Commissioning LNG Sample Clauses

Commissioning LNG. (a) Company shall provide LNG required for the Acceptance Tests (“Commissioning LNG”), and pay for such LNG (except the Testing Fuel Quantity), in accordance with the Delivery Protocol. (b) Owner shall use reasonable endeavours to assist Company in sourcing Commissioning LNG and delivering it to Lampung. (c) Owner shall pay for the Testing Fuel Quantity at the LNG Price, with payment of sums due under this Clause 6.10 to be made by deduction from sums due to Owner under Monthly Invoices.
AutoNDA by SimpleDocs

Related to Commissioning LNG

  • Commissioning Commissioning tests of the Interconnection Customer’s installed equipment shall be performed pursuant to applicable codes and standards. The ISO and Connecting Transmission Owner must be given at least five Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least fifteen (15) days written notice to the SLDC / ALDC / DISCOM as the case may be, of the date on which it intends to synchronize the Power Project to the Grid System. 4.1.2 Subject to Article 4.1.1, the Power Project may be synchronized by the Power Producer to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 4.1.3 The synchronization equipment and all necessary arrangements / equipment including Remote Terminal Unit (RTU) for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the Power Producer at its generation facility of the Power Project at its own cost. The Power Producer shall synchronize its system with the Grid System only after the approval of GETCO / SLDC / ALDC and GEDA. 4.1.4 The Power Producer shall immediately after each synchronization / tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. 4.1.5 The Power Producer shall commission the Project within SCOD. 4.1.6 The Power Producer shall be required to obtain Developer and/ or Transfer Permission, Key Plan drawing etc, if required, from GEDA. In cases of conversion of land from Agricultural to Non-Agriculture, the commissioning shall be taken up by GEDA only upon submission of N.A. permission by the Power Producer. 4.1.7 The Power Producer shall be required to follow the Forecasting and Scheduling procedures as per the Regulations issued by Hon’ble GERC from time to time. It is to clarify that in terms of GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019 the procedures for Forecasting, Scheduling & Deviation Settlment are applicable to all solar generators having combined installed capacity above 1 MW connected to the State Grid / Substation including those connected via pooling stations.

  • Construction Phase Services 3.1.1 – Basic Construction Services

  • Decommissioning (a) The Contractor shall submit to the Designated Authority, for its approval, pursuant to sub-paragraph 4.11(d)(v), a Decommissioning Plan for the Development Area and a schedule of provisions for the Decommissioning Costs Reserve. (b) The Decommissioning Plan shall be revised and resubmitted to the Designated Authority for its approval at such times as are reasonable having regard to the likelihood that the Decommissioning Plan (including cost estimates thereunder) may need to be revised. (c) The Contractor shall carry out the Decommissioning Plan substantially in accordance with its terms. (d) Estimates of the monies required for the funding of the Decommissioning Plan shall be charged as Recoverable Costs beginning in the Calendar Year following the Calendar Year in which Commercial Production first occurs. The amount charged in each Calendar Year shall be calculated as follows: (i) The total Decommissioning costs at the expected date of Decommissioning shall first be calculated. (ii) There shall be deducted from such total Decommissioning costs the additions made to the Decommissioning Costs Reserve made, and taken as Recoverable Costs, in all previous Calendar Years together with interest on such Recoverable Costs calculated to the approved date of Decommissioning at the actual or forecast rate of Uplift (whichever is applicable). (iii) The residual Decommissioning costs, resulting from the calculations under sub-paragraph 4.14(d)(i) and (ii), shall then be discounted to the Calendar Year in question at the forecast rate of Uplift for each Calendar Year remaining until the Calendar Year of Decommissioning. (iv) The discounted total of residual Decommissioning costs shall then be divided by the total number of Calendar Years remaining prior to the Calendar Year of Decommissioning itself, including the Calendar Year in question. (v) The resultant amount shall be the addition to the Decommissioning Costs Reserve for the Calendar Year in question. (vi) It is the intention of this provision that the total accumulated provision allowed, including interest calculated to the Calendar Year of Decommissioning at the rate of Uplift, will equal the total Decommissioning costs. (vii) If the amount in sub-paragraph 4.14(d)(v) is a negative amount, then such amount shall be treated as a reduction of Recoverable Costs for the Calendar Year in question.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:

  • Construction Completion The related Construction shall have been completed substantially in accordance with the related Plans and Specifications, the related Deed and all Applicable Laws, and such Leased Property shall be ready for occupancy and operation. All fixtures, equipment and other property contemplated under the Plans and Specifications to be incorporated into or installed in such Leased Property shall have been substantially incorporated or installed, free and clear of all Liens except for Permitted Liens.

  • Interconnection Facilities Engineering Procurement and Construction Interconnection Facilities, Network Upgrades, and Distribution Upgrades shall be studied, designed, and constructed pursuant to Good Utility Practice. Such studies, design and construction shall be based on the assumed accuracy and completeness of all technical information received by the Participating TO and the CAISO from the Interconnection Customer associated with interconnecting the Large Generating Facility.

  • Contract Closure Contracting Officer shall give appropriate written notice to Purchaser when Purchaser has complied with the terms of this contract. Purchaser shall be paid refunds due from Timber Sale Account un- der B4.24 and excess cooperative deposits under B4.218.

  • PRE-CONSTRUCTION PHASE SERVICES The Pre-Construction Phase shall be deemed to commence upon the date specified in a written Notice to Proceed with Pre-Construction Phase Services issued by Owner and shall continue through completion of the Construction Documents and procurement of all major Subcontractor agreements. Contractor is not entitled to reimbursement for any costs incurred for Pre-Construction Phase Services performed before issuance of the written Notice to Proceed. Pre-Construction Phase Services may overlap Construction Phase Services. Contractor shall perform the following Pre-Construction Phase Services:

  • Project Completion Report At the completion of construction and once a Project is placed in service, the Subrecipient must submit a Project Completion Report that includes the total number of units built and leased, affordable units built and leased, DR-MHP units built and leased, an accomplishment narrative, and the tenants names, demographics and income for each DR-MHP unit.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!