Percent Complete. The percentage each portion of the applicable Work is completed, as compared to and categorized in the Schedule of Values, as of the end of the period covered by such Application for Payment. The percentage of the Work that is completed in each Application for Payment shall be the percentage of Work that has actually been completed and not rejected for the applicable Deliverable Portion of Work.
Percent Complete. The percentage each portion of the Work is completed, as compared to and categorized in the Schedule of Values, as of the end of the period covered by such Application for Payment. The percentage of the Work that is completed in each Application for Payment shall be the lesser of (a) the percentage of Work that has actually been completed and not rejected for the applicable Deliverable Portion of Work or (b) the percentage obtained dividing (i) Construction Manager’s actual, incurred expenses, on account of the Work for which Construction Manager has made payment attributed to the applicable Deliverable Portion of Work, by (ii) the share of the GMP in the applicable GMP Amendment allocated to that Work, as set forth in the Schedule of Values. Progress Report. A current Progress Report, updated Project Schedule, and updated Construction Schedule for the Deliverable Portion of Work applicable to the Application for Payment, all in accordance with Sections 4.6 and 5.3.
Percent Complete. Percent complete for the metabolic clinic variable collected across three years by type of surveillance system.
Percent Complete. Percent complete for the hospitalization variable collected across three years by type of surveillance system.
Percent Complete. Figure 6. Percent complete of the Length of stay – hospitalization variable collected across three years by type of surveillance system.
Percent Complete. Design progress shall be assessed according to design phase and percent complete as defined in Exhibit C - ODM. Exhibit H.1 Zero percent (0%) complete shall occur at the commencement of the Feasibility Approval Phase (if used), or Scope Approval Phase (if Feasibility Approval Phase is not a project requirement). 100% complete design documents shall be the ‘as-bid’ set of documents issued after the lowest responsible bidder and chosen add alternates have been identified as per section 8.6.10.
Percent Complete. List all of the tasks in the work statement and provide the cumulative percent complete for each task listed.
Percent Complete. Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete. To allow for proper schedule management, cost load the correction of punch list from Government pre-final inspection activity(ies) not less than 1 percent of the total contract value, which activity(ies) may be declared 100 percent complete upon completion and correction of all punch list work identified during Government pre-final inspection(s).