Examples of Joint Meter Reading in a sentence
The SOLAR POWER GENERATOR shall be required to give an advance notice of at least 90 days prior to the proposed commissioning date.xi) Joint Meter Reading (JMR) shall be taken at Delivery Point and Pooling Substation (if applicable)/plant premise at the time of connectivity of the Project with Grid.
Joint Meter Reading (JMR) shall be taken at Delivery Point and Pooling Substation (if applicable)/plant premise at the time of connectivity of the Project with Grid.
The POWER PRODUCER shall be required to give an advance notice of at least 90 days prior to the proposed commissioning date.xi) Joint Meter Reading (JMR) shall be taken at Delivery Point and Pooling Substation (if applicable)/plant premise at the time of connectivity of the Project with Grid.
However, in case the Joint meter reading report is not signed in the first three business days of any month due to non- availability of the Purchaser's authorized representative, the report signed by the Power Producer shall be considered as Joint Meter Reading Report.
The SOLAR POWER PRODUCER shall be required to give an advance notice of at least 90 days prior to the proposed commissioning date.xi) Joint Meter Reading (JMR) shall be taken at Delivery Point and Pooling Substation (ifapplicable)/plant premise at the time of connectivity of the Project with Grid.
Joint Meter Reading (JMR) shall be taken at Delivery Point at the time of connectivity of the Project with Grid.
However, in case the Joint meter reading report is not signed in the first seven business days of any month due to non-availability of the Purchaser's authorized representative, the report signed by the Supplier shall be considered as Joint Meter Reading Report.
Joint Meter Reading (JMR) shall be taken at Delivery Point and Pooling Substation (if applicable)/plant premise on the date of site visit by the commissioning committee.
BILLING PROCEDURE AND PAYMENTS5.1 The Generating Company shall raise monthly bill, based on the monthly Joint Meter Reading with help of MRI of the Bill Meter installed at interconnection point along with the detailed MRI Report of the Meter at the time of reading and Load Survey data of previous 35 days.
MRI Document of the Bill Meter shall be taken at the time of the Joint Meter Reading.