DAMAGES FOR DELAY IN COMPLETION Sample Clauses

DAMAGES FOR DELAY IN COMPLETION. 29.1 If Completion does not occur by the Date for Completion, due to the default of either Party, the Party who is at fault must pay the other Party as liquidated damages on Completion: (a) interest on the Price at the rate of 10% per annum calculated on a daily basis from the date 7 days after the Date for Completion to Completion (inclusive); and (b) the amount of $660.00 (including GST) to be applied towards any legal costs and disbursements incurred by the Party not at default if Completion occurs later than 7 days after the Date for Completion. 29.2 The Party at fault must pay the amount specified in clause 29.1 in addition to any other damages to which the Party not at fault is entitled both at law and under this Contract. 29.3 The Parties agree that: (a) the amount of any damages payable under clause 29.1(a) to the Party not in default is a genuine and honest pre-estimate of loss to that Party for the delay in Completion; and (b) the damages must be paid on Completion.
AutoNDA by SimpleDocs
DAMAGES FOR DELAY IN COMPLETION. 30.1 If Completion does not occur by the Date for Completion, due to the default of either party, the party who is at fault must pay the other party as liquidated damages on Completion: (a) interest on the Price at the rate of 10% per annum calculated on a daily basis from the Date for Completion to Completion; and (b) the amount of $660 (including GST) to be applied towards any legal costs and disbursements incurred by the party not at default if Completion occurs later than 5 Working Days after the Date for Completion. 30.2 The party at fault must pay the amount specified in clause 30.1 in addition to any other damages to which the party not at fault is entitled both at law and under this Contract. 30.3 The parties agree that: (a) the amount of any damages payable under clauses 30.1(a) to the party not in default is a genuine and honest pre-estimate of loss to that party for the delay in Completion, and (b) the damages must be paid on Completion.
DAMAGES FOR DELAY IN COMPLETION. 43.1 If the Contractor fails to complete the Works by the date for practical completion stated in the appendix to these conditions, or within any extended time fixed under clause 36.0 of these conditions, and the Architect certifies in writing that in his opinion the same ought reasonably so to have been completed, then the Contractor shall pay or allow to the Employer a sum calculated at the rate stated in the said appendix as liquidated damages for the period during which the Works shall so remain or have remained incomplete, and the Employer may deduct such sum from any money due or to become due to the Contractor under the contract or recover the same from the Contractor as a debt. 43.2 The payment or deduction of such damages shall not relieve the Contractor from his obligations to complete the Works or any part thereof or from any other obligations and liabilities under the contract.
DAMAGES FOR DELAY IN COMPLETION. 23.1 If Completion does not occur by the Date for Completion, due to the default of the Buyer, then the Buyer must pay the Seller as liquidated damages on Completion: (a) interest on the unpaid balance of the Price at the rate of 10% per annum calculated on a daily basis from the Date for Completion to Completion; and (b) the amount of $1,100 (GST inclusive) to be applied towards any legal costs and disbursements incurred by the Seller if Completion occurs later than 5 Working Days after the Date for Completion. 23.2 The Buyer agrees that: (a) the amount of any damages payable under clause 23.1 to the Seller is a genuine and honest pre-estimate of loss to that party for the delay in Completion; and (b) the damages must be paid on Completion.
DAMAGES FOR DELAY IN COMPLETION. If the Work is uncompleted after the Contract Time, including all extensions and adjustments in accordance with General Provisions Section 80-07 “Determination and Extension of Contract Time”, the sum stipulated in General Provisions Section 80-08 “Failure to Complete on Time” will be deducted from any money due or to become due the Contractor or their surety. Such deducted sums shall not be deducted as a penalty but shall be considered as liquidation of a reasonable portion of damages including but not limited to additional engineering services that will be incurred by the Owner should the Contractor fail to complete the work in the Contract Time provided in this Contract.
DAMAGES FOR DELAY IN COMPLETION. A. Liquidated Damages for Delay (Not Used) B. COUNTY's Rights Cumulative C. Waiver of Liquidated Damages (Not Used)
DAMAGES FOR DELAY IN COMPLETION. 27.1 If the Sub-Contractor fails to complete the sub-contract works by the date for practical completion stated in the appendix to these conditions or within any extended time fixed under clause 25.0 herein, and the Architect certifies in writing that in his opinion the same ought reasonably so to have been completed, then the Sub-Contractor shall pay or allow to the Contractor a sum calculated at the rate stated in the said appendix as liquidated damages for the period during which the works shall so remain or have remained incomplete. 27.2 The Contractor may deduct such sum from any money due or to become due to the Sub-Contractor under the sub-contract or recover the same from the Sub-Contractor as a debt. Provided that the Contractor shall not be entitled to recover any liquidated damages from the Sub- Contractor without first obtaining the Architect‟s certificate of delay prescribed herein.
AutoNDA by SimpleDocs
DAMAGES FOR DELAY IN COMPLETION. 16.1 If Completion does not occur on or before the Date for Completion, due to the default of the Buyer, the Buyer must pay to the Seller as liquidated damages on Completion: (a) interest on the Price at the rate of 10% per annum calculated on a daily basis from the Date for Completion to Completion; and (b) the sum of $550.00 (including GST) to be applied towards any additional legal costs and disbursements incurred by the party not at fault if Completion occurs later than 7 days after the Date for Completion. 16.2 The Buyer must pay the sum specified in clause 16.1(b) in addition to any other damages to which the Seller is entitled both at law and under this Contract. 16.3 The Buyer agrees that: (a) the amount of any damages payable pursuant to clauses 16.1 to the Seller is a genuine and honest pre-estimate of loss to the Seller for the delay in completion; and (b) the damages will be paid on Completion. 16.4 This clause is an essential term of this Contract.

Related to DAMAGES FOR DELAY IN COMPLETION

  • Damages for delay Subject to the provisions of Clause 12.4, if COD does not occur prior to the 91st day after the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Performance Security for delay of each day until COD is achieved.

  • Liquidated Damages for Delay In addition to the Contractor bearing the actual cost of correcting any non-compliant work or any other actual damages resulting from Contractor’s breach of this Agreement, the Contractor agrees to pay the Contractor delay damages in the amount of $500.00 per day for every day that the goods and/or services to be provided pursuant to this Agreement have not been timely delivered to the District in compliance with the Scope of Services set forth above, unless the delay has been properly excused by the terms of this Agreement. The parties agree that the District’s actual damages for delay are difficult to estimate and that this $500.00 per day sum is a reasonable pre-estimate of the District’s actual damages for each day of delay and that the is $500.00 per day sum is intended by the parties to be in the nature of liquidated damages, not a penalty. It is not the parties’ intent for this provision to limit either party’s remedies against the other for the breach of this Agreement, except for the District’s money damages for unexcused delays caused by the Contractor.

  • No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.

  • Force Majeure, Notice of Delay, and No Damages for Delay The Contractor will not be responsible for delay resulting from its failure to perform if neither the fault nor the negligence of the Contractor or its employees or agents contributed to the delay and the delay is due directly to acts of God, wars, acts of public enemies, strikes, fires, floods, or other similar cause wholly beyond the Contractor’s control, or for any of the foregoing that affect subcontractors or suppliers if no alternate source of supply is available to the Contractor. In case of any delay the Contractor believes is excusable, the Contractor will notify the Department or Customer in writing of the delay or potential delay and describe the cause of the delay either (1) within 10 days after the cause that creates or will create the delay first arose, if the Contractor could reasonably foresee that a delay could occur as a result, or (2) if delay is not reasonably foreseeable, within five days after the date the Contractor first had reason to believe that a delay could result. The foregoing will constitute the Contractor’s sole remedy or excuse with respect to delay. Providing notice in strict accordance with this paragraph is a condition precedent to such remedy. No claim for damages will be asserted by the Contractor. The Contractor will not be entitled to an increase in the Contract price or payment of any kind from the Department or Customer for direct, indirect, consequential, impact or other costs, expenses or damages, including but not limited to costs of acceleration or inefficiency, arising because of delay, disruption, interference, or hindrance from any cause whatsoever. If performance is suspended or delayed, in whole or in part, due to any of the causes described in this paragraph, after the causes have ceased to exist the Contractor will perform at no increased cost, unless the Department or Customer determines, in its sole discretion, that the delay will significantly impair the value of the Contract to the State of Florida or to Customers, in which case the Department or Customer may (1) accept allocated performance or deliveries from the Contractor, provided that the Contractor grants preferential treatment to Customers with respect to commodities or contractual services subjected to allocation, or (2) purchase from other sources (without recourse to and by the Contractor for the related costs and expenses) to replace all or part of the commodity or contractual services that are the subject of the delay, which purchases may be deducted from the Contract quantity, or (3) terminate the Contract in whole or in part.

  • Effect of Failure or Delay in Requesting Compensation Failure or delay on the part of any Lender or the Issuing Bank to demand compensation pursuant to this Section 5.01 shall not constitute a waiver of such Lender’s or the Issuing Bank’s right to demand such compensation; provided that the Borrower shall not be required to compensate a Lender or the Issuing Bank pursuant to this Section 5.01 for any increased costs or reductions incurred more than 180 days prior to the date that such Lender or the Issuing Bank, as the case may be, notifies the Borrower of the Change in Law giving rise to such increased costs or reductions and of such Lender’s or the Issuing Bank’s intention to claim compensation therefor; provided further that, if the Change in Law giving rise to such increased costs or reductions is retroactive, then the 180-day period referred to above shall be extended to include the period of retroactive effect thereof.

  • Notice to Allow Conversion by Hxxxxx If (A) the Company shall declare a dividend (or any other distribution in whatever form) on the Common Stock, (B) the Company shall declare a special nonrecurring cash dividend on or a redemption of the Common Stock, (C) the Company shall authorize the granting to all holders of the Common Stock of rights or warrants to subscribe for or purchase any shares of capital stock of any class or of any rights, (D) the approval of any stockholders of the Company shall be required in connection with any reclassification of the Common Stock, any consolidation or merger to which the Company is a party, any sale or transfer of all or substantially all of the assets of the Company, or any compulsory share exchange whereby the Common Stock is converted into other securities, cash or property or (E) the Company shall authorize the voluntary or involuntary dissolution, liquidation or winding up of the affairs of the Company, then, in each case, the Company shall cause to be filed at each office or agency maintained for the purpose of conversion of this Debenture, and shall cause to be delivered to the Holder at its last address as it shall appear upon the Debenture Register, at least twenty (20) calendar days prior to the applicable record or effective date hereinafter specified, a notice stating (x) the date on which a record is to be taken for the purpose of such dividend, distribution, redemption, rights or warrants, or if a record is not to be taken, the date as of which the holders of the Common Stock of record to be entitled to such dividend, distributions, redemption, rights or warrants are to be determined or (y) the date on which such reclassification, consolidation, merger, sale, transfer or share exchange is expected to become effective or close, and the date as of which it is expected that holders of the Common Stock of record shall be entitled to exchange their shares of the Common Stock for securities, cash or other property deliverable upon such reclassification, consolidation, merger, sale, transfer or share exchange, provided that the failure to deliver such notice or any defect therein or in the delivery thereof shall not affect the validity of the corporate action required to be specified in such notice. To the extent that any notice provided hereunder constitutes, or contains, material, non-public information regarding the Company or any of the Subsidiaries, the Company shall simultaneously file such notice with the Commission pursuant to a Current Report on Form 8-K. The Holder shall remain entitled to convert this Debenture during the 20-day period commencing on the date of such notice through the effective date of the event triggering such notice except as may otherwise be expressly set forth herein.

  • Notice to Allow Conversion by Xxxxxx If (A) the Company shall declare a dividend (or any other distribution in whatever form) on the Common Stock, (B) the Company shall declare a special nonrecurring cash dividend on or a redemption of the Common Stock, (C) the Company shall authorize the granting to all holders of the Common Stock of rights or warrants to subscribe for or purchase any shares of capital stock of any class or of any rights, (D) the approval of any stockholders of the Company shall be required in connection with any reclassification of the Common Stock, any consolidation or merger to which the Company is a party, any sale or transfer of all or substantially all of the assets of the Company, or any compulsory share exchange whereby the Common Stock is converted into other securities, cash or property or (E) the Company shall authorize the voluntary or involuntary dissolution, liquidation or winding up of the affairs of the Company, then, in each case, the Company shall cause to be filed at each office or agency maintained for the purpose of conversion of this Note, and shall cause to be delivered to the Holder at its last address as it shall appear upon the Note Register, at least twenty (20) calendar days prior to the applicable record or effective date hereinafter specified, a notice stating (x) the date on which a record is to be taken for the purpose of such dividend, distribution, redemption, rights or warrants, or if a record is not to be taken, the date as of which the holders of the Common Stock of record to be entitled to such dividend, distributions, redemption, rights or warrants are to be determined or (y) the date on which such reclassification, consolidation, merger, sale, transfer or share exchange is expected to become effective or close, and the date as of which it is expected that holders of the Common Stock of record shall be entitled to exchange their shares of the Common Stock for securities, cash or other property deliverable upon such reclassification, consolidation, merger, sale, transfer or share exchange, provided that the failure to deliver such notice or any defect therein or in the delivery thereof shall not affect the validity of the corporate action required to be specified in such notice. To the extent that any notice provided hereunder constitutes, or contains, material, non-public information regarding the Company or any of the Subsidiaries, the Company shall simultaneously file such notice with the Commission pursuant to a Current Report on Form 8-K. The Holder shall remain entitled to convert this Note during the 20-day period commencing on the date of such notice through the effective date of the event triggering such notice except as may otherwise be expressly set forth herein.

  • Delay in Commencement Notwithstanding the Commencement Date, if for any reason Lessor cannot deliver possession of the Premises to Lessee on said date, Lessor shall not be subject to any liability therefor, nor shall such failure affect the validity of this Lease or the obligations of Lessee hereunder or extend the Term hereof, but in such case Lessee shall not be obligated to pay rent until possession of the Premises is tendered to Lessee; provided, however, that if Lessor shall not have delivered possession of the Premises within ninety (90) days from the Commencement Date and such delay is absent of force majeure or otherwise, Lessee may, at Lessee’s option, by notice in writing to Lessor within ten (10) days thereafter, cancel this Lease, in which event the parties shall be discharged from all obligations hereunder. If Lessee occupies the Premises prior to the Commencement Date, such occupancy shall be subject to all provisions hereof; such occupancy shall not advance the Expiration Date, and Lessee shall pay rent from its date of occupancy at the initial monthly rates set forth below. If Lessor, by reason of force majeure or otherwise, cannot deliver the Premises within ninety (90) days from the Commencement Date, Lessor or Lessee may, at their respective options, by notice in writing within ten (10) days thereafter, cancel this Lease. In the event Lessor is required to improve the Premises in the manner described on Exhibit “B” attached hereto (the “Lessor’s Work”), Lessor agrees to use reasonable diligence to have Lessor’s Work completed and the Premises ready for occupancy on or before the Commencement Date.

  • Compensation for Damages or Losses When investments by investors of either Contracting Party suffer damages or losses owing to war, armed conflict, a state of national emergency, revolt, insurrection, riot or other similar events in the territory of the other Contracting Party, they shall be accorded by the latter Contracting Party a treatment, as regards compensation or other settlement, not less favourable than that accorded to its own investors or to investors of any Third State.

  • NO LIMITATION OF LIABILITY FOR DAMAGES FOR PERSONAL INJURY OR PROPERTY DAMAGE ARE