Examples of Third Notification in a sentence
All work done to comply with the warranty shall itself be warranted for one year beginning on the date of the City's Third Notification of the corrections, repairs, replacements or changes.
The Contractor shall provide reasonable protection of the Work from vandalism until Third Notification.
All work done to comply with the warranty shall itself be warranted for one year beginning on the date of the City’s Third Notification of the corrections, repairs, replacements or changes.
The warranty period will begin on the date the Engineer issues Third Notification unless otherwise specified in the Contract.
Beginning 30 Calendar Days after the date of Third Notification, interest will begin to accrue at the rate established by ORS 279C.570 on any money due and payable to the Contractor as final payment, determined as described above.
The Second Notification will list: The date the time charges stopped;Final trimming and cleanup tasks (see 00140.90);Equipment to be removed from the Project Site;Minor corrective work not involving additional payment to be completed; andSubmittals, including, without limitation, all required certifications, bills, forms, warranties, certificate of insurance coverage (00170.70(b)), and other documents, required to be provided to the Engineer before Third Notification will issue.
The Contractor shall warrant all Work and workmanship, including Changed Work, Additional Work, Incidental Work, On-Site Work, and Extra Work, and Materials and Equipment incorporated in the Work, for 1 year from the date of Third Notification, except that warranties according to 00170.85(b)(1) and manufacturers' warranties and extended warranties according to 00170.85(c) shall not be abridged.
The Second Notification will list: • The date the time charges stopped;• Final trimming and cleanup tasks (see 00140.90);• Equipment to be removed from the Project Site;• Minor corrective work not involving additional payment to be completed; and• Submittals, including without limitation all required certifications, bills, forms, warranties, certificate of insurance coverage (00170.70(b)), and other documents, required to be provided to the Engineer before Third Notification will issue.
Plant Establishment and Maintenance 01040.70 General - The Contractor is responsible for the survival of all plant material until the Third Notification is issued or the end of a plant Establishment Period of 1 calendar year.
Interim approvals issued by the Engineer, including but not limited to Third Notification, will not discharge the Contractor from responsibility for errors in prosecution of the Work, for improper fabrication, for failure to comply with Contract requirements, or for other deficiencies, the nature of which are within the Contractor's control.