Scheduled Plant Outages Sample Clauses

Scheduled Plant Outages. The Seller shall, not less than one (1) month prior to the Commercial Operation Date and on an annual basis for the remainder of the Term, at least one (1) month prior to the anniversary of the Commercial Operation Date provide to the Operating Committee its proposals for Scheduled Plant Outages, including any planned interruption or reduction of the Power Plant’s Contracted Capacity for the remainder of the Contract Year and the forthcoming Contract Year, as appropriate. Such schedule shall include: the number of expected Scheduled Plant Outages and the extent of expected reductions in the Contracted Capacity of the Power Plant as a result of such Scheduled Plant Outages; and the estimated dates and duration of each Scheduled Plant Outage. The Operating Committee shall, upon receipt of the proposals contemplated in clause 12.8.1, meet and coordinate the timing of Scheduled Plant Outages for the forthcoming Contract Year, at least as close to one (1) month prior to the commencement of that Contract Year as possible. If there is a requirement to change the dates of any Scheduled Plant Outage, the Seller shall provide NamPower with written notice at least twenty-eight (28) days in advance of the relevant Scheduled Plant Outage. NamPower may approve such a request for a change of date within five (5) days of such request. Such an approval shall not be unreasonably withheld or delayed. Subject to having complied with the foregoing provisions of this Clause 12.8 (Scheduled Plant Outages), the Seller shall be entitled to remove any Unit and/or the Power Plant from service at the agreed date and time for the Scheduled Plant Outage. The Seller shall be responsible for all costs incurred by it in connection with or arising from any scheduled maintenance carried out by it or on its behalf on the Power Plant. NamPower shall not be entitled to any payment and/or indemnification and/or reimbursement from the Seller in connection with any Scheduled Plant Outages.
AutoNDA by SimpleDocs
Scheduled Plant Outages. 12.7.1 The Seller shall, not less than one (1) Month prior to the Commercial Operation Date and on an annual basis for the remainder of the Term, at least one (1) Month prior to the anniversary of the Commercial Operation Date provide to ZESCO its proposals for Scheduled Plant Outages, including any planned interruption or reduction of the Power Plant’s capacity for the remainder of the Contract Year or the forthcoming Contract Year, as appropriate. Such schedule shall include:

Related to Scheduled Plant Outages

  • Scheduled Outages (a) Commencing at least sixty (60) days before Initial Synchronization and throughout the Delivery Term, Seller shall, no later than January 1, April 1, July 1 and October 1 of each year, submit to SCE, using the Web Client, Seller’s schedule of proposed planned outages (“Outage Schedule”) for the subsequent twenty-four month period.

  • Scheduled Downtime For the purposes of this Agreement, Scheduled Downtime will mean those hours, as determined by us but which will not occur between the hours of 9:00 AM and 5:00 PM Pacific Time, Monday through Friday without your authorization or unless exigent circumstances exist, during which time we will perform scheduled maintenance or adjustments to the Environment. We will use our best efforts to provide you with at least twenty-four (24) hours of notice prior to scheduling Scheduled Downtime.

  • Contract Duration Actual Contract Duration: …………………………………………………………………………. Description / Performance Very poor (1) Poor (2) Fair (3) Good (4) Excellent (5) Quality of office administration Quality of site management Competence of xxxxxxx Co-operation during contract Quality of workmanship Quality of materials Programme management Rectification of condemned work Tidiness of site Adequacy of equipment Adequacy of labour force Procurement of materials Labour relations Any other remarks considered necessary to assist in evaluation of the contractor? ................................................................................................................................................................................... ...................................................................................................................................................................................

  • Scheduled Maintenance Maintenance window for disruptive work to Service will be limited 12:00 A.M. to 4:00 A.M., Central Daylight Time (CDT), any day with requirement of one (1) calendar week notification to Customer prior to maintenance. LightEdge will send an e-mail notification of such disruptive maintenance to Service to Authorized Contacts of Customer. Once notification is sent to Customer this will be considered a “Scheduled Maintenance”. Any Service SLAs will NOT apply during a Scheduled Maintenance.

  • Unscheduled Maintenance Unscheduled maintenance may be required to resolve issues that are critical for Customer and/or performance of the Cloud Services. Druva will use its commercially reasonable efforts to notify Customer at least six (6) hours prior to the unscheduled maintenance.

  • Planned Outages Seller shall schedule Planned Outages for the Project in accordance with Good Industry Practices and with the prior written consent of Buyer, which consent may not be unreasonably withheld or conditioned. The Parties acknowledge that in all circumstances, Good Industry Practices shall dictate when Planned Outages should occur. Seller shall notify Buyer of its proposed Planned Outage schedule for the Project for the following calendar year by submitting a written Planned Outage schedule no later than October 1st of each year during the Delivery Term. The Planned Outage schedule is subject to Buyer’s approval, which approval may not be unreasonably withheld or conditioned. Buyer shall promptly respond with its approval or with reasonable modifications to the Planned Outage schedule and Seller shall use its best efforts in accordance with Good Industry Practices to accommodate Xxxxx’s requested modifications. Notwithstanding the submission of the Planned Outage schedule described above, Seller shall also submit a completed Outage Notification Form to Buyer no later than fourteen (14) days prior to each Planned Outage and all appropriate outage information or requests to the CAISO in accordance with the CAISO Tariff. Seller shall contact Buyer with any requested changes to the Planned Outage schedule if Seller believes the Project must be shut down to conduct maintenance that cannot be delayed until the next scheduled Planned Outage consistent with Good Industry Practices. Seller shall not change its Planned Outage schedule without Buyer’s approval, not to be unreasonably withheld or conditioned. Seller shall use its best efforts in accordance with Good Industry Practices not to schedule Planned Outages during the months of July, August, September and October. At Buyer’s request, Seller shall use commercially reasonable efforts to reschedule Planned Outage so that it may deliver Product during CAISO declared or threatened emergency periods. Seller shall not substitute Energy from any other source for the output of the Project during a Planned Outage.

  • Forced Outages During any forced outage, the NYISO or Connecting Transmission Owner may suspend interconnection service to the Interconnection Customer to effect immediate repairs on the New York State Transmission System or the Distribution System. The NYISO shall use Reasonable Efforts to provide the Interconnection Customer with prior notice. If prior notice is not given, the NYISO shall, upon request, provide the Interconnection Customer written documentation after the fact explaining the circumstances of the disconnection.

  • Scheduled Hours Hours falling within an employee's scheduled tour.

  • Contract Work The provision of goods and services identified in the Contract constitute the contract work (Contract Work). Contractor shall perform the Contract Work pursuant to the terms of the Contract. Contractor shall furnish all labor, materials, equipment, tools, transportation, services, appliances, and appurtenances for the Contract Work in strict conformity with this Contract, within the time-period prescribed by the City.

  • Scheduled Overtime Scheduled overtime is overtime which is assigned by the end of the employee's last worked shift prior to the overtime assignment and which does not immediately precede or immediately follow a scheduled work shift. Unless notified otherwise in advance of the scheduled starting time of the scheduled overtime assignment, any employee who is scheduled to report for work and who reports as scheduled shall be assigned at least two (2) hours work. If work is not available, the employee may be excused from duty and paid for two (2) hours at the employee's appropriate rate. If the employee begins work but is excused from duty before completing two (2) hours of work, the employee shall be paid for two (2) hours at the employee's appropriate rate.