Site Start Date definition

Site Start Date means the date on which the Developer will commence development of the Site, including the Developer Works (which is typically the date on which the foundations for any works on the Site commence);
Site Start Date means the relevant date as shown in the Construction Programme on which the Contractor shall commence the Works for each of the Project Facilities;

Examples of Site Start Date in a sentence

  • On receipt of the completed Information Request Sheet, BT shall use its reasonable endeavours to provide the Developer with the Specification for the Site on or before the Site Start Date and in accordance with the Developer’s Guide.

  • The Developer will complete and return the Information Request Sheet no later than 4 weeks before the Site Start Date.

  • On/Off Campus, New Site, Start Date, International, Distance Ed, Language The University of Hawaiʻi at Hilo (UH Hilo) has been approved by the University of Hawaiʻi Board of Regents to initiate a Bachelor of Science Degree in Aeronautical Sciences.

  • Any changes to the number of Premises, First Occupancy Date or Site Start Date may require a new Connectivity Assessment and BT reserves the right to amend the Developer Contribution Charge in line with any changes notified to them or of which they become aware.

  • Norwegian and Hebrew versions of the software will be delivered after Site Start Date.

  • Without limiting the foregoing, Grand Virtual agrees to provide Licensee with the Software in English plus translated and useable versions in French, German, Italian, Spanish, Dutch, Danish, Greek, Swedish, Portuguese, Japanese, traditional Chinese, simplified Chinese, and Korean on or before the Site Start Date, and at no additional charge or cost.

  • CONSTRUCTION TIMEFRAME: Once allapprovals, permits and finances are confirmed and land settlement has been received, you will be ready to be transferred to our Construction Team where you will be advised of your Site Start Date by your Client Liaison Coordinator.

  • Therefore, another task in the near future is to authorize somebody else, may be one of the staffs or one within the family, to handle either production matters or managerial matters.

  • Site Start Date: the first day of your program.2. Site End Date: the last day of your program.

  • Information in the site occupancy summary section includes:Address, Location/Site Code, AHCCCS ID, District, County, Site Start Date and End Date which auto populate from vendor data in the QVADS.DDD Funded Count is auto populated using member authorizations to sites or the approved schedule.

Related to Site Start Date

  • Project Start Date means the first Milestone Start Date specified in Schedule B;

  • Start Date for Term Calculation Purposes Only: Regardless of actual award/effective date of Contract, for Agreement “term” calculation purposes only, the Agreement “start date” is the last day of the month that Award Notifications are anticipated as published in the Solicitation. Example: If the anticipated award date published in the Solicitation is August 27, 2020 but extended negotiations delay award until September 24, 2020 the end date of the resulting initial “two-year” term Agreement, (which is subject to an extension(s)) will still be August 31, 2022 in this example

  • Construction Completion Date means the Completion Date of the Construction as specified in the Statutory Declaration of Completion for the Project;

  • Contract Start Date means the date specified in your Contract for Signature as the date this Contract starts;

  • Supply Start Date means the date(s) specified in clause 2.8;

  • Service Commencement Date means the date the Transmission Provider begins to provide service pursuant to the terms of an executed Service Agreement, or the date the Transmission Provider begins to provide service in accordance with Tariff, Part II, section 15.3 or Tariff, Part III, section 29.1.

  • Billing Commencement Date means the earlier of:

  • Construction Start Date means the later to occur of the date on which Seller delivers to Buyer (a) a copy of the Notice to Proceed that Seller has delivered to the EPC Contractor for the Project, and (b) a written Certification substantially in the form attached hereto as Appendix IV-1.

  • Construction Commencement Date means the date set out in the Addendum, if applicable, by which you must commence construction of the Hotel. For the Hotel to be considered under construction, youmust have begun to pour concrete foundations for the Hotel or otherwise satisfied any site-specific criteria for “under construction” set out in the Addendum.

  • Completion Date means the date of completion of the Services by the Service Provider as certified by the Procuring Entity

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • Base station means the station as set out in Part-II (SOQ) hereof where the vehicle(s) / equipment shall be permanently based, (i.e. based for minimum period of 10 (Ten) days at a stretch) which may be changed at the discretion of the Company.

  • Commencement Date means the date of this Agreement;

  • Project Commencement Date means the commencement date notified to the Minister pursuant to clause 4(1);

  • Framework Commencement Date means [insert date dd/mm/yyyy];

  • Initial Operation means the first integral operation of the complete equipment covered under the Contract with the sub-system and supporting equipment in service or available for service.

  • Lease Commencement Date means the Closing Date. The “Lease Expiration Date” shall mean the later of (i) the date of the final payment in full of the French Advances and (ii) the Vehicle Lease Expiration Date for the last Lease Vehicle leased by the Lessee hereunder. The “Term” of this Agreement shall mean the period commencing on the Lease Commencement Date and ending on the Lease Expiration Date.

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • Work space means that portion of the court’s facilities dedicated to each court reporter, including but not limited to actual space in the courtroom and any designated office space.

  • project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;

  • Service Start Date means the date on which services were first supplied under this Agreement.

  • Completion Period means the period starting from the date of issue of "Order" and required to complete the work in all respect.

  • Services Commencement Date means the date delivery of the Services shall commence as specified in the Key Provisions. If no date is specified in the Key Provisions this date shall be the Commencement Date;

  • Substantial Completion Date means the date on which Substantial Completion occurs.

  • Construction Completion means physical construction of a cleanup action component is complete.

  • Construction Period means the period commencing from the Appointed Date and ending on the date of the Completion Certificate;