Clearance of Site. Following the issue of each of i) the Certificate of Substantial Completion and ii) the Certificate of Final Completion, the Contractor shall clear away and remove from Site all equipment, surplus materials, rubbish and temporary works of every kind which are not being used for the performance of the Contractor’s obligations under this Contract, and leave the Site in a clean and functional condition. If the Contractor fails to do so within twenty eight (28) days of the Certificate of Substantial Completion or the Certificate of Final Completion (as applicable), UNICEF may sell or otherwise dispose of any remaining items and the cost of doing so, less the sums received by UNICEF from any sale, shall be recoverable by UNICEF from the Contractor as a debt and/or deducted from any sums due to the Contractor under this Contract.