Schedule Revisions. If the sequence of construction differs significantly, as determined by the District Representative and/or Architect, from the Contract Schedule, Contractor shall submit within fifteen (15) days a revised schedule to the District Representative for approval. When a requested or proposed change to the Work will have an impact on the critical path, Contractor shall submit a schedule fragment showing this impact. If the requested or proposed change is accepted by District, the schedule fragment shall be incorporated into the Contract Schedule. Time extensions will be considered only to the extent there is insufficient remaining float to accommodate these changes, and pursuant to Section 14 of these General Conditions. No additional cost will be allowed for the incorporation of approved changes into the Contract Schedule. Should Contractor, after approval of the Contract Schedule, intend to change its plan of construction, it shall submit its requested revisions to the District Representative, along with a written statement of the revision, including a description of the logic for rescheduling the Work, methods of maintaining adherence to intermediate milestones and other specific dates and the reasons for the revisions. If the requested changes are acceptable to the District Representative, they will be incorporated into the Contract Schedule in the next reporting period. Schedule revisions shall be submitted at least seven (7) days prior to the date of submission of update information. District will have seven (7) days to review the revisions.
Schedule Revisions. 6 If the sequence of construction differs significantly, as determined by the District’s Representative, from the 7 Construction Schedule, the Entity shall submit within fifteen (15) days a revised schedule to the District’s 8 Representative for acceptance. Updating the Construction Schedule to reflect actual progress shall not be 9 considered revisions to the Construction Schedule. 10 11 When a Proposed Change Order is issued which has the potential to impact specified completion dates, a 12 Network Window shall be prepared by the Entity to reflect the impact of such changes as expeditiously as is 13 reasonably possible in light of the nature, quantity and timing of potential changes. The District’s 14 Representative will promptly review and act on the Network Window. If the Network Window has been 15 accepted by the Owner and the Entity permitted by the Owner to proceed with the Proposed Change Order, the 16 Network Window shall be incorporated into the Construction Schedule. Time extensions will be considered 17 only to the extent there is insufficient remaining float to accommodate these changes, and pursuant to Article 18 14 of these General Construction Terms and Conditions. No additional cost beyond that provided in Article 15 19 will be allowed for the incorporation of approved Proposed Change Orders into the Construction Schedule, 20 except that, if Owner Initiated Changes, as defined and described in Section 15.02, exceed twelve percent 21 (12%) of the Total Base Rent, the Entity shall be entitled to compensation for its added costs of updating and 22 maintaining the schedule as a result of such changes. Such added costs must be properly substantiated by 23 supporting data. 24 25 Should the Entity, after acceptance of the Construction Schedule, intend to change its plan of Construction, 26 it shall submit their requested revisions to the District’s Representative, along with a written statement of 27 the revision, including a description of the logic for rescheduling the Work, methods of maintaining 28 adherence to Intermediate milestones and other specific dates and the reasons for the revisions. If the 29 requested changes are acceptable to the District’s Representative, they will be incorporated into the 30 Construction Schedule in the next reporting period. 31 32 Schedule revisions shall be submitted at least seven (7) days prior to the date of submission of update 33 information. The Owner will have seven (7) days to review the revisions. 34
Schedule Revisions. 5.1.4.1 If the sequence of construction differs significantly, as determined by PM/CM, from the CONTRACT SCHEDULE, CONTRACTOR shall submit within five (5) days a revised schedule to PM/CM for acceptance.
5.1.4.2 When a proposed CHANGE ORDER is issued which has the potential to impact specified completion dates, the CHANGE ORDER request shall include a description of the impact of such changes. If approved, it shall be incorporated into the CONTRACT SCHEDULE. Time extensions will be considered only to the extent there is insufficient remaining float to accommodate these changes, and pursuant to Section 6 of the CONTRACT DOCUMENTS.
5.1.4.3 Should CONTRACTOR, after acceptance of the CONTRACT SCHEDULE, intend to change its plan of construction, it shall submit its requested revisions to PM/CM, along with a written statement of the revision, including a description of the logic for rescheduling the work, methods of maintaining adherence to intermediate milestones and other specific dates and the reasons for the revisions. If the requested changes are acceptable to PM/CM, they will be incorporated into the CONTRACT SCHEDULE in the next reporting period.
5.1.4.4 Schedule revisions shall be submitted at least five (5) days prior to the date of submission of update information. PM/CM will have five (5) days to review the revisions.
Schedule Revisions. The implementation of revised schedule logic and/or activity duration estimates for updating a schedule whether furnished by the DBE or the District do not constitute an extension of Contract Time, relaxation of Project Milestones or basis for a change to the GMP. Such revisions are for the purpose of maintaining the accuracy of the schedule’s representation of the work to be accomplished and to present best duration estimates for work yet to be performed.
Schedule Revisions. If the assumptions and/or circumstances used to create the Pricing Schedule are found to be incorrect or misstated or to have substantially changed, then HP and Customer shall meet and in good faith negotiate equitable changes to the Schedule, which may include, but is not limited to, adjusting rates and/or service level commitments, in adherence with the NASPO ValuePoint Master Agreement. Any changes will only have effect for the future without any retroactive effect on any rates or charges that have already been invoiced. HP will not be liable for failure to meet any obligations in this Schedule to the extent such failure is due to delayed, false, or inaccurate information provided by Customer.
Schedule Revisions. The implementation of revised schedule logic and/or activity duration estimates for updating the contract schedule or other interim schedule whether furnished by the Design/Builder or the District do not constitute an extension of Contract Time, relaxation of Contract Milestones or basis for a change to the Stipulated Sum. Such revisions are for the purpose of maintaining the accuracy of the Contract Schedule’s representation of the work to be accomplished and to present best duration estimates for work yet to be performed. In updating the Contract Schedule, the Design/Builder shall make no modifications to Activity ID numbers in the accepted contract schedule, schedule calculation rules/criteria, or the Activity Coding Structure provided by the Construction Project Manager without the explicit written permission of the District, which permission the District may withhold at its sole discretion.
Schedule Revisions. 6.5.6.1. Schedule Revisions are defined as any changes to schedule activities or logic other than the updating of actual start and completion dates, percent complete or remaining duration. The Contractor shall revise the Baseline Schedule when the Construction Manager determines that it is no longer useful as a status and control mechanism, when a change or delay impacts the Contractor’s timing and sequence of the work, or when the Contractor has submitted logic changes that affect critical or near critical activities as determined by the Construction Manager. Schedule Revisions must be submitted in accordance with the Specification for the Construction Manager’s review and acceptance. After the Construction Managers accepts the schedule revision, the Contractor shall incorporate the accepted revision into the next Monthly Schedule Update. Schedule Revisions are not to be used to change milestones dates of Contract Time.
Schedule Revisions. It is understood by the Parties that certain tasks involved in the performance of the Services may need to be confirmed and/or modified as the Services progress and Schedule A and/or Schedule B may require amendment to meet the Client's objectives. Schedule A and/or Schedule B may be revised by agreement between the Parties, provided that the Party suggesting the revision communicates the same in a signed writing to the other Party, and within ten days thereafter, the other Party indicates acceptance thereof in a signed writing. In the event that the revision has an impact on the Fees in Schedule A or Schedule B, Encode shall promptly advise the Client of adjustments thereto. No change to the Services in Schedule A or Schedule B shall be implemented before Encode has received written concurrence from Client to the change to the Services in Schedule A or Schedule B and to any consequent change in the Fees in Schedule A or Schedule B.
Schedule Revisions. Revisions to Exhibit E to show adjustments to the Schedule shall be prepared by Tenant and become a part of this Agreement, subject to reasonable objections of Landlord that are received in writing by Tenant no later than five (5) business days after Landlord’s receipt of such revisions. No other revision of the Schedule shall become effective unless agreed upon in writing by both parties. The parties may agree to a revision to Exhibit E, which shall then become binding upon the parties, but reserving, however, the right to contest the allocations of the delay between the parties.
IV. Coordination