NOTICE TO CURE A DEFAULT Sample Clauses

NOTICE TO CURE A DEFAULT. If the Construction Manager persistently fails to supply enough properly qualified workers, proper materials, or equipment to maintain the approved Schedule of the Work or fails to make prompt payment to its workers, Subcontractors, or Material Suppliers, disregards Laws or orders of any public authority having jurisdiction, or is otherwise guilty of a material breach of a provision of this Agreement, the Construction Manager may be deemed in default. If the Construction Manager fails within seven (7) Days after receipt of written notice to commence and continue satisfactory correction of such default with diligence and promptness, then the Owner shall give the Construction Manager a second notice to correct the default within a three (3) Day period. If the Construction Manager fails to promptly commence and continue satisfactory correction of the default following receipt of such second notice, the Owner without prejudice to any other rights or remedies may: (a) take possession of the Worksite; (b) complete the Work utilizing reasonable means; (c) withhold payment due to the Construction Manager; and
AutoNDA by SimpleDocs
NOTICE TO CURE A DEFAULT. If the Construction Manager persistently fails to supply enough properly qualified workers, proper materials, or equipment to maintain the approved Schedule of the Work or fails to make prompt payment to its workers, Subcontractors, or Material Suppliers, disregards Laws or orders of any public authority having jurisdiction, or is otherwise guilty of a material breach of a provision of this Agreement, the Construction Manager may be deemed in default. If the Construction Manager fails within seven (7) Days after receipt of written notice to commence and continue satisfactory correction of such default with diligence and promptness, then the Owner shall give the Construction Manager a second notice to correct the default within a three (3) Day period. If the Construction Manager fails to promptly commence and continue satisfactory correction of the default following receipt of such second notice, the Owner without prejudice to any other rights or remedies may: (a) take possession of the Worksite; (b) complete the Work utilizing reasonable means; (c) withhold payment due to the Construction Manager; and (d) as the Owner deems necessary, supply workers and materials, equipment, and other facilities for the satisfactory correction of the default, and charge the Construction Manager, the costs and expenses, including reasonable Overhead, profit, and attorneys' fees.
NOTICE TO CURE A DEFAULT. If Private Entity persistently fails to supply enough qualified workers, proper materials, or equipment to maintain the approved Schedule of the Work, or fails to make prompt payment to its workers, Subcontractors, or Suppliers, disregards Laws or orders of any public authority having jurisdiction, or is otherwise guilty of a material breach of a provision of this Agreement, Private Entity may be deemed in default.
NOTICE TO CURE A DEFAULT. If Miner persistently or recurrently refuses or fails to perform the work required under Exhibit A, supply enough properly skilled workers or equipment to diligently and reasonably prosecute the Work; or having received prompt payment from the Owner, fails to make prompt payment to its workers, Subcontractors, government entities, or Material Suppliers, or is otherwise guilty of a material breach of a provision of this Agreement, Miner may be deemed in default. If Miner fails within ten (10) working Days after written notification to cure if reasonably possible, or commence and continue satisfactory action for correction of such default with diligence and promptness, then Owner shall give the Miner a second written notice to initiate action to correct the default within a three (3) business Day period. If the Miner fails to promptly cure if reasonably possible, or commence and continue action for satisfactory correction of the default following receipt of such second notice, the Owner, without prejudice to any other rights or remedies, shall have the right to terminate this Agreement. In the case of an default that cannot reasonably or practicably be cured within the notice period, the Miner shall submit a plan and schedule for correction or other resolution of the condition within the timelines of this subparagraph.
NOTICE TO CURE A DEFAULT. If the Constructor persistently fails to supply enough qualified workers, proper Materials to maintain the approved Schedule of the Work, or fails to make prompt payment to its workers, Subcontractors, or Material Suppliers, disregards Laws or orders of any public authority having jurisdiction, or is otherwise guilty of a material breach of a provision of this Agreement, the Constructor may be deemed in default. If the Constructor fails within twenty one (21) Days after receipt of written notice to commence and continue satisfactory correction of such default with diligence and promptness, then the Owner shall give the Constructor a second notice to correct the default within a three (3) Day period.
NOTICE TO CURE A DEFAULT. 11.2.1. If Design-Builder persistently fails perform its obligations under this Agreement, or fails to make prompt payment to its workers, Subcontractors, or Suppliers, disregards Laws or orders of any public authority having jurisdiction or is otherwise guilty of a material breach of a provision of this Agreement, Design-Builder may be deemed in default. If Design-Builder fails within seven (7) Days after receipt of written notice to commence and continue satisfactory correction of such default, then Owner shall give Design-Builder a second notice to correct the default within a three (3) Day period.
NOTICE TO CURE A DEFAULT. If the Subcontractor fails to supply enough qualified workers, proper materials, or equipment, to maintain the Progress Schedule, or fails to make prompt payment to its workers, subsubcontractors, or suppliers, or disregards Laws or orders of any public authority having jurisdiction, or otherwise is guilty of a material breach of a provision of this Agreement, the Subcontractor shall be deemed in default of this Agreement. If the Subcontractor fails within three (3) Business Days after written notification to commence and continue satisfactory correction of the default with diligence and promptness, then the Constructor shall give a second notice to the Subcontractor and surety, if any, to correct the default within a two
AutoNDA by SimpleDocs
NOTICE TO CURE A DEFAULT. If Design-Builder persistently fails to supply enough qualified workers, proper materials, or equipment to maintain the approved Schedule of the Work, or fails to make prompt payment to its workers, Subcontractors, or Suppliers, disregards Laws or orders of any public authority having jurisdiction, or is otherwise guilty of a material breach of a provision of this Agreement, Design-Builder may be deemed in default.
Time is Money Join Law Insider Premium to draft better contracts faster.