Schedule Recovery Plans Sample Clauses

Schedule Recovery Plans. 9.8.1 If, during the performance of the Work, Contractor is delayed such that Mechanical Completion of a Unit is projected to be achieved after the Target Completion Date for such Unit (as indicated in the current Project Schedule) Owners may require Contractor to prepare a proposed plan that feasibly explains how Contractor will improve schedule progress to achieve Mechanical Completion for such Unit by its Target Completion Date (each such plan aRecovery Plan”), and Contractor will participate in such meetings as Owners may reasonably require in connection with the preparation and implementation of such Recovery Plan. 9.8.2 Contractor will submit its proposed Recovery Plan to Owners within a reasonable period of time (considering the complexity of the issues involved) after Owners provide notice to Contractor’s Authorized Representative, but not more than thirty (30) Days after notification by Owners of such request for a Recovery Plan; provided that in the event Contractor does not submit a Recovery Plan within thirty (30) Days of Owners’ request, Owners shall be entitled to withhold future provisional payments of the portion of the Schedule Earned Fee with respect to the Unit in question until a Recovery Plan is approved (approval not to be unreasonably withheld). Upon receipt of such proposed Recovery Plan, Owners will review and comment upon the same within ten (10) Days. Contractor will accept and incorporate Owners’ reasonable comments and resubmit, within ten (10) Days of receiving such comments, the proposed Recovery Plan to Owners. Contractor will implement the approved Recovery Plan, and will use commercially reasonable efforts to adhere to such Recovery Plan in order to achieve Mechanical Completion of such Unit by the Target Completion Date for such Unit. Owners’ approval of the Recovery Plan will not relieve Contractor of any of its obligations under this Agreement. Additional costs associated with implementing an approved Recovery Plan shall be Reimbursable Costs, and any schedule revisions set forth in an approved Recovery Plan shall be promptly incorporated into the Project Schedule. 9.8.3 Owners may request that Contractor accelerate any aspect of the Work. Contractor shall use commercially reasonable efforts to meet Owners’ request.
AutoNDA by SimpleDocs

Related to Schedule Recovery Plans

  • Disaster Recovery Plan Contractor agrees that upon request of System Agency, Contractor shall provide copies of its most recent business continuity and disaster recovery plans.

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.

  • Shift Schedule The words "shift schedule" when used in this Agreement shall mean a timetable of the shifts and off days assigned to a position or group of positions which commences at the beginning of a pay period and includes one complete rotation of said shifts.

  • Business Plans As promptly as possible, but in no event later than July 15, 2010 (and, as applicable, with current information as of June 30, 2010) the Manager shall deliver to the Initial Member written plans (each, a “Business Plan”) detailing the strategy to be used by it in managing and disposing of the assets of the Company in respect of all of the Loans for achieving the Company’s purposes with respect thereto, in conformance with the Servicing Standard, based, to the extent appropriate, on information gathered by the Company with respect to the Loans, which shall include (i) individual Business Plans for each of the ten (10) largest Loans based on their Unpaid Principal Balance as of the Cut-Off Date (as set forth on the Loan Schedule), and (ii) a consolidated Business Plan covering all Loans (a “Consolidated Business Plan”). With respect to the first such Business Plans and Consolidated Business Plan, the Manager shall meet with the Initial Member as reasonably requested by the Initial Member from time to time during the thirty (30) Business Days following the Initial Member’s receipt of the same, to review and discuss such Business Plans and Consolidated Business Plan, including changes thereto suggested by the Initial Member. Within thirty (30) Business Days following expiration of such review period, the Manager will deliver to the Initial member a final version of such Business Plans and Consolidated Business Plan reflecting such changes as the Manager considers to be appropriate in light of its discussions with the Initial Member during such review period. The Manager shall thereafter review and revise each Business Plan and Consolidated Business Plan as the circumstances may require, and in any event provide periodic updates to such Business Plans (and for each such update, the same shall cover the ten (10) largest Loans based on their Unpaid Principal Balance as of the time of such update) and Consolidated Business Plan to the Initial Member, in January (current as of December 31 of the immediately preceding year) and July (current as of June 30 of such year) of each year, commencing in January 2011, with each such periodic update to de delivered as part of the Monthly Reports due at such time pursuant to Section 7.4(b), Upon reasonable notice by the Initial Member, the Company shall make its personnel who are familiar with such Business Plans and Consolidated Business Plans available during normal business hours for the purposes of discussing such Business Plans and Consolidated Business Plans with representatives of the Initial Member and responding to questions therefrom. (a) Each Business Plan and Consolidated Business Plan will set forth a strategy for the disposition of the Loans addressed thereby which strategy may consist of one or more of the following: (i) the pay-off of Loans at a discount; (ii) modifications of the related note and/or mortgage, including reductions in the mortgage loan interest rate, reductions in the principal balance and rescheduling principal payments; (iii) foreclosure upon the related Underlying Collateral (or acquisition thereof by deed in lieu of foreclosure) and subsequent sale thereof; (iv) assumptions of Loans by new borrowers; (v) repairs to and, if applicable, completion of construction of the related Underlying Collateral, with a view towards selling such Underlying Collateral or the Loan secured thereby; (vi) sale of a Loan, either singly or in pools, before or after restructuring; and (vii) any other method of work-out, rehabilitation and disposition consistent with the Servicing Standard and other general duties of the Company specified in this Agreement. (b) Each Business Plan and Consolidated Business Plan will set forth a strategy for the disposition of each related Acquired Property which strategy may consist of one or more of the following: (i) the sale or leasing of the Acquired Property in whole or in parts, or in pools; (ii) making repairs to and, if applicable, completion of construction the Acquired Property or making changes to the Acquired Property so that it may be used for uses other than its current use, with a view toward selling the Acquired Property; (iii) rehabilitation or improvement and, if applicable, completion of construction of the Acquired Property, with a view toward selling the Acquired Property; (iv) continued leasing or sales activity with respect to the Acquired Property available for leasing or sale (in whole or in part) at the time it is transferred to a Ownership Entity; and (v) maintenance, landscaping and general upkeep of the Acquired Property. (c) Each Business Plan or Consolidated Business Plan shall contain the Company's estimate of the present value of the net amount that is recoverable with respect to each related Loan and projected Working Capital Expenses with respect thereto, and, in reasonable detail, the manner of calculation of such estimates. The Consolidated Business Plan shall include projected financials including statements of income, assets, and cash flows for the Company. Such cash flow projections shall, for the Consolidated Business Plan and each update thereto, include an Excel model of projected cash flows by month, as of June 30 and December 31 of each year (or, in the case of the initial Consolidated Business Plan, as of the date of preparation and delivery thereof) and covering a period not less than the upcoming 6 months, including projected monthly cash inflows on the Loans and REO, projected Excess Working Capital Advances and/or Discretionary Funding Advances, projected outflows of Servicing Expenses, projected Funding Draws, projected Working Capital Reserve levels, projected net monthly cash available for deposit into the Defeasance Account, and the amount and allocation of any projected distributions to Initial Member and Private Owner.

  • Budget Schedule Subrecipient agrees that the expenditures of any and all funds under this Contract will be in accordance with the Budget Schedule, a copy of which is attached hereto as Attachment C, and which by this reference is incorporated herein and made a part hereof as if fully set forth.

  • Disaster Recovery and Business Continuity The Parties shall comply with the provisions of Schedule 5 (Disaster Recovery and Business Continuity).

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Flexible Work Schedule A flexible work schedule is any schedule that is not a regular, alternate, 9/80, or 4/10 work schedule and where the employee is not scheduled to work more than 40 hours in the "workweek" as defined in Subsections F. and H., below.

  • Attachment C, Standard State Provisions for Contracts and Grants Attachment C is hereby deleted in its entirety and replaced by the Attachment C December 15, 2017 attached to this Amendment. Child Support (Applicable to natural persons only; not applicable to corporations, partnerships or LLCs). Contractor is under no obligation to pay child support or is in good standing with respect to or in full compliance with a plan to pay any and all child support payable under a support order as of the date of this amendment.