Effect of Continued Event of Force Majeure Sample Clauses

Effect of Continued Event of Force Majeure. Following the occurrence of a Force Majeure Event, Operator shall take all reasonable measures to mitigate or limit the amount of Operating Expenses until the effects of the Force Majeure Event are remedied. Operator shall consult with Owner with respect to its plans to mitigate or limit such Operating Expenses and shall take such actions as are reasonably directed by Owner. Owner shall continue to pay such reduced Operating Expenses as provided herein.
AutoNDA by SimpleDocs
Effect of Continued Event of Force Majeure. Following the occurrence of a Force Majeure Event, Operator shall take all reasonable measures to mitigate or limit the amount of Operating Expenses until the effects of the Force Majeure Event are remedied. Operator shall consult with Owner with respect to its plans to mitigate or limit such Operating Expenses and shall take such actions as are reasonably directed by Owner. Owner shall continue to pay such reduced Operating Expenses as provided herein. If Operator is prevented from performing its obligations hereunder, in whole or in part, by the occurrence of a Force Majeure Event (a) affecting the Operator and not affecting the Project and (ii) such Force Majeure Event continues for a one hundred eighty (180) day period, Owner may deliver to Operator a Termination Notice specifying a Termination Date thirty (30) days following the delivery of such Termination Notice.
Effect of Continued Event of Force Majeure. Notwithstanding ------------------------------------------- anything herein to the contrary, if an event of Force Majeure continues for a period of more than five (5) days, Operator shall take all reasonable measures to mitigate or limit Operator's costs incurred hereunder (including reducing its work force within permitted statutory time periods) for the duration of the Force Majeure event. Operator shall consult with Owner with respect to its plans to mitigate or limit such Costs and shall take such actions as are reasonably directed by Owner. Owner shall pay Operator the Costs incurred to provide the Services during the entire period of Force Majeure.

Related to Effect of Continued Event of Force Majeure

  • Event of Force Majeure The Recipient will not be in default by reason only of any failure in the performance of the Project in accordance with Schedule 1 – Statement of Work if such failure arises without the fault or negligence of the Recipient and is caused by any event of Force Majeure.

  • Effect of Force Majeure Event If either party to this contract cannot meet an obligation under this contract because of an event outside the control of that party (‘a force majeure event’): (a) the obligation, other than an obligation to pay money, is suspended to the extent it is affected by the force majeure event for as long as the force majeure event continues; and (b) the affected party must use its best endeavours to give the other party prompt notice of that fact including full particulars of the event, an estimate of its likely duration, the extent to which the affected party’s obligations are affected and the steps being taken to remove, overcome or minimise those effects.

  • Events of Force Majeure Neither Party shall be held liable or responsible to the other Party nor be deemed to be in default under, or in breach of any provision of, this Agreement for failure or delay in fulfilling or performing any obligation of this Agreement when such failure or delay is due to force majeure, and without the fault or negligence of the Party so failing or delaying. For purposes of this Agreement, force majeure is defined as causes beyond the control of the Party, including, without limitation, acts of God; acts, regulations, or laws of any government; war; civil commotion; destruction of production facilities or materials by fire, flood, earthquake, explosion or storm; labor disturbances; epidemic; and failure of public utilities or common carriers. In such event Medistem or Licensee, as the case may be, shall immediately notify the other Party of such inability and of the period for which such inability is expected to continue. The Party giving such notice shall thereupon be excused from such of its obligations under this Agreement as it is thereby disabled from performing for so long as it is so disabled and the 30 days thereafter. To the extent possible, each Party shall use reasonable efforts to minimize the duration of any force majeure.

  • Effect of Force Majeure If either Party is rendered wholly or partially unable to perform its obligations under this Agreement because of a Force Majeure Act, that Party shall be excused from whatever performance is affected by the Force Majeure Act to the extent so affected, provided that: a) Within five (5) Business Days after the occurrence of the inability to perform due to a Force Majeure Act, the Affected Party provides a written notice to the other Party of the particulars of the occurrence, including an estimation of its expected duration and probable impact on the performance of its obligations hereunder, and continues to furnish periodic reports with respect thereto, every seven (7) days, during the period of Force Majeure, b) The Affected Party shall use all reasonable efforts to continue to perform its obligations hereunder and to correct or cure as soon as possible the Force Majeure Act, c) The suspension of performance shall be of no greater scope and no longer duration than is reasonably necessitated by the Force Majeure Act, d) The Affected Party shall provide the other Party with prompt notice of the cessation of the Force Majeure Act giving rise to the excuse from performance and shall thereupon resume normal performance of obligations under this Agreement with utmost promptitude, e) The non-performance of any obligation of either Party that was required to be performed prior to the occurrence of a Force Majeure Act shall not be excused as a result of such subsequent Force Majeure Act, f) The occurrence of a Force Majeure Act shall not relieve either Party from its obligations to make any payment hereunder for performance rendered prior to the occurrence of Force Majeure Act or for partial performance hereunder during period of subsistence Force Majeure Act; and g) The Force Majeure Act, shall not relieve either Party from its obligation to comply with Applicable Laws. The Affected Party shall exercise all reasonable efforts to mitigate or limit damages to the other Party.

  • Notification of Force Majeure Event 11.5.1 The Affected Party shall give notice to the other Party of any event of Force Majeure as soon as reasonably practicable, but not later than seven (7) days after the date on which such Party knew or should reasonably have known of the commencement of the event of Force Majeure. If an event of Force Majeure results in a breakdown of communications rendering it unreasonable to give notice within the applicable time limit specified herein, then the Party claiming Force Majeure shall give such notice as soon as reasonably practicable after reinstatement of communications, but not later than one (1) day after such reinstatement. Provided that, such notice shall be a pre-condition to the Affected Party’s entitlement to claim relief under this Agreement. Such notice shall include full particulars of the event of Force Majeure, its effects on the Party claiming relief and the remedial measures proposed. The Affected Party shall give the other Party regular reports on the progress of those remedial measures and such other information as the other Party may reasonably request about the Force Majeure. 11.5.2 The Affected Party shall give notice to the other Party of (i) the cessation of the relevant event of Force Majeure; and (ii) the cessation of the effects of such event of Force Majeure on the performance of its rights or obligations/ roles under this Agreement, as soon as practicable after becoming aware of each of these cessations.

  • Duration of Force Majeure An Interconnection Party shall not be responsible, or considered to be in Breach or Default under this Interconnection Service Agreement, for any non-performance, any interruption or failure of service, deficiency in the quality or quantity of service, or any other failure to perform any obligation hereunder to the extent that such failure or deficiency is due to Force Majeure. An Interconnection Party shall be excused from whatever performance is affected only for the duration of the Force Majeure and while the Interconnection Party exercises Reasonable Efforts to alleviate such situation. As soon as the non-performing Interconnection Party is able to resume performance of its obligations excused because of the occurrence of Force Majeure, such Interconnection Party shall resume performance and give prompt notice thereof to the other parties.

  • Effect of Event of Default If any Event of Default described in Section 13.1.4 shall occur in respect of the Company, the Commitments shall immediately terminate and the Loans and all other Obligations hereunder shall become immediately due and payable and the Company shall become immediately obligated to Cash Collateralize all Letters of Credit, all without presentment, demand, protest or notice of any kind; and, if any other Event of Default shall occur and be continuing, the Administrative Agent may (and, upon the written request of the Required Lenders shall) declare the Commitments to be terminated in whole or in part and/or declare all or any part of the Loans and all other Obligations hereunder to be due and payable and/or demand that the Company immediately Cash Collateralize all or any Letters of Credit, whereupon the Commitments shall immediately terminate (or be reduced, as applicable) and/or the Loans and other Obligations hereunder shall become immediately due and payable (in whole or in part, as applicable) and/or the Company shall immediately become obligated to Cash Collateralize the Letters of Credit (all or any, as applicable), all without presentment, demand, protest or notice of any kind. The Administrative Agent shall promptly advise the Company of any such declaration, but failure to do so shall not impair the effect of such declaration. Any cash collateral delivered hereunder shall be held by the Administrative Agent (without liability for interest thereon) and applied to the Obligations arising in connection with any drawing under a Letter of Credit. After the expiration or termination of all Letters of Credit, such cash collateral shall be applied by the Administrative Agent to any remaining Obligations hereunder and any excess shall be delivered to the Company or as a court of competent jurisdiction may elect.

  • Definition of Force Majeure For the purposes of this section, an event of force majeure shall mean any cause beyond the control of the affected Interconnection Party or Construction Party, including but not restricted to, acts of God, flood, drought, earthquake, storm, fire, lightning, epidemic, war, riot, civil disturbance or disobedience, labor dispute, labor or material shortage, sabotage, acts of public enemy, explosions, orders, regulations or restrictions imposed by governmental, military, or lawfully established civilian authorities, which, in any of the foregoing cases, by exercise of due diligence such party could not reasonably have been expected to avoid, and which, by the exercise of due diligence, it has been unable to overcome. Force majeure does not include (i) a failure of performance that is due to an affected party’s own negligence or intentional wrongdoing; (ii) any removable or remediable causes (other than settlement of a strike or labor dispute) which an affected party fails to remove or remedy within a reasonable time; or (iii) economic hardship of an affected party.

  • EFFECT OF AN EVENT OF DEFAULT If any Event of Default shall occur, except where otherwise provided in this Agreement or the Related Documents, all commitments and obligations of Lender under this Agreement or the Related Documents or any other agreement immediately will terminate (including any obligation to make further Loan Advances or disbursements), and, at Lender's option, all Indebtedness immediately will become due and payable, all without notice of any kind to Borrower, except that in the case of an Event of Default of the type described in the "Insolvency" subsection above, such acceleration shall be automatic and not optional. In addition, Lender shall have all the rights and remedies provided in the Related Documents or available at law, in equity, or otherwise. Except as may be prohibited by applicable law, all of Lender's rights and remedies shall be cumulative and may be exercised singularly or concurrently. Election by Lender to pursue any remedy shall not exclude pursuit of any other remedy, and an election to make expenditures or to take action to perform an obligation of Borrower or of any Grantor shall not affect Lender's right to declare a default and to exercise its rights and remedies.

  • SUSPENSION & TERMINATION FOR DEFAULT Enterprise Services may suspend Contractor’s operations under this Master Contract immediately by written cure notice of any default. Suspension shall continue until the default is remedied to Enterprise Services’ reasonable satisfaction; Provided, however, that, if after thirty (30) days from such a suspension notice, Contractor remains in default, Enterprise Services may terminate Contractor’s rights under this Master Contract. All of Contractor’s obligations to Enterprise Services and Purchasers survive termination of Contractor’s rights under this Master Contract, until such obligations have been fulfilled.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!