Estimated Project Development Milestone Schedule Sample Clauses

Estimated Project Development Milestone Schedule. 4Q06 · Ongoing collection of wind data at site · Plan of Development for Transmission Line submitted to USBLM · Conditional-Use-Permit Application submitted to Beaver County, Utah · Conditional Use Permit granted by Beaver County, Utah on Dec. 4, 2006 · Wind Turbine Generators (WTGs) Purchased – 80 Clipper C99 WTGs · Discussion with Utah State Tax Assessors Office regarding Property Tax Assessment 1Q07 · Final System Impact Study Reviewed with the Los Angeles Department of Water and Power (“LADWP”) · Completion of LADWP interconnection studies · Sign Interconnection Studies Agreement with LADWP/IPA. · NEPA Kickoff of Facility and Transmission Line commences · Seller hires NEPA contractor · Seller hires transmission engineering firm to design the project transmission line · Identify NEPA study requirements with the BLM · (Title 14 CEQA Compliance) · Property Tax Assessment Ongoing 2Q07 · Apply for Xxxxxxx County, Utah Conditional Use Permit · BLM’s NEPA review ongoing (Biological, Plant, Archeological) · Seller orders transmission line poles, conductors and other long-lead time equipment · Property tax assessment ongoing 3Q07 · USBLM’s NEPA review ongoing
Estimated Project Development Milestone Schedule. 1Q10 · Submit SF299 To BLM · Receive Approval from USBLM for Engineering · Submit Final Layout For Xxxxxxx County Conditional Use Permit · Submit Final Layout for Beaver County Conditional Use Permit · Amendment to Plan of Development submitted to USBLM · Receive Final, Amended Right of Way Grant from USBLM · Obtain construction water right approvals and leases · Receive layout approval under Xxxxxxx County, Conditional-Use-Permit No. Z-2008-008 · Receive layout approval under Beaver County Conditional Use Permit No. 2006-09 Amended · Receive site layout approval from XXXXX for state lands · Notice To Proceed from USBLM for Construction · Construction Commences 2Q10 · Complete Civil Construction (Roads/Pads) · Complete WTG Turbine Foundations · Start WTG Deliveries to Site · Start Turbine Erection 3Q10 · Complete WTG Turbine Deliveries · Complete WTG Turbine Erection · Start Turbine Commissioning 4Q10 · Complete Turbine Commissioning · Construction Demobilization Cleanup/Restoration · Commercial Operation Date Achieved

Related to Estimated Project Development Milestone Schedule

  • Milestone Schedule Please state the status and progress of each Milestone and identify any completed Milestone(s) for the previous calendar quarter.

  • Development Milestones In addition to its obligations under Paragraph 7.1, LICENSEE specifically commits to achieving (either itself or through the acts of a SUBLICENSEE) the following development milestones in its diligence activities under this AGREEMENT: (a) (b).

  • Project Specific Milestones In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before October 1, 2020, Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.2 Delivery of major electrical equipment. On or before October 1, 2020, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

  • Project/Milestones Taxpayer is a food producer and full line grocery store chain, proposing to expand its in- house food manufacturing. In consideration for the Credit, Taxpayer agrees to maintain at least 44 full-time employees, determined on an annual full-time equivalent basis, at its Merced food manufacturing facility; and, to hire full-time employees and invest in a research and development equipment, manufacturing equipment, tenant improvements, and a facility as part of its expansion in Merced and/or Riverside, California (collectively, the “Project”). Taxpayer agrees that for the purposes of satisfying the milestones in Exhibit A (“Milestones”), Taxpayer will only count jobs and investment at its Merced food manufacturing facility and/or a new food manufacturing facility in Riverside, and that no other jobs or investment at any retail or other facility can be counted. For the purposes of calculating the number of full-time employees, no employee transferred from another affiliate, facility, or entity owned, related to, or controlled by the Taxpayer shall be included in the calculation. Taxpayer shall not be entitled to any portion of the Credit if it fails to maintain at least 44 full-time employees, determined on an annual full-time equivalent basis, at its Merced facility for the entire duration of the agreement. Further, Taxpayer agrees to satisfy the Milestones and must maintain Milestones for a minimum of three (3) taxable years thereafter. In the event Taxpayer employs more than the number of full- time employees, determined on an annual full-time equivalent basis, than required in Exhibit A, for purposes of satisfying the “Minimum Annual Wage of California Full-time Employees Hired” and the “Cumulative Average Annual Wage of California Full-time Employees Hired,” Taxpayer may use the wages of any of the full-time employees hired within the required time period. For purposes of calculating the “Minimum Annual Wage of California Full-time Employees Hired” and the “Cumulative Average Annual Wage of California Full-time

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • Development Milestone Payments Pfizer shall make the payments set forth below within [**] days (or [**] days after [**] following the first occurrence of each event described below for a Licensed Product Covered by a Valid Claim that achieves such milestone (each event a “Development Milestone” and each payment a “Development Milestone Payment”). Development Milestone Development Milestone Payment [**] [**] [**] [**] [**] [**] [**] [**] [**] [**] [**] [**] [**] [**] [**] [**] [**] [**] [**]. The Development Milestone Payment in clause (2) of this Section 3.3 may become payable as set forth in Section 4.6. Whether or not the Development Milestone in clause (2) of this Section 3.3 is achieved, the Development Milestone Payment in clause (2) shall, pursuant to Section 4.6, in all cases become payable prior to the time the Development Milestone Payment in clause (3) of this Section 3.3 becomes payable. With respect to the Development Milestone in clause (3) of this Section 3.3, in the case of a [**] that is determined to have become [**], such Development Milestone, if achieved based on such [**], shall be achieved upon [**]; provided, however, if either [**], such Development Milestone shall be deemed to have been met on the date of such determination. With respect to the Development Milestone in clause (8) of this Section 3.3, such Development Milestone will be paid in [**], provided that if such Licensed Product [**]. (For the avoidance of doubt, all payment [**] that became payable prior to such [**] shall continue to be payable and there shall be [**] of the [**] Development Milestone Payment will be deemed to have been achieved and payable on [**], and will be paid by Pfizer within [**] days thereafter, until the earlier of [**]. For example, [**] of such Development Milestone, such Development Milestone Payment would be paid [**] of the Development Milestone [**]. For the avoidance of doubt: (a) except for (i) the Development Milestone Payment set forth in clause (6) of this Section 3.3 [**], (ii) the Development Milestone Payment set forth in clause (8) of this Section 3.3 [**] and (iii) the Development Milestone Payment set forth in clause (9) of this Section 3.3 [**], each Development Milestone Payment shall be payable only once upon achievement of the applicable Development Milestone and only on the first occurrence of the corresponding Development Milestone regardless of the number of Licensed Products and (b) satisfaction of a Development Milestone by an Affiliate or by a sublicensee or assignee of, or Third Party retained by, Pfizer or its Affiliates shall be deemed to have been satisfied by Pfizer for the purposes of this Section 3.3.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Project Plan Development of Project Plan Upon the Authorized User’s request, the Contractor must develop a Project Plan. This Project Plan may include Implementation personnel, installation timeframes, escalation procedures and an acceptance plan as appropriate for the Services requested. Specific requirements of the plan will be defined in the RFQ. In response to the RFQ, the Contractor must agree to furnish all labor and supervision necessary to successfully perform Services procured from this Lot. Project Plan Document The Contractor will provide to the Authorized User, a Project Plan that may contain the following items: • Name of the Project Manager, Contact Phone Numbers and E-Mail Address; • Names of the Project Team Members, Contact Phone Numbers and E-Mail Address; • A list of Implementation milestones based on the Authorized User’s desired installation date; • A list of responsibilities of the Authorized User during system Implementation; • A list of designated Contractor Authorized Personnel; • Escalation procedures including management personnel contact numbers; • Full and complete documentation of all Implementation work; • Samples of knowledge transfer documentation; and • When applicable, a list of all materials and supplies required to complete the Implementation described in the RFQ. Materials and Supplies Required to Complete Implementation In the event that there are items required to complete an Implementation, the Contractor may request the items be added to its Contract if the items meet the scope of the Contract. Negotiation of Final Project Plan If the Authorized User chooses to require a full Project Plan, the State further reserves the right for Authorized Users to negotiate the final Project Plan with the apparent RFQ awardee. Such negotiation must not substantively change the scope of the RFQ plan, but can alter timeframes or other incidental factors of the final Project Plan. The Authorized User will provide the Contractor a minimum of five (5) business days’ notice of the final negotiation date. The Authorized User reserves the right to move to the next responsible and responsive bidder if Contractor negotiations are unsuccessful.

  • Milestones Subject to the provisions of the SGIP, the Parties shall agree on milestones for which each Party is responsible and list them in Attachment 4 of this Agreement. A Party’s obligations under this provision may be extended by agreement. If a Party anticipates that it will be unable to meet a milestone for any reason other than a Force Majeure event, it shall immediately notify the other Parties of the reason(s) for not meeting the milestone and: (1) propose the earliest reasonable alternate date by which it can attain this and future milestones, and (2) requesting appropriate amendments to Attachment 4. The Party affected by the failure to meet a milestone shall not unreasonably withhold agreement to such an amendment unless: (1) it will suffer significant uncompensated economic or operational harm from the delay, (2) attainment of the same milestone has previously been delayed, or (3) it has reason to believe that the delay in meeting the milestone is intentional or unwarranted notwithstanding the circumstances explained by the Party proposing the amendment.

  • Project Timeline The Project Timeline establishes a start and end date for each Phase of the Project. Developed during the Initiate & Plan Stage and revised as mutually agreed to, if needed, the timeline accounts for resource availability, business goals, size and complexity of the Project, and task duration requirements.