Payment for Change of Scope. 15.3.1 Within [15 (fifteen)] days of issuing a Change of Scope Order relating to Maintenance Depots, the Authority shall make a part payment to the Operator in a sum equal to [20% (twenty per cent)] of the cost of Change of Scope as agreed hereunder upon furnishing of a bank guarantee by the Operator for an equivalent amount and for a period of [180 (one hundred and eighty)] days, substantially in the form specified in Schedule-D. The Operator shall, after commencement of work, present to the Authority bills for payment in respect of the works and services in progress or completed works and services, as the case may be, supported by such Documentation as is reasonably sufficient for the Authority to determine the accuracy thereof. Within [30 (thirty)] days of receipt of such bills, the Authority shall disburse to the Operator such amounts as are reasonable and after making a proportionate deduction for the advance payment made hereunder, and in the event of any Dispute, final adjustments thereto shall be made under and in accordance with the Dispute Resolution Procedure. 15.3.2 Notwithstanding anything to the contrary contained in Clause 15.3.1, all costs arising out of any Change of Scope Order shall be borne by the Operator, subject to an aggregate ceiling of 0.25% (zero point two five per cent) of the Total Project Cost. Any costs in excess of the ceiling shall be reimbursed by the Authority in accordance with Clause 15.3.1.
Appears in 3 contracts
Samples: Public Private Partnership Agreement, Model Concession Agreement, Model Concession Agreement
Payment for Change of Scope. 15.3.1 Within [15 (fifteen)] ) days of issuing a Change of Scope Order relating to Maintenance Depots, the Authority shall make a part payment to the Operator in a sum equal to [20% (twenty per cent)] ) of the cost of Change of Scope as agreed hereunder upon furnishing of a bank guarantee by the Operator for an equivalent amount and for a period of [180 (one hundred and eighty)] ) days, substantially in the form specified in Schedule-D. The Operator shall, after commencement of work, present to the Authority bills for payment in respect of the works and services in progress or completed works and services, as the case may be, supported by such Documentation as is reasonably sufficient for the Authority to determine the accuracy thereof. Within [30 (thirty)] ) days of receipt of such bills, the Authority shall disburse to the Operator such amounts as are reasonable and after making a proportionate deduction for the advance payment made hereunder, and in the event of any Dispute, final adjustments thereto shall be made under and in accordance with the Dispute Resolution Procedure.
15.3.2 Notwithstanding anything to the contrary contained in Clause 15.3.1, all costs arising out of any Change of Scope Order shall be borne by the Operator, subject to an aggregate ceiling of 0.25% (zero point two five per cent) of the Total Project Cost. Any costs in excess of the ceiling shall be reimbursed by the Authority in accordance with Clause 15.3.1.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Payment for Change of Scope. 15.3.1 16.3.1 Within [15 7 (fifteen)] seven) days of issuing a Change of Scope Order relating to Maintenance DepotsOrder, the Authority shall make a part an advance payment to the Operator Concessionaire in a sum equal to [20% (twenty per cent)] ) of the cost of Change of Scope as agreed hereunder upon furnishing hereunder, and in the event of a bank guarantee Dispute, 20% (twenty per cent) of the cost assessed by the Operator for an equivalent amount and for a period of [180 (one hundred and eighty)] daysIndependent Engineer or the Independent Panel, substantially in as the form specified in Schedule-D. case may be. The Operator Concessionaire shall, after commencement of work, present to the Authority bills for payment in respect of the works and services in progress or completed works and servicesworks, as the case may be, supported by such Documentation as is reasonably sufficient for the Authority to determine the accuracy thereof. Within [30 (thirty)] ) days of receipt of such bills, the Authority shall disburse to the Operator Concessionaire such amounts as are certified by the Independent Engineer or the Independent Panel, as the case may be, as reasonable and after making a proportionate deduction for the advance payment made hereunder, and in the event of any Dispute, final adjustments thereto shall be made under and in accordance with the Dispute Resolution Procedure.
15.3.2 16.3.2 Notwithstanding anything to the contrary contained in Clause 15.3.116.3.1 above, all costs arising out of any Change of Scope Order issued during the Construction Period shall be borne by the OperatorConcessionaire, subject to an aggregate ceiling of 0.25% (zero point two five per cent) of the Total Project Cost. Any costs in excess of the ceiling shall be reimbursed by the Authority in accordance with Clause 15.3.116.3.1.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Payment for Change of Scope. 15.3.1 Within [15 (fifteen)] ) days of issuing a Change of Scope Order except for the items in clause 15.
1.1. a relating to Maintenance Depots, the Authority shall make a part payment to the Operator in a sum equal to [20% (twenty per cent)] ) of the cost of Change of Scope as agreed hereunder upon furnishing of a bank guarantee by the Operator for an equivalent amount and for a period of [180 (one hundred and eighty)] ) days, substantially in the form specified in Schedule-D. The Operator shall, after commencement of work, present to the Authority bills for payment in respect of the works and services in progress or completed works and services, as the case may be, supported by such Documentation as is reasonably sufficient for the Authority to determine the accuracy thereof. Within [30 (thirty)] ) days of receipt of such bills, the Authority shall disburse to the Operator such amounts as are reasonable and after making a proportionate deduction for the advance payment made hereunder, and in the event of any Dispute, final adjustments thereto shall be made under and in accordance with the Dispute Resolution Procedure.
15.3.2 Notwithstanding anything to the contrary contained in Clause 15.3.1, all costs arising out of any Change of Scope Order shall be borne by the Operator, subject to an aggregate ceiling of 0.25% (zero point two five per cent) of the Total Project Cost. Any costs in excess of the ceiling shall be reimbursed by the Authority in accordance with Clause 15.3.1.
Appears in 1 contract
Samples: Concession Agreement