Examples of Construction Baseline Schedule in a sentence
Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work.
Contractor shall submit for review and approval a Construction Baseline Schedule to Owner and Design Professional no later than twenty-one (21) days after the effective date of the Notice to Proceed with construction.
The Construction Baseline Schedule shall indicate the dates for starting and completing the various aspects required to complete the work and shall utilize the Longest Path Method with fully editable logic.
Construction Baseline Schedule: After contract award and before Pre-Construction conference, submit baseline schedule, large enough to show entire schedule for entire construction period.
The Contracting Officer and Contractor shall participate in a preliminary meeting(s) to discuss the proposed schedule and requirements of this section prior to the Contractor preparing the Construction Baseline Schedule.
The population of this research were all manufacturing multinational companies listed on the Indonesia Stock Exchange between 2008-2018.
Develop the Construction Baseline Schedule, as design progresses, with detailed construction activities.
Within seven calendar days after the joint review between the Contractor and Contracting Officer or their representative, the Contractor shall revise and resubmit the Construction Baseline Schedule in accordance with agreements reached during the joint review.
Contractor shall prepare and submit to City a detailed Construction Baseline Schedule (showing all milestones with critical activities on the Baseline Schedule) for each street segment(s) and/or location(s) identified and requested for repairs and Work prior to commencing construction.
Longest Path (Critical) Activities must not make up more than [30 percent] [ ] of all activity within the Construction Baseline Schedule.