Performance of Disputed Work Sample Clauses

Performance of Disputed Work. If TxDOT refuses to issue a Change Order based on DB Contractor’s request, DB Contractor shall nevertheless perform all work as specified by Directive Letter, and shall have the right to submit the issue to dispute resolution pursuant to Section 19. DB Contractor shall maintain and deliver to TxDOT, upon request, contemporaneous records, meeting the requirements of Section 13.9, for all work performed which DB Contractor believes constitutes extra work (including non-construction work), until all Claims and Disputes regarding entitlement or cost of such work are resolved.
AutoNDA by SimpleDocs
Performance of Disputed Work. Contractor shall continue to perform all Work, including any disputed Work, during the pendency of a Dispute concerning Contractor’s entitlement to a Change Order or the relief due Contractor pursuant to a Directive Letter or VPRA-Directed Change. Contractor’s continued performance in accordance with this Section 14.18 of these General Terms and Conditions will be without prejudice to any pending Claim.
Performance of Disputed Work. If TxDOT refuses to issue a Change Order based on Integrator’s request, Integrator shall nevertheless perform all work as specified by Directive Letter, and shall have the right to submit the issue to dispute resolution pursuant to Section 19. Integrator shall maintain and deliver to TxDOT, upon request, contemporaneous records, meeting the requirements of Section 13.10, for all work performed which Integrator believes constitutes extra work (including non-construction work), until all Disputes regarding entitlement or cost of such work are resolved.
Performance of Disputed Work. If TxDOT refuses to issue a Change Order based on Fabricator’s request, Fabricator shall nevertheless perform all work as specified by Directive Letter, and shall have the right to submit the issue to dispute resolution pursuant to Section 16. Fabricator shall maintain and deliver to TxDOT, upon request, contemporaneous records, meeting the requirements of Section 11.1.5, for all work performed which Fabricator believes constitutes extra work (including non-construction work), until all Disputes regarding entitlement or cost of such work are resolved.

Related to Performance of Disputed Work

  • Performance of Work The Work shall be constructed in a good and workmanlike manner substantially in accordance with the Construction Plans. The Work shall be subject, at the option of Landlord, to the inspection of Landlord, Landlord's Architect and Landlord's General Contractor from time to time, during the period in which the Work is being performed, provided that such inspection does not unreasonably interfere with the completion of the Work. If such inspections reveal that any of the Work is not being constructed substantially in conformance with the provisions of this Agreement or the Final Plans, Tenant at its expense shall correct same forthwith. Only new, first class materials shall be used in the performance of the Work. At all times during the construction of the Work, it shall be Tenant's responsibility to cause each of Tenant's contractors and subcontractors to maintain protection of the Premises in such a manner as to prevent any damage to the Work, or to adjacent property and improvements by reason of the performance of the Work. Tenant's contractor and subcontractors shall properly secure the Premises, including, to the extent required, the furnishing of temporary guard rails and barricades. Landlord for good cause shall have the right to require Tenant to terminate any construction work at any time being performed by or on behalf of Tenant in the Premises, and to require that any contractor or subcontractor, or any employee of same, leave the Building. Upon written notification, setting forth in reasonable detail such good cause, from Landlord to Tenant to cease any work, Tenant shall forthwith remove from the Premises all agents, employees and contractors of Tenant performing such work until such time as Landlord shall have given its written consent for the resumption of such construction work (such consent not to be unreasonably withheld or delayed), and Tenant shall have no claim for damages of any nature whatsoever against Tenant in connection therewith.

  • Performance of the Work The Contractor shall perform all of the Work required for the complete and prompt execution of everything described or shown in, or reasonably implied from the Contract Documents for the above referenced Project.

  • Performance while Dispute is Pending Notwithstanding the existence of a dispute, the Supplier must continue without delay to carry out all of its responsibilities under the Contract that are not affected by the dispute. If the Supplier fails to continue without delay to perform its responsibilities under the Contract, in the accomplishment of all undisputed work, the Supplier will bear any additional costs incurred by Sourcewell and/or its Participating Entities as a result of such failure to proceed.

  • Finality of Disputes 13.1.1 Except as otherwise specifically provided for in this Agreement, no claim may be brought for any dispute arising from this Agreement more than twelve (12) months from the date the occurrence which gives rise to the dispute is discovered or reasonably should have been discovered with the exercise of due care and attention.

  • Notice of Dispute The party wishing to commence the dispute resolution process must give written notice (Notice of Dispute) to the other parties of: