Termination in Consequence of Force Majeure Sample Clauses

Termination in Consequence of Force Majeure. ‌ If circumstances of Force Majeure have occurred that have materially affected the Work and have continued for a period of forty-five (45) days in the aggregate, and there is a corresponding delay in the schedule for performance and the Guaranteed Substantial Completion Date of forty-five (45) days in the aggregate caused by the Force Majeure, then, notwithstanding that Seller may by reason thereof have been granted an extension of the schedule for performance and the Guaranteed Substantial Completion Date, by Change Order, Buyer shall be entitled to provide notice of its intent to terminate this Agreement upon thirty (30) days notice to Seller. If at the expiration of such thirty (30)-day period such Force Majeure shall still continue, Buyer may elect to terminate this Agreement.
AutoNDA by SimpleDocs
Termination in Consequence of Force Majeure. If a Force Majeure shall have occurred that has affected Seller’s performance of its obligations hereunder and that has continued for a continuous period of thirty (30) days or more, then Seller shall be entitled to terminate the Agreement. Upon such termination for a Force Majeure, Buyer shall be responsible for making any and all payments up to the start of such Force Majeure event.
Termination in Consequence of Force Majeure. If circumstances of Force Majeure have occurred that have materially affected the Work and have continued for a period of forty-five (45) days in the aggregate, and there is a corresponding delay in the schedule for performance and the Guaranteed Substantial Completion Date of forty-five (45) days in the aggregate caused by the Force Majeure, then, notwithstanding that Contractor may by reason thereof have been granted an extension of the schedule for performance and the Guaranteed Substantial Completion Date by Change Order, Company shall be entitled to provide notice of its intent to terminate this Contract upon thirty (30) days notice to Contractor. If, at the expiration of such thirty (30)-day period, such Force Majeure shall still continue, Company may elect to terminate this Contract as a Voluntary Termination. 66 EXECUTION VERSION CONTRACT NUMBER 51008
Termination in Consequence of Force Majeure. If an event of Force Majeure continues for a period of forty-five (45) days in the aggregate that materially affects the ability of Developer to perform the Work, and as a result thereof there is a corresponding delay in the schedule for performance of the Work and the Guaranteed Substantial Completion Date of at least forty-five (45) days, then, notwithstanding that Developer may by reason thereof have been granted an extension of the schedule for performance of the Work and the Guaranteed Substantial Completion Date, by Change Order, PacifiCorp shall be entitled to terminate this Agreement upon thirty (30) days advance written notice to Developer. If at the expiration of such thirty (30)-day period such Force Majeure shall still continue, this Agreement shall automatically terminate without any further action on the part of either Party and the provisions of Section 30.3(a) shall apply.
Termination in Consequence of Force Majeure. If circumstances of Force Majeure have occurred and shall continue for a period of 180 days then, not withstanding that the Service Provider may by reason thereof have been granted an extension of Time for completion of the works, either party shall by entitled to serve upon the other 30 days notice to terminate the contract. If at the expiry of the period of 30 days Force Majeure shall still continue the contract shall terminate.

Related to Termination in Consequence of Force Majeure

  • Effect of Force Majeure If either Party is rendered wholly or partially unable to perform its obligations under this Agreement because of a Force Majeure Act, that Party shall be excused from whatever performance is affected by the Force Majeure Act to the extent so affected, provided that:

  • Termination for Force Majeure In the event of a force majeure that lasts longer than thirty (30) days from the date that a Party claiming relief due to the force majeure event gives notice to the other Party, the Party not claiming relief under the force majeure event may terminate this Agreement upon written notice to the other Party. For the avoidance of doubt, the COVID-19 pandemic does not constitute a force majeure event.

  • Termination by Either Party This Agreement may be terminated upon 60 days written notice without cause or penalty by either the Company (acting through the Conflicts Committee) or the Advisor. The provisions of Articles 1, 10, 12, 13, 15 and 16 shall survive termination of this Agreement.

  • Termination by Owner The Owner may terminate this Agreement in whole or in part, for the failure of the Consultant to: