Progress Updates to CPM Schedule Sample Clauses

Progress Updates to CPM Schedule. After approval by Owner of the baseline CPM Schedule described in Section 5.3A, Contractor shall manage and update (no less frequently than twice per month) the CPM Schedule. Each updated CPM Schedule shall meet the requirements of Section 5.3A, and in addition shall (i) at a minimum, be prepared with the same level of detail as the baseline CPM Schedule, (ii) reflect the Work as actually performed or as forecasted, and (iii) show any other information requested by Owner. Contractor shall submit to Owner current updates to the CPM Schedule on a periodic basis, which shall be submitted with each Progress Report and Invoice. Contractor shall promptly correct any errors or inconsistencies in the updates to the CPM Schedule identified to Contractor by Owner and resubmit a corrected update for Owner’s review.
AutoNDA by SimpleDocs
Progress Updates to CPM Schedule. After approval by Owner of the baseline CPM Schedule described in Section 5.3.1, Contractor shall manage and update (no less frequently than once every four (4) weeks) the CPM Schedule with Primavera, P6 using the critical path method to show actual progress and the current forecast to complete the Work. Each updated CPM Schedule shall meet the requirements of Section 5.3.1, and in addition shall (i) at a minimum, be prepared with the same level of detail as the baseline CPM Schedule, (ii) show the baseline CPM Schedule, (iii) for each activity completed, show the actual start and finish dates for each such completed activity, (iv) for each activity started but not yet completed, show the actual start date for each such activity, the progress of Work for each such activity and forecasted completion date for each such activity, (v) for each activity not yet started, show the forecasted start and completion date for each such activity, (vi) show the actual costs incurred and to be incurred; (vii) show the man-hours expended and the projected manpower to be used per activity, showing the number of personnel, the positions and titles of such personnel, and a general description of the Work being performed, (viii) show the forecasted date of achievement of Mechanical Completion, Substantial Completion and Final Completion of the Project, and (ix) update the CPM Schedule with all other information shown in the baseline CPM Schedule, reflecting the Work as actually performed or as forecasted, including manhours for each activity. Contractor shall submit to Owner current updates to the CPM Schedule every four (4) weeks. Contractor shall promptly correct any errors or inconsistencies in the updates to the CPM Schedule identified to Contractor by Owner and resubmit a corrected update for Owner’s review.

Related to Progress Updates to CPM Schedule

  • Progress Update Information included with the annual Data Access Request (DAR) renewal or Closeout summarizing the analysis of controlled-access datasets obtained through the DAR and any publications and presentations derived from the work.

  • Updates to Schedules Should any of the information or disclosures provided on any of the Schedules attached hereto become outdated or incorrect in any material respect, the Borrower shall promptly provide the Agent in writing with such revisions or updates to such Schedule as may be necessary or appropriate to update or correct same; provided, however, that no Schedule shall be deemed to have been amended, modified or superseded by any such correction or update, nor shall any breach of warranty or representation resulting from the inaccuracy or incompleteness of any such Schedule be deemed to have been cured thereby, unless and until the Required Banks, in their sole and absolute discretion, shall have accepted in writing such revisions or updates to such Schedule.

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • Shift Schedule The words "shift schedule" when used in this Agreement shall mean a timetable of the shifts and off days assigned to a position or group of positions which commences at the beginning of a pay period and includes one complete rotation of said shifts.

  • Detailed Description of Services / Statement of Work Describe fully the services that Contractor will provide, or add and attach Exhibit B to this Agreement.

  • Progress Report By March 1 of each year, ***** will submit a written annual report to Stanford covering the preceding calendar year. The report will include information sufficient to enable Stanford to satisfy reporting requirements of the U.S. Government and for Stanford to ascertain progress by ***** toward meeting this Agreement’s diligence requirements. Each report will describe, where relevant: *****’s progress toward commercialization of Licensed Product, including work completed, key scientific discoveries, summary of work-in-progress, current schedule of anticipated events or milestones, market plans for introduction of Licensed Product, and significant corporate transactions involving Licensed Product. ***** will specifically describe how each Licensed Product is related to each Licensed Patent.

  • Updates “Updates” are changes that do not require a change to the established Centralized Contract terms and conditions. Updates may include: Centralized Contract changes and updates made in accordance with the previously approved pricing formula (e.g. discount from list price); adding new products or services within the established, previously approved pricing structure; lowering pricing of products or services already on Contract, deleting products or services available through the Centralized Contract, adding product or service that do not fall under the previously established price structure or discounts under the Contract, re-bundled products, and other updates not listed above that are deemed to be in the best interest of the State and do not result in a change to the established Centralized Contract terms and conditions. Updates must be submitted to OGS for review, and must be accompanied by a justification of reasonableness of price if the change results in a change in pricing methodology. OGS will notify Contractor in writing if approved.

  • Schedule Updates the Contractor agrees to maintain the Work duration schedule updates on an ongoing basis and, when the County requests it, include the updates in its payment request. The Contractor may be required to submit a narrative report with each monthly update which shall include a description of current and anticipated problem areas, delaying factors and their impact, and an explanation of corrective action taken or proposed. Failure to do so may be considered a material breach of the Contract. Any additional or unanticipated costs or expense required to maintain the schedules shall be solely the Contractor’s obligation and Contractor agrees not to charge the County.

  • Modifications and Updates to the Wire Center List and Subsequent Transition Periods 5.4.6.1 In the event AT&T identifies additional wire centers that meet the criteria set forth in Sections 5.4.2.1 or 5.4.2.2 above, but that were not included in the Master List of Unimpaired Wire Centers or AT&T’s List of Unimpaired Wire Centers, AT&T shall include such additional wire centers in a CNL. Each such list of additional wire centers shall be considered a Subsequent Wire Center List. AT&T will follow any limitations on the frequency with which it may issue such lists and notification procedures set forth in applicable Commission orders. 5.4.6.2 TWTC shall have thirty (30) business days to dispute the additional wire centers listed on AT&T’s CNL. Absent such dispute, effective thirty (30) business days after the date of a AT&T CNL providing a Subsequent Wire Center List, AT&T shall not be required to provide DS1 and DS3 Dedicated Transport, as applicable, in such additional wire center(s), except pursuant to the self-certification process as set forth in Section 1.9.1 of this Attachment. 5.4.6.3 For purposes of Section 5.4.6.1 above, AT&T shall make available DS1 and DS3 Dedicated Transport that were in service for TWTC in a wire center on the Subsequent Wire Center List as of the thirtieth (30th) business day after the date of AT&T’s CNL identifying the Subsequent Wire Center List (Subsequent Embedded Base) until one hundred eighty (180) days after the thirtieth (30th) business day Version: 4Q06 Standard ICA 11/30/06 from the date of AT&T’s CNL identifying the Subsequent Wire Center List (Subsequent Transition Period). 5.4.6.4 The rates set forth in Exhibit B shall apply to the Subsequent Embedded Base during the Subsequent Transition Period. 5.4.6.5 No later than one hundred eighty (180) days from AT&T’s CNL identifying the Subsequent Wire Center List, TWTC shall submit an LSR(s) or spreadsheet(s) as applicable, identifying the Subsequent Embedded Base of circuits to be disconnected or converted to other AT&T services. 5.4.6.5.1 In the case of disconnection, the applicable disconnect charges set forth in this Agreement shall apply. 5.4.6.5.2 If TWTC chooses to convert DS1 and/or DS3 Dedicated Transport to special access circuits in existence as of the Effective Date of this Agreement, AT&T will include such DS1 and/or DS3 Dedicated Transport within TWTC’s total special access circuits, and apply any discounts to which TWTC is entitled from the transition period of 3/11/2006 to the conversion date. Conversions will be subject to the switch-as-is charge set forth in Exhibit A to this Attachment 2. 5.4.6.5.3 AT&T shall not impose disconnect or nonrecurring installation charges when transitioning the Subsequent Embedded Base of DS1 and DS3 Dedicated Transport in existence as of the Effective Date of this Agreement. 5.4.6.6 If TWTC fails to submit the LSR(s) or spreadsheet(s) for all of its Subsequent Embedded Base by one hundred eighty (180) days after the date of AT&T’s CNL identifying the Subsequent Wire Center List, AT&T will identify TWTC’s remaining Subsequent Embedded Base, if any, and will transition such circuits to the equivalent tariffed AT&T service(s), or in the case of Georgia, to the equivalent 271 service(s) set forth in Exhibit 1. In the states of Florida, Kentucky, Mississippi and South Carolina, those circuits identified and transitioned by AT&T shall be subject to the applicable disconnect charges as set forth in this Agreement and the full nonrecurring charges for installation of the equivalent tariffed AT&T service as set forth in AT&T’s tariffs. In the states of Alabama, Georgia, North Carolina and Tennessee, those circuits identified and transitioned by AT&T shall be subject to the applicable switch-as-is rates set forth in Exhibit A of Attachment

  • BACKGROUND STATEMENT The Borrower has requested that the Lenders make available a revolving credit facility in the aggregate principal amount of $400,000,000. The Lenders are willing to make available to the Borrower the revolving credit facility provided for herein subject to and on the terms and conditions set forth in this Agreement.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!