Close Out Submittals. Upon completion of its work, Subcontractor shall submit all “in place” or “as-built” drawings, owner’s manuals, operating manuals, labor and materials warranties, and any other close out documents required by the Contract Documents (collectively, the “Close Out Submittals”). Final Payment (defined herein) to Subcontractor (including any payments that may be otherwise due for Disputes (defined herein)) shall not be deemed due to Subcontractor until such time as Subcontractor has submitted all required Close Out Submittals.

Appears in 23 contracts

Samples: Subcontract Agreement, Subcontract Agreement, Subcontract Agreement

AutoNDA by SimpleDocs

Close Out Submittals. Upon completion of its work, Subcontractor shall submit all "in place" or "as-built" drawings, owner’s 's manuals, operating manuals, labor and materials warranties, and any other close out documents required by the Contract Documents (collectively, the "Close Out Submittals"). Final Payment (defined herein) to Subcontractor (including any payments that may be otherwise due for Disputes (defined herein)) shall not be deemed due to Subcontractor until such time as Subcontractor has submitted all required Close Out Submittals.

Appears in 5 contracts

Samples: Subcontract Agreement, Subcontract Agreement, Subcontract Agreement

Close Out Submittals. Upon completion of its work, Subcontractor shall submit all "in place" or “as-"as- built" drawings, owner’s 's manuals, operating manuals, labor and materials warranties, and any other close out documents required by the Contract Documents (collectively, the "Close Out Submittals"). Final Payment (defined herein) to Subcontractor (including any payments that may be otherwise due for Disputes (defined herein)) shall not be deemed due to Subcontractor until such time as Subcontractor has submitted all required Close Out Submittals.

Appears in 2 contracts

Samples: Subcontract Agreement, Subcontract Agreement

Close Out Submittals. Upon completion of its work, Subcontractor shall submit all “in place” or “as-built” drawings, owner’s manuals, operating manuals, labor and materials warranties, and any other close out documents required by the Contract Documents (collectively, the “Close Out Submittals”)Documents. Final Payment (defined herein) to Subcontractor (including any payments that may be otherwise due for Disputes (defined herein)Claims) shall not be deemed due to Subcontractor until such time as Subcontractor has submitted all required Close Out Submittals.

Appears in 2 contracts

Samples: Subcontract Agreement, Subcontract Agreement

AutoNDA by SimpleDocs

Close Out Submittals. Upon completion of its work, Subcontractor shall submit all “in place” or “as-built” drawings, owner’s manuals, operating manuals, labor and materials warranties, and any other close out documents required by the Contract Documents (collectively, the “Close Out Submittals”)Documents. Final Payment (defined herein) to Subcontractor (including any payments that may be otherwise due for Disputes (defined herein)Claims) shall not be deemed due to Subcontractor until such time as Subcontractor has submitted all required Close Close-Out Submittals.

Appears in 1 contract

Samples: Subcontract Agreement

Time is Money Join Law Insider Premium to draft better contracts faster.