Examples of Substantial Completion Deadline in a sentence
If TxDOT does not issue NTP3 on or before 547 days after issuance of NTP1, Developer shall complete the NTP3 Work by the Substantial Completion Deadline for Segment F-2.
If TxDOT does not issue NTP4 on or before 576 days after NTP1, Developer shall complete the NTP4 Work by the Substantial Completion Deadline for Segment G.
Should a Proposer propose meeting Substantial Completion for Segment A prior to 1500 days following NTP1, TxDOT will adjust the maximum payment curve as appropriate to allow full payment by the proposed Substantial Completion Deadline (but no earlier than 1100 days following NTP1), provided that the Form M-2 submitted by such Proposer shows Anticipated Draw/Cash Flow ending at the proposed Substantial Completion Deadline rather than continuing through 50 months after NTP1.
The Substantial Completion Date for the Project shall occur no later than the Long Stop Date, which is a date beyond the Substantial Completion Deadline to be set forth in the Contract Term Provision Documents.