Common use of Re-Tests Clause in Contracts

Re-Tests. 7.5.1 Where the Metering System has failed the Proving Test, the Generator must undertake a re-test no later than five (5) Business Days after the failed Proving Test in accordance with the timetable set out at paragraph 7.4 of this MOF.

Appears in 2 contracts

Samples: Private Network CFD Agreement, Private Network CFD Agreement

AutoNDA by SimpleDocs

Re-Tests. 7.5.1 Where the Metering System has failed the Proving Test, the Generator must undertake a re-re- test no later than five (5) Business Days after the failed Proving Test in accordance with the timetable set out at paragraph 7.4 of this MOF.

Appears in 1 contract

Samples: Private Network CFD Agreement

AutoNDA by SimpleDocs

Re-Tests. 7.5.1 Where the Metering System has failed the Proving Test, the Generator must undertake a re-test no later than five (5) Business Days after the failed Proving Test in accordance with the timetable set out at paragraph 7.4 7.47.4 of this MOF.

Appears in 1 contract

Samples: Private Network CFD Agreement