Initial Outage Plan definition

Initial Outage Plan has the meaning given such expression in Section 5.1(a);
Initial Outage Plan means the outage plan developed in Years 3-6.
Initial Outage Plan means the outage plan developed in Years 3-6 and beyond.

Examples of Initial Outage Plan in a sentence

  • The Operational Assessment Sub Group will consider the impact of the request on the Initial Outage Plan and associated Operational Assessment.

  • In week 6 each year the Initial Outage Plan for Year 3 shall become the Provisional Outage Plan for Year 2 and each Initial Outage Plan beyond Year 3 to Year 6 will similarly be rolled forward and a new Year 6 Plan will be started.

  • The Initial Outage Plan will become part of the Provisional Outage Plan as governed by STCP 11-1.

  • In week 6 each year the Initial Outage Plan for Year 3 shall become the Page Break Provisional Outage Plan for Year 2 and each Initial Outage Plan beyond Year 3 toYear 6 will similarly be rolled forward and a new Year 6 Plan will be started.

  • It’s location within the Kidbrooke Area for Intensification where policy is to optimise the potential for new housing.

  • Initial/Provisional Outage Plans9.16.16 Based on the outage needs information submitted, the TSO shall prepare an Initial Outage Plan for the next year and a Provisional Outage Plan for a further two years.9.16.17 Whereas the TSO, in preparing the outage plans, shall endeavor to accommodate GCPs’ requests for particular dates, the outage needs submitted by a GCP only represent a preference which shall be subject to the scheduling considerations of the TSO.

  • NGET shall use the Initial Outage Plan to perform an Operational Assessment.

  • Signing the protocol will constitute approval of the services performed.

  • Exterior alterations and/or additions up to 500 square feet to non-conformingsingle family dwellings or duplexes may maintain their non-conforming status provided they maintain the building footprint.

  • Deleted: PLDs and Project ListingDeleted:Deleted: Project ListingsDeleted: and Deleted: and Deleted: Page Deleted: ofIssue 004 - xx/06/2011 The Initial Outage Plan will become part of the Provisional Outage Plan as governed by STCPDeleted: 003 - 14/01/Deleted: 4Deleted: ¶11-1.

Related to Initial Outage Plan

  • Planned Outage means the removal of equipment from service availability for inspection and/or general overhaul of one or more major equipment groups. To qualify as a Planned Outage, the maintenance (a) must actually be conducted during the Planned Outage, and in Seller’s sole discretion must be of the type that is necessary to reliably maintain the Project, (b) cannot be reasonably conducted during Project operations, and (c) causes the generation level of the Project to be reduced by at least ten percent (10%) of the Contract Capacity.

  • Generator Planned Outage means the scheduled removal from service, in whole or in part, of a generating unit for inspection, maintenance or repair with the approval of the Office of the Interconnection in accordance with the PJM Manuals.

  • Unplanned Outage refers to the unavailable status of the units of the Power Plant other than Planned Outage. Based on the urgency of the needs of outage, the Unplanned Outage can be classified into five categories: (1) immediate outage; (2) the outage which could be delayed for a short while but the units must exit within six hours; (3) the outage which could be postponed over six hours but the units must exit within seventy-two hours; (4) the outage which could be deferred over seventy-two hours but the units must exit before the next Planned Outage; and (5) the prolonged outage which is beyond the period of the Planned Outage.

  • Outage has the meaning set forth in the CAISO Tariff.

  • Generator Forced Outage means an immediate reduction in output or capacity or removal from service, in whole or in part, of a generating unit by reason of an Emergency or threatened Emergency, unanticipated failure, or other cause beyond the control of the owner or operator of the facility, as specified in the relevant portions of the PJM Manuals. A reduction in output or removal from service of a generating unit in response to changes in market conditions shall not constitute a Generator Forced Outage.

  • PJM Region Peak Load Forecast means the peak load forecast used by the Office of the Interconnection in determining the PJM Region Reliability Requirement, and shall be determined on both a preliminary and final basis as set forth in Tariff, Attachment DD, section 5.

  • Scheduled Commissioning Date or “SCD” of the Project shall mean [Insert Date];

  • System Impact Study means an assessment by the Transmission Provider of (i) the adequacy of the Transmission System to accommodate a Completed Application, an Interconnection Request or an Upgrade Request, (ii) whether any additional costs may be incurred in order to provide such transmission service or to accommodate an Interconnection Request, and (iii) with respect to an Interconnection Request, an estimated date that an Interconnection Customer’s Customer Facility can be interconnected with the Transmission System and an estimate of the Interconnection Customer’s cost responsibility for the interconnection; and (iv) with respect to an Upgrade Request, the estimated cost of the requested system upgrades or expansion, or of the cost of the system upgrades or expansion, necessary to provide the requested incremental rights. System Protection Facilities: “System Protection Facilities” shall refer to the equipment required to protect (i) the Transmission System, other delivery systems and/or other generating systems connected to the Transmission System from faults or other electrical disturbance occurring at or on the Customer Facility, and (ii) the Customer Facility from faults or other electrical system disturbance occurring on the Transmission System or on other delivery systems and/or other generating systems to which the Transmission System is directly or indirectly connected. System Protection Facilities shall include such protective and regulating devices as are identified in the Applicable Technical Requirements and Standards or that are required by Applicable Laws and Regulations or other Applicable Standards, or as are otherwise necessary to protect personnel and equipment and to minimize deleterious effects to the Transmission System arising from the Customer Facility. Transmission Facilities:

  • Scheduled Commercial Operation Date shall have the meaning ascribed to it in Clause 5.4.1;

  • Continuous Improvement Plan means a plan for improving the provision of the Goods and/or Services and/or reducing the Charges produced by the Supplier pursuant to Framework Schedule 12 (Continuous Improvement and Benchmarking);

  • Scheduled Outage has the meaning given to it in the Grid Code;

  • Service Outage means an instance when the Customer is unable to route traffic to one or more Customer Sites via the Network, which results in Service Downtime;

  • Unscheduled Outage means any outage that is not a “Scheduled Outage”. “Committed Time” shall mean, as to each Business Day, one hour before the trading session for that day is scheduled to open on the NYSE and one hour after the trading session on the NYSE for that day finally closes, but excluding the following periods of Scheduled Outage (defined below). A “Scheduled Outage” shall mean (1) those time periods from 12 AM Saturday to 6:00 AM Sunday each week and 11:00 PM to 12:00 AM daily, during which Computershare’s System maybe unavailable due to routine maintenance; and (2) any time period as to which Company has received prior notice. ≥99.5% <99.5% to ≥98% <98%

  • Unplanned Service Interruption means any Service Interruption where events or circumstances prevent the timely communication of prior warning or notice to the Trader or any affected Customer;

  • Excused Outage means any disruption to or unavailability of Services caused by or due to (i) Scheduled Maintenance,

  • Planned Downtime means planned downtime for upgrades and maintenance to the Services scheduled in advance of such upgrades and maintenance.

  • Excused Downtime means the number of minutes in the Charging Period, rounded to the nearest minute that the link state of Customer’s Port is ‘down’ due to:

  • Potential electrical output capacity means, with regard to a unit, 33 per- cent of the maximum design heat input of the unit.

  • Service Animal means an animal that is required by a person with a disability for assistance and is certified, in writing, as having been trained by a professional service animal institution to assist a person with a disability and which is properly harnessed in accordance with standards established by a professional service animal institution.

  • Forced Outage means any unplanned reduction or suspension of the electrical output from the Facility resulting in the unavailability of the Facility, in whole or in part, in response to a mechanical, electrical, or hydraulic control system trip or operator-initiated trip in response to an alarm or equipment malfunction and any other unavailability of the Facility for operation, in whole or in part, for maintenance or repair that is not a scheduled maintenance outage and not the result of Force Majeure.

  • Integrated Development Plan means a plan formulated and approved as envisaged in Section 25 of the Municipal Systems Act 2000, as amended.

  • Generator Maintenance Outage means the scheduled removal from service, in whole or in part, of a generating unit in order to perform necessary repairs on specific components of the facility, if removal of the facility meets the guidelines specified in the PJM Manuals.

  • Outages means the planned unavailability of transmission and/or generation facilities dispatched by PJM or the NYISO, as described in Section 35.9 of this Agreement.

  • Combined sewer system means a system for conveying both sanitary sewage and storm water runoff.

  • Interconnection Feasibility Study means either a Generation Interconnection Feasibility Study or Transmission Interconnection Feasibility Study.

  • Generation Service means the sale of electricity, including ancillary services such as the provision of reserves, to a Customer by a Competitive Supplier.