No Extension of Final Completion Date Sample Clauses

No Extension of Final Completion Date. If Contractor is delayed at any time for any reason during the execution and completion of any portion of the Work, then Contractor shall employ additional personnel as are necessary to accelerate the progress of the Work to meet the Milestone Dates identified in the Purchase Order or Project Schedule. Subject to the provisions of Section 12.2, Exelon will not pay and Contractor shall bear Contractor’s increased costs related to Contractor’s accelerated performance. Subject to the terms of the Contract Documents, Contractor acknowledges and agrees that no extension to the date of Final Completion identified in the Purchase Order or Project Schedule shall be granted unless agreed to in writing by Exelon and Contractor.
AutoNDA by SimpleDocs
No Extension of Final Completion Date. If Contractor is delayed *** during the execution and completion of any portion of the Work, then Contractor shall *** as are necessary to *** of the *** to meet the *** identified in the Purchase Order or Project Schedule. Subject to the provisions of ***, ComEd will *** and Contractor shall *** related to Contractor’s ***. Subject to the terms of the Contract Documents, Contractor acknowledges and agrees that no extension to the date of Final Completion identified in the Purchase Order or Project Schedule shall be granted unless agreed to in writing by ComEd and Contractor.
No Extension of Final Completion Date. Except to the extent caused by Company, its contractors, Force Majeure or site trespass, if there is any delay such that the Guaranteed Substantial Completion Date is not reasonably likely to be met, at any time during the execution and completion of any portion of the Work, then Contractor shall employ additional personnel and material as are necessary to accelerate the progress of the Work to meet the Milestone Dates, including the Guaranteed Substantial Completion Date and the Final Completion Date identified in the Contract Documents. Subject to the provisions of the Contract Documents, Company will not pay, and Contractor shall bear, Contractor’s increased costs related to Contractor’s accelerated performance. Subject to the terms of the Contract Documents, Contractor acknowledges and agrees that no extension to the Final Completion Date shall be granted unless agreed to in writing by Company and Contractor. If Contractor fails to meet the Guaranteed Substantial Completion Date, it will be subject to the liquidated damages detailed in Exhibit N.

Related to No Extension of Final Completion Date

  • Delivery; Acceptance of Premises; Commencement Date Landlord shall use reasonable efforts to deliver the Premises to Tenant on or before the Target Commencement Date, with Landlord’s Work Substantially Completed (“Delivery” or “Deliver”). If Landlord fails to timely Deliver the Premises, Landlord shall not be liable to Tenant for any loss or damage resulting therefrom, and this Lease shall not be void or voidable except as provided herein. If Landlord does not Deliver the Premises within 45 days of the Target Commencement Date for any reason other than Force Majeure delays and Tenant Delays, this Lease may be terminated by Tenant by written notice to Landlord, and if so terminated by Tenant: (a) the Security Deposit, or any balance thereof (i.e., after deducting therefrom all amounts to which Landlord is entitled under the provisions of this Lease), shall be returned to Tenant, and (b) neither Landlord nor Tenant shall have any further rights, duties or obligations under this Lease, except with respect to provisions which expressly survive termination of this Lease. As used herein, the terms “Landlord’s Work,” “Tenant Delays” and “Substantially Completed” shall have the meanings set forth for such terms in the Work Letter. If Tenant does not elect to void this Lease within 10 business days of the lapse of such 45 day period, such right to void this Lease shall be waived and this Lease shall remain in full force and effect. Notwithstanding anything to the contrary contained herein, if Tenant does not terminate this Lease pursuant to the immediately preceding sentence, Base Rent shall be abated 1 day for each day after such 45 day period (as extended by Force Majeure delays and Tenant Delays) that the Premises are not Delivered to Tenant.

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.

  • Commencement Date Delay Except as otherwise provided in the Lease, Delivery of the Premises shall occur when Landlord’s Work has been Substantially Completed, except to the extent that completion of Landlord’s Work shall have been actually delayed by any one or more of the following causes (“Tenant Delay”):

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Extension of Facility Termination Date The Seller may advise any Managing Agent in writing of its desire to extend the Facility Termination Date for an additional period not exceeding 364 days, provided such request is made not more than 90 days prior to, and not less than 60 days prior to, the then current Facility Termination Date. Each Managing Agent so advised by the Seller shall promptly notify each Committed Purchaser in its related Purchaser Group of any such request and each such Committed Purchaser shall notify its related Managing Agent, the Collateral Agent and the Seller of its decision to accept or decline the request for such extension no later than 30 days prior to the then current Facility Termination Date (it being understood that each Committed Purchaser may accept or decline such request in its sole discretion and on such terms as it may elect, and the failure to so notify its Managing Agent, the Collateral Agent and the Seller shall be deemed an election not to extend by such Committed Purchaser). In the event that at least one Committed Purchaser agrees to extend the Facility Termination Date, the Seller Parties, the Collateral Agent, the extending Committed Purchasers and the applicable Managing Agent or Managing Agents shall enter into such documents as such extending Committed Purchasers may deem necessary or appropriate to reflect such extension, and all reasonable costs and expenses incurred by such Committed Purchasers, the Managing Agents and the Collateral Agent (including reasonable attorneys’ fees) shall be paid by the Seller. In the event that any Committed Purchaser (a) declines the request to extend the Facility Termination Date or (b) is in a Purchaser Group with respect to which the Seller did not seek an extension of the Facility Termination Date (each such Committed Purchaser being referred to herein as a “Non-Renewing Committed Purchaser”), and, in the case of a Non-Renewing Committed Purchaser described in clause (a), the Commitment of such Non-Renewing Committed Purchaser is not assigned to another Person in accordance with the terms of this Article XI prior to the then current Facility Termination Date, the Purchase Limit shall be reduced by an amount equal to each such Non-Renewing Committed Purchaser’s Commitment on the then current Facility Termination Date.

  • Renewal, Extension The renewal or extension of any Letter of Credit shall, for purposes hereof, be treated in all respects the same as the issuance of a new Letter of Credit hereunder.

  • Extension of the Expiry Date; Non-Extension Advance No earlier than the 60th day and no later than the 40th day prior to the then effective Expiry Date (unless such Expiry Date is on or after the date that is 15 days after the Final Legal Distribution Date for the Class A Certificates), the Borrower shall request that the Liquidity Provider extend the Expiry Date to the earlier of (i) the date that is 15 days after the Final Legal Distribution Date for the Class A Certificates and (ii) the date that is the day immediately preceding the 364th day occurring after the last day of the Consent Period (as hereinafter defined). Whether or not the Borrower has made such request, the Liquidity Provider shall advise the Borrower no earlier than the 40th day (or, if earlier, the date of the Liquidity Provider’s receipt of such request, if any, from the Borrower) and no later than the 25th day prior to the then effective Expiry Date (such period, the “Consent Period”), whether, in its sole discretion, it agrees to so extend the Expiry Date. If the Liquidity Provider advises the Borrower on or before the date on which the Consent Period ends that such Expiry Date shall not be so extended, or fails to irrevocably and unconditionally advise the Borrower on or before the date on which the Consent Period ends that such Expiry Date shall be so extended (and, in each case, if the Liquidity Provider shall not have been replaced in accordance with Section 3.5(e) of the Intercreditor Agreement), the Borrower shall be entitled on and after the date on which the Consent Period ends (but prior to the then effective Expiry Date) to request a Non-Extension Advance in accordance with Section 2.02(b) hereof and Section 3.5(d) of the Intercreditor Agreement.

  • Request for Issuance, Amendment, Renewal, Extension; Certain Conditions To request the issuance of a Letter of Credit or the amendment, renewal or extension of an outstanding Letter of Credit, the Borrower shall hand deliver or telecopy (or transmit by electronic communication, if arrangements for doing so have been approved by the applicable Issuing Bank) a LC Request to the applicable Issuing Bank and the Administrative Agent not later than 1:00 p.m. on the third Business Day preceding the requested date of issuance, amendment, renewal or extension (or such later date and time as is reasonably acceptable to the applicable Issuing Bank). A request for an initial issuance of a Letter of Credit shall specify in form and detail reasonably satisfactory to the applicable Issuing Bank: (i) the proposed issuance date of the requested Letter of Credit (which shall be a Business Day); (ii) the amount thereof; (iii) the expiry date thereof; (iv) the name and address of the beneficiary thereof; (v) the documents to be presented by such beneficiary in case of any drawing thereunder; (vi) the full text of any certificate to be presented by such beneficiary in case of any drawing thereunder and (vii) such other matters as the applicable Issuing Bank may reasonably require. A request for an amendment, renewal or extension of any outstanding Letter of Credit shall specify in form and detail reasonably satisfactory to the applicable Issuing Bank (w) the Letter of Credit to be amended, renewed or extended; (x) the proposed date of amendment, renewal or extension thereof (which shall be a Business Day), (y) the nature of the proposed amendment, renewal or extension, and (z) such other matters as the applicable Issuing Bank may reasonably require. If requested by the applicable Issuing Bank, the Borrower also shall submit a letter of credit application substantially on the applicable Issuing Bank’s standard form in connection with any request for a Letter of Credit. A Letter of Credit shall be issued, amended, renewed or extended only if (and upon issuance, amendment, renewal or extension of each Letter of Credit the Borrower shall be deemed to represent and warrant (solely in the case of (w) and (x) that)), after giving effect to such issuance, amendment, renewal or extension (A) the aggregate LC Exposure shall not exceed $25,000,000, (B) the total Revolving Exposures shall not exceed the total Revolving Commitments, (C) the aggregate LC Exposure with respect to Letters of Credit issued by such Issuing Bank shall not exceed the LC Sublimit of such Issuing Bank, (D) the Revolving Exposure of such Issuing Bank does not exceed its Revolving Commitments and (E) if a Defaulting Lender exists, either such Revolving Lender or the Borrower has entered into arrangements satisfactory to the Administrative Agent and the Issuing Banks to eliminate any Fronting Exposure associated with such Lender.

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.