Power Factor Design Criteria (Reactive Power A wind generating plant shall maintain a power factor within the range of 0.95 leading to 0.95 lagging, measured at the Point of Interconnection as defined in this LGIA, if the ISO’s System Reliability Impact Study shows that such a requirement is necessary to ensure safety or reliability. The power factor range standards can be met using, for example without limitation, power electronics designed to supply this level of reactive capability (taking into account any limitations due to voltage level, real power output, etc.) or fixed and switched capacitors if agreed to by the Connecting Transmission Owner for the Transmission District to which the wind generating plant will be interconnected, or a combination of the two. The Developer shall not disable power factor equipment while the wind plant is in operation. Wind plants shall also be able to provide sufficient dynamic voltage support in lieu of the power system stabilizer and automatic voltage regulation at the generator excitation system if the System Reliability Impact Study shows this to be required for system safety or reliability.
Real and Reactive Power Control 36 9.6 Outages and Interruptions. 37 9.7 Switching and Tagging Rules. 41 9.8 Use of Attachment Facilities by Third Parties. 41 9.9 Disturbance Analysis Data Exchange. 42 ARTICLE 10. MAINTENANCE 42 10.1 Connecting Transmission Owner Obligations. 42 10.2 Developer Obligations. 42 10.3 Coordination. 42 10.4 Secondary Systems. 42 10.5 Operating and Maintenance Expenses. 43 ARTICLE 11. PERFORMANCE OBLIGATION 43
Reactive Power 1.8.1 The Interconnection Customer shall design its Small Generating Facility to maintain a composite power delivery at continuous rated power output at the Point of Interconnection at a power factor within the range established by the Connecting Transmission Owner on a comparable basis, until NYISO has established different requirements that apply to all similarly situated generators in the New York Control Area on a comparable basis.
Reactive Power and Primary Frequency Response 9.6.1 Power Factor Design Criteria
GEOGRAPHIC AREA AND SECTOR SPECIFIC ALLOWANCES, CONDITIONS AND EXCEPTIONS The following allowances and conditions shall apply where relevant: Where the company does work which falls under the following headings, the company agrees to pay and observe the relevant respective conditions and/or exceptions set out below in each case.
Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.
STATEWIDE ACHIEVEMENT TESTING When CONTRACTOR is a NPS, per implementation of Senate Bill 484, CONTRACTOR shall administer all Statewide assessments within the California Assessment of Student Performance and Progress (“CAASPP”), Desired Results Developmental Profile (“DRDP”), California Alternative Assessment (“CAA”), achievement and abilities tests (using LEA-authorized assessment instruments), the Fitness Gram, , the English Language Proficiency Assessments for California (“ELPAC”), and as appropriate to the student, and mandated by LEA pursuant to LEA and state and federal guidelines. CONTRACTOR is subject to the alternative accountability system developed pursuant to Education Code section 52052, in the same manner as public schools. Each LEA student placed with CONTRACTOR by the LEA shall be tested by qualified staff of CONTRACTOR in accordance with that accountability program. XXX shall provide test administration training to CONTRACTOR’S qualified staff. CONTRACTOR shall attend LEA test training and comply with completion of all coding requirements as required by XXX.
Cloud Computing State Risk and Authorization Management Program In accordance with Senate Bill 475, Acts 2021, 87th Leg., R.S., pursuant to Texas Government Code, Section 2054.0593, Contractor acknowledges and agrees that, if providing cloud computing services for System Agency, Contractor must comply with the requirements of the state risk and authorization management program and that System Agency may not enter or renew a contract with Contractor to purchase cloud computing services for the agency that are subject to the state risk and authorization management program unless Contractor demonstrates compliance with program requirements. If providing cloud computing services for System Agency that are subject to the state risk and authorization management program, Contractor certifies it will maintain program compliance and certification throughout the term of the Contract.
Synchronisation Commissioning and Commercial Operation 8.1 The Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.