Updated Project Schedule definition
Examples of Updated Project Schedule in a sentence
Each Updated Project Schedule shall be sequentially numbered and dated for identification, and Contractor shall separately maintain and archive electronically throughout the term of the Contract (e.g., no Updated Project Schedule shall “over-write” the prior version or versions of the Project Schedule or Updated Project Schedule).
Contractor will submit an electronic Project Schedule file to be posted by Princeton to the cloud-based scheduling environment as Contractor’s Updated Project Schedule for Princeton University review.
Updated Project Schedule(s) shall be subject to Princeton University’s written approval, shall not change the previously established Required Substantial Completion Date or any of the Schedule Milestones, and shall not be binding upon Princeton University in any manner unless or until Princeton University has approved such Updated Project Schedule, subject to any qualifications in such approval and all other terms of this Contract.
Updated Project Schedule(s) shall be subject to Princeton University’s written approval, shall not change the previously established Scheduled Completion Date or the Schedule Milestones, and shall not be binding upon Princeton University until Princeton University has approved such Updated Project Schedule.
In addition to the Updated Project Schedule(s), and any other reports required under Clause E1, Contractor shall provide monthly progress reports (in narrative form) that analyze and comment on issues in the Updated Project Schedule.
In addition to the Updated Project Schedule, and any other reports required under Clause E1, Contractor shall provide monthly progress reports (in narrative form) that analyze and comment on issues in the Updated Project Schedule.
After approval of the proposed Project Schedule, the Contractor shall prepare on a monthly basis, or as Princeton University may require, an Updated Project Schedule that shall document the current schedule status of the Project and incorporate changes based on actual progress and new or more reliable information.
In addition to the Updated Project Schedule(s), and any other reports required under ▇▇▇▇▇▇ ▇▇, Contractor shall provide monthly progress reports (in narrative form) that analyze and comment on issues in the Updated Project Schedule.
In addition to the Updated Project Schedule, and any other reports required under ▇▇▇▇▇▇ ▇▇, Contractor shall provide monthly progress reports (in narrative form) that analyze and comment on issues in the Updated Project Schedule.
After approval of the proposed Project Schedule, the Contractor shall prepare on a monthly basis, or as Princeton University may require, an Updated Project Schedule that shall document the current schedule status of the Project and incorporate changes based on new or more reliable information.