Construction Baseline Schedule definition

Construction Baseline Schedule means the initial time schedule prepared by Construction Manager for Owner’s information and acceptance that conveys Construction Manager’s and Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by the Design Professional and Owner), durations, and sequence of work related to the entire Project, to the extent required by the Contract Documents. The Construction Baseline Schedule shall clearly demonstrate the Longest Path of activities, critical activities durations, and necessary predecessor conditions that drive the end date of the schedule. The accepted Construction Baseline Schedule shall not change.

Examples of Construction Baseline Schedule in a sentence

  • Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work.

  • Contractor shall submit for review and approval a Construction Baseline Schedule to Owner and Design Professional no later than twenty-one (21) days after the effective date of the Notice to Proceed with construction.

  • The Construction Baseline Schedule shall indicate the dates for starting and completing the various aspects required to complete the work and shall utilize the Longest Path Method with fully editable logic.

  • Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit baseline schedule, large enough to show entire schedule for entire construction period.

  • The Contracting Officer and Contractor shall participate in a preliminary meeting(s) to discuss the proposed schedule and requirements of this section prior to the Contractor preparing the Construction Baseline Schedule.

  • The population of this research were all manufacturing multinational companies listed on the Indonesia Stock Exchange between 2008-2018.

  • Develop the Construction Baseline Schedule, as design progresses, with detailed construction activities.

  • Within seven calendar days after the joint review between the Contractor and Contracting Officer or their representative, the Contractor shall revise and resubmit the Construction Baseline Schedule in accordance with agreements reached during the joint review.

  • Contractor shall prepare and submit to City a detailed Construction Baseline Schedule (showing all milestones with critical activities on the Baseline Schedule) for each street segment(s) and/or location(s) identified and requested for repairs and Work prior to commencing construction.

  • Longest Path (Critical) Activities must not make up more than [30 percent] [ ] of all activity within the Construction Baseline Schedule.

Related to Construction Baseline Schedule

  • Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;

  • The Project Plan means the document to be developed by the Supplier and approved by the Purchaser, pursuant to GCC Clause 19, based on the requirements of the Contract and the Preliminary Project Plan included in the Supplier’s bid. The “Agreed and Finalized Project Plan” is the version of the Project Plan approved by the Purchaser, in accordance with GCC Clause 19.2. Should the Project Plan conflict with the Contract in any way, the relevant provisions of the Contract, including any amendments, shall prevail.

  • Work Schedule means the approved order and timeline for how the requirements of this contract, including Work on individual Units or groups of Units, will be fulfilled by the Contractor.

  • Direct Construction Cost means the sum of the amounts that the Construction Manager actually and necessarily incurs for General Conditions Costs, Cost of the Work and Construction Manager’s Contingency during the Construction Phase as allowed by this Agreement. Direct Construction Cost does not include Pre-Construction Phase Fees or Construction Phase Fees.

  • Constructional Plant means all appliances or things whatever nature required in or about the execution, completion or maintenance of the works or temporary works (as hereinafter defined) but does not include materials or other things intended to form or forming part of the permanent work or temporary housing, hutting, office, stores, etc.,