Construction Period means the period commencing from the Appointed Date and ending on the date of the Completion Certificate;
Construction Completion Date means the date by which the overall development of the Project is completed in accordance with the provisions of this Agreement and when the Construction Completion Certificate is issued by the Independent Engineer as per Article 14.1.
Project Completion Date means the date on which the Completion Certificate is issued;
Construction Budget means the fully-budgeted costs for the acquisition and construction of a given parcel of real property (including, without limitation, the cost of acquiring such parcel of real property, reserves for construction interest and operating deficits, tenant improvements, leasing commissions, and infrastructure costs) as reasonably determined by the Parent in good faith.
Construction Plans means plans, drawings, specifications and related documents, and construction schedules for the construction of the Project, together with all supplements, amendments or corrections, submitted by the Developer and approved by the City in accordance with this Agreement.
Construction Work means any work in connection with⎯
Construction Commencement Date means the date set out in the Addendum, if applicable, by which you must commence construction of the Hotel. For the Hotel to be considered under construction, youmust have begun to pour concrete foundations for the Hotel or otherwise satisfied any site-specific criteria for “under construction” set out in the Addendum.
Construction Activities means the disturbance of soils associated with clearing, grading, excavation activities or other construction-related activities.
Construction Completion means physical construction of a cleanup action component is complete.
Construction activity means any clearing, grading or excavation associated with large construction activity or associated with small construction activity.
Construction Phase means that Phase of the Project which shall commence after the Authority provides the Trade Contractor with written Notice to Proceed with the Construction Phase.
Project Completion means completion of the Redevelopment in accordance with this Agreement to the state where the whole of the Morley Shopping Centre, as so redeveloped, is capable of occupation for its intended purpose;
Target Completion Date has the meaning given such term in Section 3.3(b).
The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.
Construction Plant means appliances, machinery with necessary supply to up keep and maintenance of the works or temporary works but dose not include materials or other things intended to form part of the permanent work.
Scheduled Completion Date shall be the date set forth in Clause 10.3;
construction site means a workplace where construction work is being performed;
Project Year means the 12 month period beginning from the Effective Date and ending 12 months thereafter and each successive 12 month period following thereafter;
Substantial Completion Date means the required date for Substantial Completion of the Project. The Substantial Completion Date can be adjusted only by written Change Order.
Final Completion Date means the date on which Final Completion occurs.