Common use of Outage Schedules Clause in Contracts

Outage Schedules. The Transmission Developer or Connecting Transmission Owner, as applicable, and pursuant to ISO Procedures, shall post scheduled outages of its respective transmission facilities on the NYISO OASIS.

Appears in 26 contracts

Samples: Transmission Project Interconnection Agreement, Transmission Project Interconnection Agreement, Interconnection Agreement

AutoNDA by SimpleDocs

Outage Schedules. The Transmission Developer or Connecting Transmission Owner, as applicable, applicable and pursuant to ISO Procedures, shall post scheduled outages of its respective transmission facilities on the NYISO OASIS.

Appears in 3 contracts

Samples: Transmission Project Interconnection Agreement, Transmission Project Interconnection Agreement, Transmission Project Interconnection Agreement

AutoNDA by SimpleDocs

Outage Schedules. The Transmission Developer or Connecting Transmission Owner, as applicable, and pursuant to ISO Procedures, shall post scheduled outages of its respective transmission facilities on the NYISO OASIS.OASIS.β€Œ

Appears in 1 contract

Samples: Transmission Project Interconnection Agreement