Hydraulic Testing Sample Clauses

Hydraulic Testing. A straddle packer system and accompanying equipment will be used to perform the hydraulic testing to determine the hydraulic conductivity of the rock at regular intervals down the borehole. The test locations will be based on the information gained from the geophysical well logging and core logging activities.
AutoNDA by SimpleDocs
Hydraulic Testing. The contractor shall include the cost of any required hydraulic testing of the fire sprinkler system.
Hydraulic Testing. After completion of job, if required, hydraulic testing shall be carried out. Any defect observed is to be rectified immediately by the party till Hydraulic Testing is cleared.
Hydraulic Testing. In Phase II, the Upper Floridan aquifer test well and monitoring xxxxx installed in Phase I will be used to conduct up to two 72‐ to 120‐hour pump tests to estimate the hydraulic properties of the Upper Floridan aquifer. Water levels will be monitored using rented or owned submersible pressure transducers and dataloggers provided by CH2M. The design of an infiltration gallery or evaluation of existing features on the site to receive the produced water and test infiltration will be performed by CH2M. If construction of the temporary infiltration gallery is necessary, the gallery will be constructed by a subcontractor, coordinated and managed by CH2M and contracted by the City.
Hydraulic Testing i. Install data loggers to evaluate confined aquifer conditions at key locations.

Related to Hydraulic Testing

  • Acceptance Testing At the time of installation of a LIS trunk group, and at no additional charge, acceptance tests will be performed to ensure that the service is operational and meets the applicable technical parameters.

  • Testing Landlord shall have the right to conduct annual tests of the Premises to determine whether any contamination of the Premises or the Project has occurred as a result of Tenant’s use. Tenant shall be required to pay the cost of such annual test of the Premises; provided, however, that if Tenant conducts its own tests of the Premises using third party contractors and test procedures acceptable to Landlord which tests are certified to Landlord, Landlord shall accept such tests in lieu of the annual tests to be paid for by Tenant. In addition, at any time, and from time to time, prior to the expiration or earlier termination of the Term, Landlord shall have the right to conduct appropriate tests of the Premises and the Project to determine if contamination has occurred as a result of Tenant’s use of the Premises. In connection with such testing, upon the request of Landlord, Tenant shall deliver to Landlord or its consultant such non-proprietary information concerning the use of Hazardous Materials in or about the Premises by Tenant or any Tenant Party. If contamination has occurred for which Tenant is liable under this Section 30, Tenant shall pay all costs to conduct such tests. If no such contamination is found, Landlord shall pay the costs of such tests (which shall not constitute an Operating Expense). Landlord shall provide Tenant with a copy of all third party, non-confidential reports and tests of the Premises made by or on behalf of Landlord during the Term without representation or warranty and subject to a confidentiality agreement. Tenant shall, at its sole cost and expense, promptly and satisfactorily remediate any environmental conditions identified by such testing in accordance with all Environmental Requirements. Landlord’s receipt of or satisfaction with any environmental assessment in no way waives any rights which Landlord may have against Tenant.

  • Stability Testing Patheon may be requested to conduct stability testing on the Products in accordance with the protocols set out in the Specifications for the separate fees and during the time periods set out in Schedule C to a Product Agreement. Patheon will not make any changes to these testing protocols without prior written approval from Client. If a confirmed stability test failure occurs, Patheon will notify Client within one Business Day, after which Patheon and Client will jointly determine the proceedings and methods to be undertaken to investigate the cause of the failure, including which party will bear the cost of the investigation. Patheon will not be liable for these costs unless it has failed to perform the Manufacturing Services in accordance with the Specifications, cGMPs, and Applicable Laws. Patheon will give Client ail stability test data and results at Client’s request.

  • Commissioning Commissioning tests of the Interconnection Customer's installed equipment shall be performed pursuant to applicable codes and standards. If the Interconnection Customer is not proceeding under Section 2.3.2, the Utility must be given at least ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • Sampling The Licensee agrees that the Composition is purchased as a “Work Made for Hire” whereby the clearing of any sampled materials is the responsibility of Licensee.

  • Product Testing Upon request, Customer shall provide Operator a laboratory report for each Product delivery by Customer or Customer’s supplier. Operator will not be obligated to receive Contaminated Product for throughput across the Berths, nor will Operator be obligated to accept Product that fails to meet the quality specifications set forth in the arrival notice.

  • Plant The expression ‘Plant’ as used in the tender papers shall mean every temporary accessory necessary or considered necessary by the Engineer to execute, construct, complete and maintain the work and all altered, modified, substituted and additional works ordered in the time and the manner herein provided and all temporary materials and special and other articles and appliance of every sort kind and description whatsoever intended or used therefore.

  • Stability 14.01 Maintain a documented, ongoing stability program to monitor the stability of the Product using stability indicating procedures. X 14.02 Data analysis and trending reporting will be performed. X

  • Fuel 28.1 The Vehicle must be returned with the amount of fuel equal to that at the time of the commencement of the rental. If the Vehicle is returned with less fuel, the difference will be charged to You at a rate of $5.00 including GST per litre (which includes a service component).

  • Compatibility 1. Any unresolved issue arising from a mutual agreement procedure case otherwise within the scope of the arbitration process provided for in this Article and Articles 25A to 25G shall not be submitted to arbitration if the issue falls within the scope of a case with respect to which an arbitration panel or similar body has previously been set up in accordance with a bilateral or multilateral convention that provides for mandatory binding arbitration of unresolved issues arising from a mutual agreement procedure case.