Common use of Design-Builder’s Schedules Clause in Contracts

Design-Builder’s Schedules. § 3.1.9.1 The Design-Builder, promptly after execution of this Agreement, shall prepare and submit for the Owner’s information a schedule for the Work. The schedule, including the time required for design and construction, shall not exceed time limits current under the Design-Build Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Design-Build Documents, shall provide for expeditious and practicable execution of the Work, and shall include allowances for periods of time required for the Owner’s review and for approval of submissions by authorities having jurisdiction over the Project. § 3.1.9.2 The Design-Builder shall perform the Work in general accordance with the most recent schedules submitted to the Owner.

Appears in 12 contracts

Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder

AutoNDA by SimpleDocs

Design-Builder’s Schedules. § 3.1.9.1 The Design-Builder, promptly after within ten (10) calendar days of the execution of this Agreement, Contract shall prepare and submit for the Owner’s information a schedule for the WorkWork (“Project Schedule”). The scheduleProject Schedule, including the time required for design and construction, shall not exceed time limits current under the Design-Build Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Design-Build Documents, shall provide for expeditious and practicable execution of the Work, and shall include allowances for periods of time required for the Owner’s review and for approval acceptance of submissions by authorities having jurisdiction over the Project. § 3.1.9.2 The . Only with the Owner’s prior written acceptance, may the Design-Builder shall perform adjust the Work in general accordance with Project Schedule, if necessary, as the most recent schedules submitted to Project proceeds until the Ownercommencement of construction.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Design Builder

AutoNDA by SimpleDocs

Design-Builder’s Schedules. § 3.1.9.1 The Design-Builder, promptly after execution of this Agreement, shall prepare and submit for the Owner’s information a schedule for the Work. The schedule, including the time required for design and construction, shall not exceed time limits current under the Design-Build Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Design-Build Documents, shall provide for expeditious and practicable execution of the Work, and shall include allowances for periods of time required for the Owner’s review and for approval of submissions by authorities having jurisdiction over the Project. § 3.1.9.2 The Design-Builder shall perform the Work in general accordance with the most recent schedules submitted to the Owner.Owner.‌

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Design Builder