Project Cost Schedule definition

Project Cost Schedule means an itemized schedule in the form of SCHEDULE 1 to the Disbursement Request.
Project Cost Schedule means an itemized schedule in the form attached as Schedule 1 to Exhibit D-2 hereto.
Project Cost Schedule shall have the meaning ascribed to such term in Section 7.01.

Examples of Project Cost Schedule in a sentence

  • In these cases a copy of the State Audit as well as the Project Cost Schedule and Source and Application Schedule must be submitted.

  • In these cases, a copy of the State Audit as well as the Project Cost Schedule and Source and Application Schedule must be submitted.

  • GENERAL OPERATING CHARGES0.430.350.790.080.070.1545-Total BASELINE COSTS73.54110.39183.939.2213.8323.0560100Physical Contingencies4.548.2012.740.571.031.60647Price Contingencies6.053.449.490.760.431.19365Total PROJECT COSTS84.13122.03 206.1710.5415.2925.8359112 Table 2.5: Summary Project Cost Schedule by Components (US$ Million) COMPONENTS20142015201620172018TotalA.

  • The Borrower will proceed diligently to acquire, construct and/or and equip the Project, in accordance with the Project Cost Schedule and the Plans, without delay.

  • With respect to any Project which is impacted by a Seller Event of Default, a cost increase for such Project over the amount set forth for such Project on the Project Cost Schedule and equal to or greater than $0.28 per watt as a direct result of the applicable Seller Event of Default.

  • In April 2018, the FTA advised MTACC to incorporate its current updates and then commence with a subsequent revision that addresses any changes resulting from the MTACC Six-Point Plan for ESA.The updates of the Project, Cost, Schedule, Risk Management, Contract Packaging, and Technical Capacity and Capability Plans will document the changes called for by the incorporation of the MTACC Six-Point Plan for ESA to reduce future programmatic risks.

  • Any Project costs incurred in excess of the budgeted amounts set forth in the Project Cost Schedule will be paid for by the Borrower upon demand of the Bank.

  • For this facility, procurement activities continue with a number of key facility components received on site, including the wet electrostatic precipitator and the canister decontamination equipment.WTP Project Cost, Schedule, and Baseline Revisions On December 22, 2006, the Department’s Secretarial Acquisition Executive approved a revised baseline at a cost of $12.26 billion, and the project has already been appropriated $3.64 billion for design and construction.

  • This Contingency Fund shall increase to the extent any actual costs not payable under the Design Build Agreement are less than those anticipated under the Project Cost Schedule.

  • WORKS Table 2.5: Summary Project Cost Schedule by Components (UA ‘000) COMPONENTS Table 2.6 Source of Finance by Category of Expenditure (UA ‘000) Expenditure Category ADF Loan GoG TotalADF: TotalExpenditure (%)I.


More Definitions of Project Cost Schedule

Project Cost Schedule. The Project Cost Schedule reflects a total Project Cost of Thirteen Million Eight Hundred Ninety-Nine Thousand Two Hundred Seventy-Seven and No/100ths Dollars ($13,899,277.00). The Project Cost Schedule includes Special Tenant Improvement Allowances totaling Five Hundred Seventy-Two Thousand One Hundred Ninety-Four and No/100ths Dollars ($572,194.00) for Exterior Modifications (representing $338,631.00) and Atrium/Interior Modifications (representing $233,563.00) as shown on the Budget Reconciliation attached to the Project Cost Schedule; the sum of One Million Eight Hundred Forty-Four Thousand Five Hundred and No/100ths ($1,844,500.00) as the "Tenant Improvement Allowance" (at $20.00 per square foot for 92,225 square feet) for design and installation of the interior improvements ("Tenant Improvements"); and an additional sum of Seventy Thousand and No/100ths Dollars ($70,000.00) for lobby enhancement. The Exterior Modifications and Atrium/Interior Modifications are incorporated into the Conceptual Plans and Specifications. The Exterior Modifications, the Atrium/Interior Modifications, the Building expansion to 92,225 square feet, the increased Building elevation, the Architectural Precast Upgrade, as defined below, and the net increase in soft costs and construction interest result in an aggregate increase of $1,210,687 to the Project budget. This increase will be funded as follows: (i) $436,963 - funded by Base Rent; $175,000 - paid by Landlord; $ 70,000 - lobby enhancement allowance -------- provided by Landlord $681,963 Total

Related to Project Cost Schedule

  • Original Project Cost means the capital expenditure incurred by the Generating Company or the Transmission Licensee, as the case may be, within the original scope of the project up to the cut-off date as admitted by the Commission;

  • Project Cost means the price payable to Service Provider over the entire period of Agreement (i.e. Rs. <in words>) for the full and proper performance of its contractual obligations.

  • The Contract Price/Project Cost means the price payable to the Vendor under the Contract for the full and proper performance of its contractual obligations.

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.

  • Total Contract Price/Project Cost/TCO means the price payable to Service Provider over the entire period of Contract for the full and proper performance of its contractual obligations.

  • Estimated Project Cost means Benchmark cost of MNRE which is Rs 8.00 Crore/MWp as per MNRE letter no. 03/20/2014-15/GCRT/11.12.14 at the time of Bid Due date.

  • Project Costs means the costs of the construction, acquisition or equipping of the Project, as further described in the Project Budget, and such other costs as may be approved in writing by the Department, provided such costs are permitted by the Act.

  • Project Budget means the budget and project description included in the grant application. The Project Budget must succinctly describe all major elements of project work, the estimated cost of each, and clearly allocate requested grant funding and match contributions to each.

  • Approved Project Budget means the most recent statement, approved by the FTA, of the costs of the Project, the maximum amount of Federal assistance for which the TJPA is currently eligible, the specific tasks (including specified contingencies) covered, and the estimated cost of each task.

  • The Contract Price/ Project Cost means the price payable to the Vendor under the Contract for the full and proper performance of its contractual obligations.

  • Construction Budget means the fully-budgeted costs for the acquisition and construction of a given parcel of real property (including, without limitation, the cost of acquiring such parcel of real property, reserves for construction interest and operating deficits, tenant improvements, leasing commissions, and infrastructure costs) as reasonably determined by the Parent in good faith.

  • BASE budget means the minimum general fund budget of a district, which includes 80% of the basic

  • Total Contract Price/Project Cost/TCO means the price payable to Service Provider over the entire period of Contract for the full and proper performance of its contractual obligations.

  • Total Project Cost means all the funds to complete the effort proposed by the Applicant, including DOE funds (including direct funding of any FFRDC) plus all other funds that will be committed by the Applicant as Cost Sharing.

  • Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;

  • Total Project Costs means (a) the costs paid or incurred or to be paid or incurred by a Borrower Related Party in connection with or incidental to the acquisition, design, construction and equipping of the Project, including legal, administrative, engineering, planning, design, insurance, and costs of issuance; (b) amounts, if any, required by the Indenture Documents or the TIFIA Loan Documents to be paid into any fund or account upon the incurrence of the TIFIA Loan or any Secured Obligations; (c) payments when due (whether at the maturity of principal, the due date of interest, or upon optional or mandatory prepayment) during the Construction Period in respect of any indebtedness of the Borrower or any Credit Enhancement maintained by a Borrower Related Party, in each case in connection with the Project (other than the TIFIA Loan); and (d) costs of equipment and supplies and initial working capital and reserves required by the Borrower Related Parties for the commencement of operation of the Project, including general administrative expenses and overhead of the Borrower.

  • Baseline Schedule means the initial time schedule prepared by Contractor for Owner’s information and acceptance that conveys Contractor’s and Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by A/E and ODR), durations, and sequence of work related to the entire Project to the extent required by the Contract Documents. The schedule clearly demonstrates the critical path of activities, durations and necessary predecessor conditions that drive the end date of the schedule. The Baseline Schedule shall not exceed the time limit current under the Contract Documents.

  • Construction Schedule means a construction schedule indicating the planned start and completion dates of the major activities of the Work as set out in Appendix [ ], a future Appendix;

  • Eligible Project Costs means such portion of the Project costs disbursed and loaned from the OPWC to the Recipient for the sole and express purpose of acquiring, constructing, reconstructing, expanding, improving, engineering and equipping the Project, other direct expenses, and related financing costs thereto.

  • Qualified Project Costs means costs paid with respect to the Project that meet each of the following requirements: (i) the costs are properly chargeable to capital account (or would be a so chargeable with a proper election by the Borrower or but for a proper election by the Borrower to deduct such costs) in accordance with general federal income tax principles and in accordance with Section 1.103-8(a)(1) of the Regulations, provided, however, that only such portion of the interest accrued during rehabilitation or construction of the Project (in the case of rehabilitation, with respect to vacated units only) shall be eligible to be a Qualified Project Cost as bears the same ratio to all such interest as the Qualified Project Costs bear to all costs of the acquisition and construction or rehabilitation of the Project; and provided further that interest accruing after the Completion Date (as defined in the Regulatory Agreement) shall not be a Qualified Project Cost; and provided still further that if any portion of the Project is being constructed or rehabilitated by an Affiliate (whether as general contractor or a subcontractor), Qualified Project Costs shall include only (A) the actual out of pocket costs incurred by such affiliate in constructing or rehabilitating the Project (or any portion thereof) and (B) any overhead expenses incurred by such affiliate which are directly attributable to the work performed on the Project, and shall not include, for example, intercompany profits resulting from members of an “affiliated group” (within the meaning of Section 1504 of the Code) participating in the rehabilitation or construction of the Project or payments received by such affiliate due to early completion of the Project (or any portion thereof); (ii) the costs are paid with respect to a qualified residential rental project or projects within the meaning of Section 142(d) of the Code, (iii) the costs are paid after the earlier of 60 days prior to May 20, 2021, being the date on which the Governmental Lender first declared its “official intent” to reimburse costs paid with respect to the Project (within the meaning of Section 1.150-2 of the Regulations) or the date of issue of the Funding Loan, and (iv) if the costs of the acquisition and construction or rehabilitation of the Project were previously paid and are to be reimbursed with proceeds of the Funding Loan such costs were (A) “preliminary expenditures” (within the meaning of Section 1.150-2(f)(2) of the Regulations) with respect to the Project (such as architectural, engineering and soil testing services) incurred before commencement of acquisition and construction or rehabilitation of the Project that do not exceed 20% of the issue price of the Funding Loan (as defined in Section 1.148-1 of the Regulations), or (B) were capital expenditures with respect to the Project that are reimbursed no later than 18 months after the later of the date the expenditure was paid or the date the Project is placed in service (but no later than three years after the expenditures is paid); provided, however, that (w) Costs of Funding shall not be deemed to be Qualified Project Costs;(x) fees, charges or profits (including, without limitation, any Developer Fee) payable to the Borrower or a “related person” (within the meaning of Section 144(a)(3) of the Code) shall not be deemed to be Qualified Project Costs; (y) letter of credit fees and municipal bond insurance premiums which represent a transfer of credit risk shall be allocated between Qualified Project Costs and other costs and expenses to be paid from the proceeds of the Funding Loan; and (z) letter of credit fees and municipal bond insurance premiums which do not represent a transfer of credit risk (including, without limitation, letter of credit fees payable to a “related person” to the Borrower) shall not constitute Qualified Project Costs.

  • Development Schedule shall have the meaning set forth in Section 1.1.

  • Project area budget means a multiyear projection of annual or cumulative

  • Project Year means the twelve-month period beginning from the Effective Date and ending twelve months thereafter (the First Project Year), and any twelve-month period beginning at the end of the First Project Year, or the end of subsequent Project Years;

  • Construction project means the same as that term is defined in Section 38-1a-102.

  • Project Expenses means usual and customary operating and financial costs. The term does not include extraordinary capital expenses, development fees and other non-operating expenses.

  • Estimated Construction Cost or “ECC” means the amount calculated by Contractor for the total cost of all elements of the Work based on this Agreement available at the time(s) that the ECC is prepared. The ECC shall be based on current market rates with reasonable allowance for overhead, profit and price escalation and shall include and consider, without limitation, all alternates and contingencies, designed and specified by A/E and the cost of labor and materials necessary for installation of Owner furnished equipment. The ECC shall include all the cost elements included in the AACC, as defined above, and shall represent Contractor’s best current estimate of the Guaranteed Maximum Price it will propose for the Project based on the information then available. The ECC shall not include Contractor’s Pre-Construction Phase Fee, A/E’s Fees, the cost of the land and rights-of-way, or any other costs that are the direct responsibility of Owner.