Work to be done by the Completion Date Sample Clauses

Work to be done by the Completion Date. This is mandatory. Core clause 11.2(2) defines Completion as when the Contractor has done all the work which the Works Information states he is to do by the Completion Date. Rather than list all work to be done by the Completion Date, state that all work is to be done by the Completion Date except for [●]. For example: On or before the Completion Date the Contractor shall have done everything required to Provide the Works except for the work listed below which may be done after the Completion Date but in any case before the dates stated. The Project Manager cannot certify Completion until all the work except that listed below has been done and is also free of Defects which would have, in his opinion, prevented the Employer from using the works and Others from doing their work. Item of work To be completed by As built drawings of Within days after Completion Performance testing of the works in use as specified in paragraph of this Works Information. See performance testing requirements.
AutoNDA by SimpleDocs
Work to be done by the Completion Date. The whole of the Works as described by the Works Information of this contract shall be completed on or before the Completion Date. Completion includes the completion and submission of hand-over documentation, as-built drawings, and completed defect lists. The Contractor pays delay damages for late completion in terms of the Conditions of Contract. • Copies of the “Introduction Agreements” and “Indemnity Agreements” between Eskom, the Contractor and all the Landowners on the power line; • As Built Line Route Data (Gate Installation/Refurbishment; Xxxx Clearing; Herbicides Application and Access Road Data); • Structure and Structure Label Data; • Structure Foundation Type Data; • Structure Footing Resistance Data; • Insulators Assembly and Hardware Data; • Phase Conductor & Shield Wire Drum Data; • Sag & Tension Data; • Midspan Joint and Conductor Repair Data; • Crossing Clearances Data; • Jumper Clearances Data; • Stringing Equipment Calibration Certificates; • Compression Joint Test Certificates; • As Built drawings
Work to be done by the Completion Date. On or before the Completion Date the Contractor does everything required to Provide the Works. The Project Manager cannot certify Completion until all the work has been done and is also free of Defects which would have, in his opinion, prevented the Employer from using the works and Others from doing their work.
Work to be done by the Completion Date. The Project Manager cannot certify Completion until all the work except that is listed below has been done and is also free of Defects which would have, in his opinion, prevented the Employer from using the works and Others from doing their work. Item of work To be completed by 1 The works as a whole shall be completed within 9 Months from start date 2 Completion of stages Completion dates for each stage shall be agreed upon submission of the contractors program after site handover and prior to commencement of the first stage in line with the contract requirements and the program shall not exceed the planned 9 month construction period.

Related to Work to be done by the Completion Date

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.