Common use of Outage Schedules Clause in Contracts

Outage Schedules. The Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability of

Appears in 12 contracts

Samples: Service Agreement, Service Agreement, Service Agreement

AutoNDA by SimpleDocs

Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any

Appears in 4 contracts

Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Outage Schedules. The Connecting Transmission Owner Owners shall each post scheduled outages of its their transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner National Grid and NYISO for a minimum of a rolling thirty-six month periodperiod after such schedule is established in accordance with NRC Requirements and Commitments. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner National Grid may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation

Appears in 3 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Outage Schedules. The Connecting Transmission Owner Owners shall each post scheduled outages of its their transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner National Grid and NYISO for a minimum of a rolling thirty-six month periodperiod after such schedule is established in accordance with NRC Requirements and Commitments. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner National Grid may request, Developer to reschedule its maintenance as necessary to maintain the reliability of,

Appears in 2 contracts

Samples: Interconnection Agreement, Interconnection Agreement

Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any additional direct

Appears in 2 contracts

Samples: Standard Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Outage Schedules. The Connecting Transmission Owner Owners shall each post scheduled outages of its their transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner National Grid and NYISO for a minimum of a rolling thirty-six month periodperiod after such schedule is established in accordance with NRC Requirements and Commitments. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofas

Appears in 1 contract

Samples: Interconnection Agreement

Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofOwner

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Outage Schedules. The Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any additional direct costs that the Developer incurs as

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

AutoNDA by SimpleDocs

Outage Schedules. The Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability of.

Appears in 1 contract

Samples: Interconnection Agreement

Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofto

Appears in 1 contract

Samples: Interconnection Agreement

Outage Schedules. The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any additional direct costs that the Developer incurs as a result of rescheduling maintenance, including any additional overtime,

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement

Outage Schedules. The Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability ofof the New York State Transmission System. Compensation to Developer for any additional direct costs that the Developer incurs as a result of rescheduling maintenance, including any additional

Appears in 1 contract

Samples: Service Agreement