Examples of New Service Request in a sentence
As used in the Interconnection Service Agreement or Construction Service Agreement, Facilities Study shall mean that certain Facilities Study conducted by Transmission Provider (or at its direction) to determine the design and specification of the Interconnection Facilities necessary to accommodate the New Service Customer’s New Service Request in accordance with Section 207 of Part VI of the Tariff.
The fuel type specified in the New Service Request may not be changed or modified in any way for any reason, except that for New Service Requests that involve multiple fuel types, removal of a fuel type through these reduction rules will not constitute a fuel type change.
The method for identifying Contingent Facilities shall be sufficiently transparent to determine why a specific Contingent Facility was identified and how it relates to the New Service Request.
Transmission Provider, in consultation with the affected Transmission Owner(s), will conduct System Impact Studies, in three phases, to provide Applicant with information on the required Interconnection Facilities and Network Upgrades needed to support Applicant’s New Service Request.
Transmission Provider shall identify the Contingent Facilities in the System Impact Studies by reviewing unbuilt Interconnection Facilities and/or Network Upgrades, upon which the New Service Request’s cost, timing and study findings are dependent and, if delayed or not built, could cause a need for interconnection restudies of the New Service Request or reassessment of the Network Upgrades.
At the conclusion of Transmission Provider’s deficiency review for Decision Point II, refund to the Project Developer or Eligible Customer up to 90 percent of its Study Deposit submitted with its New Service Request during the Application Phase, less any actual costs.
Before the close of Decision Point II, Project Developer or Eligible Customer shall choose either to remain in the Cycle subject to the terms set forth below, or to withdraw its New Service Request.
Before the close of the Decision Point I, Project Developer or Eligible Customer shall choose either to remain in the Cycle subject to the terms set forth below, or to withdraw its New Service Request.
Transmission Provider shall include the list of the Contingent Facilities in the System Impact Study(ies) and Generator Interconnection Agreement, including why a specific Contingent Facility was identified and how it relates to the New Service Request.
The Facilities Study shall include the cost and scheduled completion date for such modifications, that will be required to provide the requested transmission service or to accommodate an Interconnection Request or Upgradea New Service Request.