Work Progress definition
Examples of Work Progress in a sentence
Contractor may revise the Work Progress Schedule when in Contractor’s judgment it becomes necessary for the management of the Work.
Owner has no duty to make progress payments unless accompanied by the updated Work Progress Schedule.
Contractor shall submit electronic and paper copy of the initial Work Progress Schedule reflecting accurate and reliable representations of the planned progress of the Work, the Work to date if any, and of Contractor’s actual plans for its completion.
Contractor shall provide with each Time Extension Request a quantitative demonstration of the impact of the delay on project completion time, based on the Work Progress Schedule.
Contactor shall include an estimate as to the date of scheduled progress recovery and an updated Work Progress Schedule illustrating Contractor’s plan for achieving timely completion of the Project.
The Contractor is responsible for providing Samples of sufficient size for test purposes and for coordinating such tests with the Work Progress Schedule to avoid delay.
Contractor’s submittal schedule must be consistent with the Work Progress Schedule and identify critical submittals.
The Owner has no duty to make progress payments unless accompanied by the updated Work Progress Schedule.
Unless indicated otherwise in those documents, Contractor shall submit to the ODR and the A/E its initial Work Progress Schedule for the Work in relation to the entire Project not later than twenty-one (21) days after the effective date of the Notice to Proceed.
Refer to requirements for the Work Progress Schedule for inclusion of procurement activities therein.