Available Relief & Termination Due to Force Majeure Event Sample Clauses

Available Relief & Termination Due to Force Majeure Event a) If, prior to the completion of the 180 (one hundred and eighty) Day period (or any extended period) for a Force Majeure Event commencing from the date of issuance of the Force Majeure Notice, the Parties are of the reasonable view that a Force Majeure Event is likely to continue beyond such 180 (one hundred and eighty) Day period or any extended period agreed in pursuance of Article
AutoNDA by SimpleDocs
Available Relief & Termination Due to Force Majeure Event a) If, prior to the completion of the 180 (one hundred and eighty) Day period (or any extended period) for a Force Majeure Event commencing from the date of issuance of the Force Majeure Notice, the Parties are of the reasonable view that a Force Majeure Event is likely to continue beyond such 180 (one hundred and eighty) Day period or any extended period agreed in pursuance of Article 11.5 (Performance Excused); or that it is uneconomic or impractical to restore the affected Unit, then the Parties may mutually decide to terminate the BESPA, and the termination shall take effect from the date on which such decision is taken. b) In case of occurrence of an event which is not a Force Majeure as per provision of this Agreement, but causes some hardship in development of the Project, which may or may not be recognized by the Government of India and for which the Government of India has or hasn’t granted any extension of time or any other relief; such event, even if sustained beyond 180 days shall not be considered as a reason for termination of BESPA under this Article. c) Without prejudice to the provisions of Article 11.10.(a) above, the Affected Party shall, after the expiry of the period of 180 (one hundred and eighty) Days or any other mutually extended period, be entitled to forthwith terminate the BESPA in its sole discretion by issuing a notice to that effect. d) On termination of the BESPA pursuant to Article 11.10.(b): i. In case of termination on account of event listed as Force Majeure as under Article 11.2 (a), (b), (c) and (d), no Termination Compensation shall be payable to the BESSD. ii. In case of termination at the instance of the BESSD, on account of an event listed as Force Majeure as per Article 11.2 (e) and (f) above, the Procurer will have the option to (but will not be obliged to) take- over the Project Assets by paying Debt Due. In case the Procurer chooses not to exercise the aforementioned option, and the same is not agreed to by the BESSD, it will result in a dispute as per the BESPA and will be resolved as per the Dispute Resolution mechanism under the BESPA. iii. the BESSD shall be eligible for undisputed payments under outstanding Monthly Bill(s), before the occurrence of Force Majeure Event.
Available Relief & Termination Due to Force Majeure Event. (a) If, prior to the completion of the 180 (one hundred and eighty) Day period (or any extended period) for a Force Majeure Event commencing from the date of issuance of the Force Majeure Notice, the Parties are of the reasonable view that a Force Majeure Event is likely to continue beyond such 180 (one hundred and eighty) Day period or any extended period agreed in pursuance of Article 11.5 (Performance Excused); or that it is uneconomic or impractical to restore the affected Unit, then the Parties may mutually decide to terminate the PPA, and the termination shall take effect from the date on which such decision is taken. (b) Without prejudice to the provisions of Article 11.10.(a) above, the Affected Party shall, after the expiry of the period of 180 (one hundred and eighty) Days or any other mutually extended period, be entitled to forthwith terminate the PPA in its sole discretion by issuing a notice to that effect. (c) On termination of the PPA pursuant to Article 11.10.(b): i. No Termination Compensation shall be payable to the SPD. ii. the SPD shall be eligible for undisputed payments under outstanding Monthly Bill(s), before the occurrence of Force Majeure Event

Related to Available Relief & Termination Due to Force Majeure Event

  • Termination Due to Force Majeure Event If the period of Force Majeure continues or is in the reasonable judgment of the Parties likely to continue beyond a period of 120 (one hundred and twenty) Days, the Parties may mutually decide to terminate this Agreement or continue this Agreement on mutually agreed revised terms. If the Parties are unable to reach an agreement in this regard, the Affected Party shall after the expiry of the said period of 120 (one hundred and twenty ) Days be entitled to terminate the Agreement in which event, the provisions of Articles 16 and 17 shall, to the extent expressly made applicable, apply.

  • Termination due to Force Majeure 13.5.1 If the Force Majeure Event or its effects continue to be present beyond the period as specified in Article 4.5.3, either Party shall have the right to cause termination of the Agreement. In such an event, this Agreement shall terminate on the date of such Termination Notice.

  • Available Relief for a Force Majeure Event 11.7.1 Subject to this Article 11: (a) no Party shall be in breach of its obligations pursuant to this Agreement except to the extent that the performance of its obligations was prevented, hindered or delayed due to a Force Majeure Event; (b) every Party shall be entitled to claim relief in relation to a Force Majeure Event in regard to its obligations, including but not limited to those specified under Article 4.5; (c) For avoidance of doubt, neither Party’s obligation to make payments of money due and payable prior to occurrence of Force Majeure events under this Agreement shall be suspended or excused due to the occurrence of a Force Majeure Event in respect of such Party. (d) Provided that no payments shall be made by either Party affected by a Force Majeure Event for the period of such event on account of its inability to perform its obligations due to such Force Majeure Event.

  • Termination Notice for Force Majeure Event If a Force Majeure Event subsists for a period of 180 (one hundred and eighty) days or more within a continuous period of 365 (three hundred and sixty five) days, either Party may in its discretion terminate this Agreement by issuing a Termination Notice to the other Party without being liable in any manner whatsoever, save as provided in this Article 34, and upon issue of such Termination Notice, this Agreement shall, notwithstanding anything to the contrary contained herein, stand terminated forthwith; provided that before issuing such Termination Notice, the Party intending to issue the Termination Notice shall inform the other Party of such intention and grant 15 (fifteen) days time to make a representation, and may after the expiry of such 15 (fifteen) days period, whether or not it is in receipt of such representation, in its sole discretion issue the Termination Notice.

  • Termination for Force Majeure 15.5.1. The License Agreement may be terminated for Force Majeure Reasons as specified in Article -14.

  • Termination Payment for Force Majeure Event 30.9.1 If Termination is on account of a Non-Political Event, the Authority shall make a Termination Payment to the Concessionaire in an amount equal to 55% (fifty five per cent) of the Debt Due less Insurance Cover. 30.9.2 If Termination is on account of an Indirect Political Event, the Authority shall make a Termination Payment to the Concessionaire in an amount equal to: (a) 55% of the Debt Due less Insurance Cover; provided that if any insurance claims forming part of the Insurance Cover are not admitted and paid, then 80% (eighty per cent) of such unpaid claims shall be included in the computation of Debt Due; (b) 60.5% (sixty point five per cent) of the Adjusted Equity; and 30.9.3 If Termination is on account of a Political Event, the Authority shall make a Termination Payment to the Concessionaire in an amount that would be payable under Clause 33.3.2 as if it were Authority’s Default.

  • Termination for continuing Force Majeure Event Either Party may, by written notice to the other, terminate this Framework Agreement if a Force Majeure Event endures for a continuous period of more than one hundred and twenty (120) Working Days.

  • SUSPENSION & TERMINATION FOR DEFAULT Enterprise Services may suspend Contractor’s operations under this Master Contract immediately by written cure notice of any default. Suspension shall continue until the default is remedied to Enterprise Services’ reasonable satisfaction; Provided, however, that, if after thirty (30) days from such a suspension notice, Contractor remains in default, Enterprise Services may terminate Contractor’s rights under this Master Contract. All of Contractor’s obligations to Enterprise Services and Purchasers survive termination of Contractor’s rights under this Master Contract, until such obligations have been fulfilled.

  • Force Majeure Event After giving effect to any applicable provision, disruption fallback or remedy specified in, or pursuant to, the relevant Confirmation or elsewhere in this Agreement, by reason of force majeure or act of state occurring after a Transaction is entered into, on any day:— (1) the Office through which such party (which will be the Affected Party) makes and receives payments or deliveries with respect to such Transaction is prevented from performing any absolute or contingent obligation to make a payment or delivery in respect of such Transaction, from receiving a payment or delivery in respect of such Transaction or from complying with any other material provision of this Agreement relating to such Transaction (or would be so prevented if such payment, delivery or compliance were required on that day), or it becomes impossible or impracticable for such Office so to perform, receive or comply (or it would be impossible or impracticable for such Office so to perform, receive or comply if such payment, delivery or compliance were required on that day); or (2) such party or any Credit Support Provider of such party (which will be the Affected Party) is prevented from performing any absolute or contingent obligation to make a payment or delivery which such party or Credit Support Provider has under any Credit Support Document relating to such Transaction, from receiving a payment or delivery under such Credit Support Document or from complying with any other material provision of such Credit Support Document (or would be so prevented if such payment, delivery or compliance were required on that day), or it becomes impossible or impracticable for such party or Credit Support Provider so to perform, receive or comply (or it would be impossible or impracticable for such party or Credit Support Provider so to perform, receive or comply if such payment, delivery or compliance were required on that day), so long as the force majeure or act of state is beyond the control of such Office, such party or such Credit Support Provider, as appropriate, and such Office, party or Credit Support Provider could not, after using all reasonable efforts (which will not require such party or Credit Support Provider to incur a loss, other than immaterial, incidental expenses), overcome such prevention, impossibility or impracticability;

  • Notification of Force Majeure Event 11.5.1 The Affected Party shall give notice to the other Party of any event of Force Majeure as soon as reasonably practicable, but not later than seven (7) days after the date on which such Party knew or should reasonably have known of the commencement of the event of Force Majeure. If an event of Force Majeure results in a breakdown of communications rendering it unreasonable to give notice within the applicable time limit specified herein, then the Party claiming Force Majeure shall give such notice as soon as reasonably practicable after reinstatement of communications, but not later than one (1) day after such reinstatement. Provided that, such notice shall be a pre-condition to the Affected Party’s entitlement to claim relief under this Agreement. Such notice shall include full particulars of the event of Force Majeure, its effects on the Party claiming relief and the remedial measures proposed. The Affected Party shall give the other Party regular reports on the progress of those remedial measures and such other information as the other Party may reasonably request about the Force Majeure. 11.5.2 The Affected Party shall give notice to the other Party of (i) the cessation of the relevant event of Force Majeure; and (ii) the cessation of the effects of such event of Force Majeure on the performance of its rights or obligations/ roles under this Agreement, as soon as practicable after becoming aware of each of these cessations.