Examples of Job Order Time in a sentence
Job Order Time, except as modified by a Job Order Change Order, begins on the date Work is to begin on a Job Order Project according to the terms of the Job Order and ends on the date Work is to be completed on a Job Order Project according to the terms of the Job Order.
No extension of the Job Order Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.
Such additional information may include: .1 If Contractor seeks an adjustment of the Job Order Time, written documentation demonstrating Contractor's entitlement to a time extension under Article 8.4, which shall be submitted within 15 days of the date requested.
This provision shall not limit any right or remedy of University in the event of any other default of Contractor other than failing to complete the Job Order Work within the applicable Job Order Time.
The purpose of granting or acknowledging substantial completion is to stop Job Order Time.
University and Contractor agree that if the Job Order Work is not completed within the applicable Job Order Time, University's damages would be extremely difficult or impracticable to determine and that the below stated amounts are reasonable estimates of and reasonable sums for such damages.
If Contractor fails to complete any Job Order Work within the applicable Job Order Time, Contractor shall pay to University, as liquidated damages and not as a penalty, the applicable below-listed sum for each day after the expiration of the Job Order Time that the Job Order Work remains incomplete.
If the cause is determined not to have been within the control of Contractor, and the suspension has prevented Contractor from completing the Work within the Job Order Time, the suspension is an excusable delay and a time extension will be granted through a Change Order.
A written instrument issued after execution of a Job Order Amendment signed by City and JOC Contractor, stating their agreement upon all of the following: the scope of the change in Job Order; the amount of the adjustment to the Job Order Price; and the extent of the adjustment to the Job Order Time.
An extension of the Job Order Time shall be the sole remedy of Contractor for delays in performance of the Work, whether or not such delays are foreseeable, except for delays caused solely by acts of Owner that constitute intentional interference with Contractor’s performance of the Work and then only to the extent such acts continue after Contractor notifies Owner in writing of such interference.