Right to suspend 2.1.1 Network Rail may serve a Suspension Notice where a Train Operator Event of Default has occurred and is continuing.
Owner’s Right to Suspend Work The Owner reserves the right, with or without the concurrence of the Design Professional, to suspend the Work at any time or from time to time at the Owner's sole discretion, upon giving Contractor five days advanced written notice thereof. If the Owner exercises this right and then resumes the Work covered hereby, Contractor shall be entitled upon timely claim to a Change Order for payment by Owner of any reasonable Actual Costs actually incurred by Contractor in connection with the suspension and resumption of the Work, as well as an extension in the time for performance of the Work to the extent Contractor is delayed by Owner's suspension, to include compensation based upon the rate for Time Dependent Overhead Costs. The Design Professional shall determine the time, which shall be binding upon both Owner and Contractor, as set forth in Section 3, Part 3.
City’s Right to Suspend for Convenience City may suspend all or any portion of Contractor’s performance under this Contract at its sole option and for its convenience for a reasonable period of time not to exceed six (6) months. City must first give ten (10) days’ written notice to Contractor of such suspension. City will pay to Contractor a sum equivalent to the reasonable value of the goods and/or services satisfactorily provided up to the date of suspension. City may rescind the suspension prior to or at six (6) months by providing Contractor with written notice of the rescission, at which time Contractor would be required to resume performance in compliance with the terms and provisions of this Contract. Contractor will be entitled to an extension of time to complete performance under the Contract equal to the length of the suspension unless otherwise agreed to in writing by the Parties.
STATE's Right to Suspend the Operations The STATE and/or the STATE's Authorized Representative has the authority to suspend portions or all of the operations due to causes including, but not limited to:
No Right to Subcontracting Subcontractor may not subcontract, either part or in whole, the Services authorized under this Agreement.
STATE'S RIGHT TO STOP THE WORK 3.3.1 If the Contractor fails to correct defective Work as required by Paragraph 13.2 or persistently fails to carry out the Work in accordance with the Contract Documents, the State, by a written order signed personally or by an agent specifically so empowered by the State in writing, may order the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of the State to the stop the Work shall not give rise to any duty on the part the State to exercise this right for the benefit of the Contractor or any other person or entity, except to the extent required by Subparagraph 6.1.3.
OWNER’S RIGHT TO STOP THE WORK If the Contractor fails to correct Work that is not in accordance with the requirements of the Contract Documents as required by Section 12.2 or repeatedly fails to carry out Work in accordance with the Contract Documents, the Owner may issue a written order to the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, the right of the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity.
Owner’s Right to Stop Work The Owner reserves the right, for itself and for any designated Construction Inspector retained by Owner, upon observation of apparent nonconforming Work, to immediately stop the affected Work. If the Work is later determined by the Design Professional to be in fact conforming Work, then Contractor shall be entitled upon timely claim to a Change Order for payment by Owner of any reasonable Actual Costs actually incurred by Contractor in connection with the stop Work order and resumption of the Work, as well as an extension in the time for performance of the Work to the extent Contractor is delayed by Owner's stop Work order. The Design Professional shall determine the time, which shall be binding upon both Owner and Contractor, as set forth in Section 3, Part 3.
City’s Right to Reject The City reserves the right to reject a certificate of insurance if Contractor’s insurance company is widely regarded in the insurance industry as financially unstable. This would include but is not limited to insurance companies with no less than AVIII rating in the A.M. Best insurance rating guide.
DISCHARGE OR SUSPENSION The Employer shall not discharge nor suspend any employee without just cause, but in respect to discharge or suspension shall give at least one (1) warning notice of a complaint against such employee to the employee, in writing, and a copy of the same to the Union, except that no warning notice need be given to an employee before he/she is discharged if the cause of such discharge is dishonesty, drinking alcoholic beverages or being under the influence of drugs or in illegal possession of drugs during the workday (including meal period) or drunkenness, recklessness resulting in serious accident while on duty, or the carrying of unauthorized passengers while on the job or offenses of equal seriousness. Except for serious accidents, a driver will not be removed from the payroll during an investigation of an accident. The driver can be assigned to non-driving work during this period. Before disciplinary action is taken, a meeting shall be held with the employee and the employee shall have the right to choose a Xxxxxxx who is readily available and on the premises. In the case of discharge for any offense other than the above mentioned, including suspension, the disciplinary action will be held in abeyance for two (2) weeks to give the Local Union the opportunity to intervene prior to the action being taken. The warning notice, suspension or discharge as herein provided shall not remain in effect for a period of more than nine (9) months from the date of said warning notice, suspension or discharge. Any disciplinary action must be by proper written notice to the employee and the Union affected. Disciplinary letters must be issued by the Company within ten (10) working days after the incident. Any employee may request an investigation as to his/her discharge or suspension. Should such investigation prove that an injustice has been done to an employee, he/she shall be reinstated. The C.P.A.P.G.C. or the impartial arbitrator shall have the authority to order full, partial or no compensation for time lost. Appeal from discharge or suspension must be taken within ten (10) days by written notice and a decision reached within thirty (30) days from the date of suspension or discharge. An employee shall be given a copy of any Company form or document signed by the employee if requested. The Company will not use absenteeism or accidents in conjunction with any other disciplinary action.