Common use of Weather Clause in Contracts

Weather. If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions at the Project Site were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.