Outage Schedules. The Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability of
Appears in 12 contracts
Samples: Service Agreement, Service Agreement, Service Agreement
Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any
Appears in 4 contracts
Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
Outage Schedules. The Connecting Transmission Owner Owners shall each post scheduled outages of its their transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner National Grid and NYISO for a minimum of a rolling thirty-six month periodperiod after such schedule is established in accordance with NRC Requirements and Commitments. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner National Grid may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Outage Schedules. The Connecting Transmission Owner Owners shall each post scheduled outages of its their transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner National Grid and NYISO for a minimum of a rolling thirty-six month periodperiod after such schedule is established in accordance with NRC Requirements and Commitments. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner National Grid may request, Developer to reschedule its maintenance as necessary to maintain the reliability of,
Appears in 2 contracts
Samples: Interconnection Agreement, Interconnection Agreement
Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any additional direct
Appears in 2 contracts
Samples: Standard Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
Outage Schedules. The Connecting Transmission Owner Owners shall each post scheduled outages of its their transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner National Grid and NYISO for a minimum of a rolling thirty-six month periodperiod after such schedule is established in accordance with NRC Requirements and Commitments. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofas
Appears in 1 contract
Samples: Interconnection Agreement
Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofOwner
Appears in 1 contract
Outage Schedules. The Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any additional direct costs that the Developer incurs as
Appears in 1 contract
Outage Schedules. The Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability of.
Appears in 1 contract
Samples: Interconnection Agreement
Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofto
Appears in 1 contract
Samples: Interconnection Agreement
Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any additional direct costs that the Developer incurs as a result of rescheduling maintenance, including any additional overtime,
Appears in 1 contract
Outage Schedules. The Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any additional direct costs that the Developer incurs as a result of rescheduling maintenance, including any additional
Appears in 1 contract
Samples: Service Agreement