Completion Deadlines definition

Completion Deadlines means Old Bee Cave Road Offsite Detention Area Completion Deadline, US 290 Westbound East Segment Completion Deadline, XX 000 Xxxxxxxxx Xxxx Xxxxxxx Xxxxxxxxxx Xxxxxxxx, XX 290 Westbound West Segment Completion Deadline, US 000 Xxxxxxxxx Xxxx Segment Completion Deadline, Substantial Completion Deadline and Final Acceptance Deadline. [Upon execution, delete Completion Deadlines for which DB Contractor did not submit an Interim Milestone Commitment] Contract Documents has the meaning set forth in Section 1.3 of this DBA.
Completion Deadlines means Old Bee Cave Road Offsite Detention Area Completion Deadline, US 290 Westbound East Segment Completion Deadline, XX 000 Xxxxxxxxx Xxxx Xxxxxxx Xxxxxxxxxx Xxxxxxxx, XX 290 Westbound West Segment Completion Deadline, US 000 Xxxxxxxxx Xxxx Segment Completion Deadline, Substantial Completion Deadline and Final Acceptance Deadline.

Examples of Completion Deadlines in a sentence

  • Except as otherwise specifically provided in Section 13, TxDOT shall have no obligation to extend a Completion Deadline and DB Contractor shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of the Project by the applicable Completion Deadlines for any reason.

  • All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.

  • All Float contained in the Project Schedule, as shown in the Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.

  • Except as specifically provided in Section 4.6 of the General Conditions, TxDOT shall have no obligation to extend a Completion Deadline, and DB Contractor shall not be relieved of its obligation to comply with the Project Schedule and meet the Completion Deadlines for any reason.

  • If approval is subject to the sole, absolute or unfettered discretion of TxDOT, then its decision shall be final, binding and not subject to dispute resolution, and such decision shall not entitle DB Contractor to an adjustment to the Price or Completion Deadline(s) or form the basis of any other Claim.

  • The Completion Deadlines for the Project are as set forth below, as such Completion Deadlines may be adjusted by Change Order pursuant to the Design-Build Contract.

  • The Completion Deadlines for the Project are as set forth below, as such may be adjusted by Change Order pursuant to the General Conditions.

  • The Reference Information Documents shall be deemed incorporated in the Contract Documents solely to the extent that they are so referenced, with the same order of priority as the Contract Document in which the reference occurs; provided, however, that DB Contractor shall only be entitled to rely on portions of the Reference Information Documents for increases to the Price and extensions of Completion Deadlines to the extent identified in Exhibit 3.

  • DB Contractor shall also be entitled to a Change Order, subject to the limitations and risk sharing provisions in the Contract Documents, to extend the applicable Completion Deadlines as a result of any delay in a Critical Path directly caused by failure or inability of TxDOT to make available any TxDOT Acquisition Parcel by the applicable “Availability Date” set forth in Table 15-1 of the Design-Build Specifications.

  • If approval is subject to the sole, absolute or unfettered discretion of TxDOT, then its decision shall be final, binding and not subject to dispute resolution, and such decision shall not entitle Developer to an adjustment to the Price or Completion Deadline(s) or form the basis of any other Claim.


More Definitions of Completion Deadlines

Completion Deadlines means Old Bee Cave Road Offsite Detention Area Completion Deadline, SH 71 Offsite Detention Area Completion Deadline, US 290 Westbound East Segment Completion Deadline, US 290 Eastbound East Segment Completion Deadline, US 290 Westbound West Segment Completion Deadline, US 290 Eastbound West Segment Completion Deadline, Substantial Completion Deadline and Final Acceptance Deadline. [Upon execution, delete Completion Deadlines for which DB Contractor did not submit an Interim Milestone Commitment] Contract Documents has the meaning set forth in Section 1.3 of this DBA.

Related to Completion Deadlines

  • Submission Deadline means 1:00 P.M., New York City time, on any Auction Date or such other time on any Auction Date as may be specified by the Auction Agent from time to time as the time by which each Broker-Dealer must submit to the Auction Agent in writing all Orders obtained by it for the Auction to be conducted on such Auction Date.

  • Objection Deadline means the date identified in the Preliminary Approval Order and Class Notice by which a Settlement Class Member must serve written objections, if any, to the Settlement to be able to object to the Settlement. The Objection Deadline shall be no later than 30 days before the Final Approval Hearing.

  • Completion Period means the period starting from the date of issue of "Order" and required to complete the work in all respect.

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • Response Deadline means 60 days after the Administrator mails Notice to Class Members and Aggrieved Employees, and shall be the last date on which Class Members may: (a) fax, email, or mail Requests for Exclusion from the Settlement, or (b) fax, email, or mail his or her Objection to the Settlement. Class Members to whom Notice Packets are resent after having been returned undeliverable to the Administrator shall have an additional 14 calendar days beyond the Response Deadline has expired.

  • Claims Objection Deadline means the later of: (a) the date that is 180 days after the Effective Date; and (b) such other date as may be fixed by the Bankruptcy Court, after notice and hearing, upon a motion Filed before the expiration of the deadline to object to Claims or Interests.

  • Election Deadline shall have the meaning set forth in Section 3.2.3.

  • Project Completion means completion of the Redevelopment in accordance with this Agreement to the state where the whole of the Xxxxxx Shopping Centre, as so redeveloped, is capable of occupation for its intended purpose;

  • Notice Deadline means 2.30 p.m. (Dublin time), provided that the Notice Deadline in respect of any Series of ETP Securities may be adjusted by agreement between the Issuer and the Margin Loan Provider with effect from the fifth calendar day following the date on which notice of such adjustment is given to the holders in accordance with Condition 17.

  • Cure Deadline shall have the meaning provided in Section 11.11(a).

  • Construction Completion Date or “Completion Date” means the date by which the overall Development of the Project is completed in accordance with the provisions of this Agreement and when the Completion Certificate is issued by the Authority as per Article 14.1.