Access Following Substantial Completion Sample Clauses

Access Following Substantial Completion. After Owner takes possession and control of the Facility upon Substantial Completion, Owner shall provide Contractor with reasonable access to the Facility in order to complete the Work, including the Punch List Items and, if applicable, to attempt to achieve the Performance Guarantees pursuant to Section 15.5; provided, however, following Substantial Completion, Owner shall not be obligated hereunder to take an outage and/or de-rate, or otherwise interfere with its operation of the Facility as a direct or indirect result of allowing Contractor access pursuant to this Section 16.4(c). Any such access by Contractor shall be subject to Owner’s processes and requirements relating to Site access, including safety, lock and tag out and confined space. Contractor shall complete the Work and shall perform its obligations using its reasonable efforts to minimize interference to the operations of the Facility and only as scheduled by mutual agreement of the Parties. Contractor shall, except to the extent otherwise agreed by the Parties, use all reasonable efforts to promptly complete all Punch List Items after the Substantial Completion Date. The Parties expect that Contractor will accomplish any necessary modifications, repairs and Punch List Items with minimal interference with the commercial operation of the Facility. Notwithstanding the provisions of Article 29, Contractor shall reimburse Owner for all costs, expenses or damages, including lost revenues incurred by or on behalf of Owner or any other Persons which result from Contractor’s performance under Section 16.4(b) or Section 16.4(c).
AutoNDA by SimpleDocs
Access Following Substantial Completion. After Owner takes possession and control of the Facility pursuant to Section 15.3 hereof, Owner shall provide Contractor with reasonable access to the Facility in order to complete the Work, including the Punchlist Items and, if applicable, to attempt to achieve one hundred percent (100%) of the Performance Guarantees pursuant to Section 14.5; provided, however, following Substantial Completion, Owner shall not be obligated hereunder to take an outage and/or de-rate, or otherwise interfere with its operation of the Project as a direct or indirect result of allowing Contractor access pursuant to this Section 15.5. Contractor shall complete the Work and shall perform its obligations using its reasonable efforts to minimize interference to the operations of the Facility and only as scheduled by mutual agreement of the Parties. Contractor shall, except to the extent otherwise agreed by the Parties, use all reasonable efforts to promptly complete all Punchlist Items after the Substantial Completion Date. The Parties expect that Contractor will accomplish any necessary modifications, repairs and Punchlist Items with minimal interference with the commercial operation of the Facility.

Related to Access Following Substantial Completion

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • At Substantial Completion and Final Completion the Contractor shall provide a certification letter certifying that the Work does not contain asbestos as required by the UTUGCs.

  • After Substantial Completion § 12.2.2.1 In addition to the Contractor’s obligations under Section 3.5, if, within one year after the date of Substantial Completion of the Work or designated portion thereof or after the date for commencement of warranties established under Section 9.9.1, or by terms of any applicable special warranty required by the Contract Documents, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct it promptly after receipt of notice from the Owner to do so, unless the Owner has previously given the Contractor a written acceptance of such condition. The Owner shall give such notice promptly after discovery of the condition. During the one-year period for correction of Work, if the Owner fails to notify the Contractor and give the Contractor an opportunity to make the correction, the Owner waives the rights to require correction by the Contractor and to make a claim for breach of warranty. If the Contractor fails to correct nonconforming Work within a reasonable time during that period after receipt of notice from the Owner or Architect, the Owner may correct it in accordance with Section 2.5.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.

  • TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION (i) The work under this Contract shall commence within seven (7) calendar days of receipt of Notice to Proceed and will be substantially complete within thirty (80) calendar days after the date when the Contract Time commences to run as provided in paragraph 2.03 of the General Conditions and completed and ready for final payment within ninety (90) calendar days after the date when the Contract Time commences to run.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: (Check one of the following boxes.) [ « » ] The date of this Agreement. [ « » ] A date set forth in a notice to proceed issued by the Owner. [ « » ] Established as follows: (Insert a date or a means to determine the date of commencement of the Work.) « » If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement.

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by September 30, 2022.