Initial compliance period means the three-year compliance period that begins January 1, 1993, except for the MCLs for dichloromethane, 1,2,4-trichlorobenzene, 1,1,2-trichloroethane, benzo(a)pyrene, dalapon, di(2-ethylhexyl)adipate, di(2-ethyl- hexyl)phthalate, dinoseb, diquat, endothall, endrin, glyphosate, hexachlorobenzene, hexachlorocyclopentadiene, oxamyl, picloram, simazine, 2,3,7,8-TCDD, antimony, beryllium, cyanide, nickel, and thallium, as they apply to a supplier whose system has fewer than 150 service connections, for which it means the three-year compliance period that began on January 1, 1996.
Compliance Date means, in each case, the date by which compliance is required under the referenced provision of ARRA’s or HIPAA’s implementing regulations, as applicable.
Final Completion Date means the date on which Final Completion occurs.
The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.
Project Completion Date means the date on which the Completion Certificate is issued;
Substantial Completion Date means the date on which Substantial Completion occurs.
Commercial Operation Date means the date on which a Material Project is substantially complete and commercially operable.
Commercial Operation Date (COD) means the date certified by the DISCOM’s committee upon successful commissioning (as per provisions of the PPA) of the project when all equipments as per rated capacity have been installed and energy has flown into the grid.
Target Completion Date has the meaning given such term in Section 3.3(b).
Construction Completion Date means the Completion Date of the Construction as specified in the Statutory Declaration of Completion for the Project;
Environmental Compliance Reserve means any reserve which the Agent establishes in its reasonable discretion after prior written notice to the Borrower from time to time for amounts that are reasonably likely to be expended by the Borrower in order for the Borrower and its operations and property (a) to comply with any notice from a Governmental Authority asserting material non-compliance with Environmental Laws, or (b) to correct any such material non-compliance identified in a report delivered to the Agent and the Lenders pursuant to Section 7.7.
Covenant Compliance Event means, at any time, Availability is less than the greater of (i) ten percent (10%) of the Loan Cap and (ii) $15,000,000. The termination of a Covenant Compliance Event as provided herein shall in no way limit, waive or delay the occurrence of a subsequent Covenant Compliance Event in the event that the conditions set forth in this definition again arise.
Testing Date means each day which is: (i) the last day of the relevant Issuer's and the Guarantor's financial year in any year; or (ii) the last day of each of the first three quarters of the relevant Issuer's and the Guarantor's financial year in any year.
Distribution Compliance Period with respect to any Notes, means the period of 40 consecutive days beginning on and including the later of (i) the day on which such Notes are first offered to Persons other than distributors (as defined in Regulation S under the Securities Act) in reliance on Regulation S and (ii) the issue date with respect to such Notes.
Substantial compliance means a level of compliance with these rules where any deficiencies pose no greater risk to resident health or safety than the potential for causing minor harm.
Time of Completion means the time for completing the execution of and passing the Tests on Completion of the Works of any section or part thereof as stated in the Contract (or as extended under Clause...) calculated from the Commencement Date
Repeat compliance period means any subsequent compliance period after the initial compliance period.
Outside Completion Date shall have the meaning assigned to such term in Section 6.3(d).
Annual Statement of Compliance As defined in Section 3.13.
Reportable Compliance Event means that any Covered Entity becomes a Sanctioned Person, or is charged by indictment, criminal complaint or similar charging instrument, arraigned, or custodially detained in connection with any Anti-Terrorism Law or any predicate crime to any Anti-Terrorism Law, or has knowledge of facts or circumstances to the effect that it is reasonably likely that any aspect of its operations is in actual or probable violation of any Anti-Terrorism Law.
Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.
Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity
Date of Completion with respect to a Project shall mean: (i) the date upon which such Project and all components thereof have been acquired or constructed and are capable of performing the functions for which they were intended, as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; or (ii) the date on which the Issuer determines, upon the recommendation of or in consultation with the Consulting Engineer, that it cannot complete such Project in a sound and economical manner within a reasonable period of time as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; provided that in each case such certificate of the Consulting Engineer shall set forth the amount of all Costs of such Project which have theretofore been incurred, but which on the Date of Completion is or will be unpaid or unreimbursed.
Covenant Compliance Certificate means a properly completed and executed Covenant Compliance Certificate substantially in the form of Exhibit X hereto.
Commercial Operations Date or "COD": The date on which Facility first achieves Commercial Operations.
project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;