Design-Builder’s Schedules. § 3.1.9.1 The Design-Builder, promptly after execution of this Agreement, shall prepare and submit for the Owner’s information a schedule for the Work. The schedule, including the time required for design and construction, shall not exceed time limits current under the Design-Build Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Design-Build Documents, shall provide for expeditious and practicable execution of the Work, and shall include allowances for periods of time required for the Owner’s review and for approval of submissions by authorities having jurisdiction over the Project.
Appears in 16 contracts
Samples: Agreement, Design Build Construction Agreement, Agreement
Design-Builder’s Schedules. § 3.1.9.1 The Design-Builder, promptly after within ten (10) calendar days of the execution of this Agreement, Contract shall prepare and submit for the Owner’s information a schedule for the WorkWork (“Project Schedule”). The scheduleProject Schedule, including the time required for design and construction, shall not exceed time limits current under the Design-Build Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Design-Build Documents, shall provide for expeditious and practicable execution of the Work, and shall include allowances for periods of time required for the Owner’s review and for approval acceptance of submissions by authorities having jurisdiction over the Project. Only with the Owner’s prior written acceptance, may the Design-Builder adjust the Project Schedule, if necessary, as the Project proceeds until the commencement of construction.
Appears in 1 contract
Samples: daniabeachfl.gov