Schedule Updating Sample Clauses

Schedule Updating. Provide regular updates of the schedule as construction progresses. Identify potential variances between scheduled and probable completion dates. Review schedule for Work not started or incomplete and recommend to the Owner and subcontractors adjustments in the schedule to meet the scheduled completion date. Provide two (2) copies of the monthly summary reports for the review and approval of the Owner of such updating activities and document all changes in the schedule.
AutoNDA by SimpleDocs
Schedule Updating. Monthly Progress Reports and Projections The XXXX Contractor shall update the schedule monthly along with the monthly progress report. Each update shall show actual dates of activities started and completed; the percent of Work completed to date on each activity started, but not yet completed; and the status of procurement of critical materials. The updated schedule data shall be submitted to CPRA’s Project Manager electronically. The XXXX Contractor also shall provide updated activity number and total float/early start sorts, a 60 Working Day look-ahead bar chart by early start, and a narrative report. The narrative report shall include a description of problem areas, current and anticipated delaying factors and their estimated impact on performance of other activities and
Schedule Updating. Immediately following each progress meeting, where revisions to the Work Progress Schedule (WPS) have been made or recognized, revise the progress schedule. Reissue revised colored copies of the WPS concurrently with minutes of each meeting.
Schedule Updating. 1. The schedule shall be updated on a regular basis until the Certificate of Acceptance has been issued. The Contractor shall meet with the County at regularly scheduled update meetings to review actual progress made through the date of the schedule update meeting, including the date activities started and/or completed, and the percentage of work completed on each activity started and/or completed. The date of each scheduled update meeting shall be mutually agreed upon by the Contractor and the County and shall be reflected on the schedule. 2. In case of disagreements at the schedule update meeting concerning actual progress to date, the County's determination shall govern. 3. Each updated schedule shall be forwarded to the County and will include a diskette containing the back-up of the schedule and three

Related to Schedule Updating

  • Schedule Updates the Contractor agrees to maintain the Work duration schedule updates on an ongoing basis and, when the County requests it, include the updates in its payment request. The Contractor may be required to submit a narrative report with each monthly update which shall include a description of current and anticipated problem areas, delaying factors and their impact, and an explanation of corrective action taken or proposed. Failure to do so may be considered a material breach of the Contract. Any additional or unanticipated costs or expense required to maintain the schedules shall be solely the Contractor’s obligation and Contractor agrees not to charge the County.

  • Disclosure Updates Promptly and in no event later than 5 Business Days after obtaining knowledge thereof, notify Agent if any written information, exhibit, or report furnished to the Lender Group contained, at the time it was furnished, any untrue statement of a material fact or omitted to state any material fact necessary to make the statements contained therein not misleading in light of the circumstances in which made. The foregoing to the contrary notwithstanding, any notification pursuant to the foregoing provision will not cure or remedy the effect of the prior untrue statement of a material fact or omission of any material fact nor shall any such notification have the effect of amending or modifying this Agreement or any of the Schedules hereto.

  • Updating At the end of each calendar quarter in which there occurs any event that materially affects the accuracy of the information contained in the Certification or, if applicable, Standard Form-LLL, Qualified Producer shall file with TVA an initial or new Standard Form-LLL with such new information or modifications as are necessary to correct any inaccuracies in the information originally declared and certified.

  • Schedule The Work shall be performed as expeditiously as possible in conformity with the schedule requirements contained herein and in the Statement of Work. The draft and final versions of all deliverables shall be submitted by the dates specified in the Exhibit A Schedule and Project Period noted in Item No. 7 of this Agreement. It is understood and agreed that the delivery of the draft and final versions of such deliverables by the Contractor shall occur in a timely manner and in accordance with the requirements of the Exhibit A Schedule.

  • Updates to Schedules Should any of the information or disclosures provided on any of the Schedules attached hereto become outdated or incorrect in any material respect, the Borrower shall promptly provide the Agent in writing with such revisions or updates to such Schedule as may be necessary or appropriate to update or correct same; provided, however, that no Schedule shall be deemed to have been amended, modified or superseded by any such correction or update, nor shall any breach of warranty or representation resulting from the inaccuracy or incompleteness of any such Schedule be deemed to have been cured thereby, unless and until the Required Banks, in their sole and absolute discretion, shall have accepted in writing such revisions or updates to such Schedule.

  • Software Updates XXXXX agrees to keep current with software licensed from Skyward and will install new versions on a timeline approved by XXXXX governance. This timeline will be communicated by NWRDC to the Districts.

  • BACKGROUND STATEMENT The Borrower has requested that the Lenders make available a revolving credit facility in the aggregate principal amount of $400,000,000. The Lenders are willing to make available to the Borrower the revolving credit facility provided for herein subject to and on the terms and conditions set forth in this Agreement.

  • Update Each year the Plant Training Committee shall prepare an Update that reviews the Findings and modifies them based on changed circumstances, measures the success of the Training Program against its objectives and modifies the Training Program accordingly.

  • Alternative Work Schedules Employees may request alternative work schedules such as a nine (9) day - 80 hour two week schedule or a four (4) day - 40 hour week schedule. Management will respond to an employee's request within 15 calendar days. Any changes from existing work schedules will be based on the needs of the service as determined by Management. Employees covered by the Fair Labor Standards Act will not be placed on alternate work schedules that mandate the payment of overtime under the Act.

  • Alternative Work Schedule An alternate forty (40) hour work schedule (other than five (5) uniform and consecutive eight (8) hour days in a seven (7) day period), or for hospital personnel an eighty (80) hour workweek in a fourteen (14) day period and other mutually agreed upon schedules that comply with applicable federal and state law. Employee work schedules normally include two (2) consecutive days off.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!