an Emergency Condition in order to (i) preserve public health and safety, (ii) preserve the reliability of the Large Generating Facility or the Interconnection Customer’s Interconnection Facilities,

  • Interconnection Customer Obligations The Interconnection Customer shall maintain the Large Generating Facility and the Interconnection Customer’s Interconnection Facilities in a safe and reliable manner and in accordance with this LGIA.

  • Services and Facilities The Procuring Entity shall make available to the Service Provider the Services and Facilities listed under Appendix F.

  • Interconnection Customer’s Interconnection Facilities The Interconnection Customer shall design, procure, construct, install, own and/or control the Interconnection Customer’s Interconnection Facilities described in Appendix A at its sole expense.

  • Interconnection Service Interconnection Service allows the Interconnection Customer to connect the Large Generating Facility to the Participating TO’s Transmission System and be eligible to deliver the Large Generating Facility’s output using the available capacity of the CAISO Controlled Grid. To the extent the Interconnection Customer wants to receive Interconnection Service, the Participating TO shall construct facilities identified in Appendices A and C that the Participating TO is responsible to construct.

  • Interconnection 2.1 This section applies to linking with suppliers providing public telecommunications transport networks or services in order to allow the users of one supplier to communicate with users of another supplier and to access services provided by another supplier, where specific commitments are undertaken.