Occurrence of Force Majeure Event. If a Force Majeure Event affecting a Party precludes that Party (Precluded Party) partially or wholly from complying with its obligations (except its Security and payment obligations) under this Agreement then:
AutoNDA by SimpleDocs
Occurrence of Force Majeure Event. A Party (Affected Party) is excused from performing its obligations under this Agreement to the extent it is prevented by circumstances which:
Occurrence of Force Majeure Event. A Party (Affected Party) is excused from performing its obligations under this Agreement to the extent it is prevented by circumstances which: are beyond its reasonable control (other than, in respect of the Recipient only, lack of funds for any reason or any strike, lockout or labour dispute) including, natural disasters, acts of war, act of terrorism, riots and strikes outside the Affected Party's organisation; and could not have been prevented or overcome by the Affected Party (or, where the Affected Party is the Recipient) exercising a standard of care and diligence consistent with that of a prudent and competent person operating within the relevant industry (a ‘Force Majeure Event’).
Occurrence of Force Majeure Event. The Funding Recipient is excused from performing its obligations under this Agreement to the extent it is prevented by circumstances beyond its reasonable control (other than a lack of Cash Contributions for any reason or any strike, lockout or labour disputes that only applies to the Funding Recipient), including but not limited to acts of God, natural disasters, acts of war, epidemic, riots and strikes outside that party's organisation.
Occurrence of Force Majeure Event. If any Force Majeure Event occurs in relation to either Party which affects or may affect the performance of any of its material obligations (other than the payment of money) under this Agreement, it shall use all Commercially Reasonable Efforts to mitigate the effects of such delay or prevention upon the performance of its obligations under this Agreement, promptly notify the other Party as to the nature and extent of such Force Majeure Event, and resume performance of its obligations as soon as reasonably possible after the removal of the cause of the delay or prevention. Neither Party shall be deemed to be in breach of this Agreement, or shall be otherwise liable to the other Party, by reason only of any delay in performance, or the non-performance of any of its obligations hereunder, to the extent that the delay or non-performance is due to any Force Majeure Event of which it has duly notified the other Party, and the time for performance of that obligation shall be extended accordingly. Without limiting Client’s right to terminate this Agreement pursuant to Section 19.3, if the performance by either Party of any of its obligations under this Agreement is prevented or delayed by a Force Majeure Event for a continuous period in excess of [***], the Parties shall enter into bona fide discussions with a view to alleviating its effects, or to agreeing upon such alternative arrangements as may be fair and reasonable in the circumstances.
Occurrence of Force Majeure Event. If a Party is prevented from performing its obligations, partly or wholly, by a Force Majeure Event:
Occurrence of Force Majeure Event. If a Force Majeure Event occurs (or in our opinion, acting in good faith, is likely to occur) and results (or is likely to result) in the Event being unable to take place as contemplated by these T&C, we may, in our sole discretion:
AutoNDA by SimpleDocs
Occurrence of Force Majeure Event. The Affected Party shall (a) provide prompt notice to the other Party of the Force Majeure Event, giving an estimate of its expected duration and the probable impact on the performance by the Affected Party of its obligations hereunder; (b) exercise all reasonable efforts to continue to perform its obligations hereunder; (c) expeditiously act to correct or cure the Force Majeure Event to the extent such action is within the power of the Affected Party; (d) exercise all reasonable efforts to mitigate or limit Damages to the other Party to the extent such action will not adversely affect its own interests; and (e) provide prompt notice to the other Party of the cessation of the Force Majeure Event. Notices and Other Communications Requirements for Notices and Other Communications Each notice, request, demand, statement or routine communication required or permitted under this Agreement, or any notice or communication that either Party may desire to deliver to the other, shall be in writing and shall be considered delivered effective: (a) if sent by personal courier, overnight courier, or mail, two (2) Business Days after it was sent or such earlier time as is confirmed by the receiving Party; or (b) if sent be facsimile or email, when verified by automated receipt or electronic logs if sent by facsimile or email. Each such notice must be addressed to the other Party at its address indicated below or at such other address and by means as either Party may designate for itself in a written notice to the other Party in accordance with this Section 15.1. DRAFT – October 22, 2003 -- #1 Joint Ownership Agreement If to PSE: Puget Sound Energy, Inc. 00000 XX 0xx Xxxxxx Xxxxxxxx, XX 00000-0000 Attn: Xxxxx X. Xxxxxxx Email: xxxxx.xxxxxxx@xxx.xxx Telephone: 000-000-0000 If to Puget LNG: Puget LNG, LLC 00000 XX 0xx Xxxxxx Xxxxxxxx, XX 00000-0000 Attn: Xxxxx Xxxxxxx Email: xxxxx.xxxxxxx@xxx.xxx Telephone: 000-000-0000 General Exercise of Rights Subject to the express provisions of this Agreement, a Party may exercise a right or remedy at its discretion, and separately or concurrently with any other right or remedy. A single or partial exercise of a right or remedy by a Party does not prevent a further exercise of that or of any other right or remedy. No Waiver No delay or forbearance by a Party in exercising any right or remedy accruing to such Party upon the occurrence of any breach or default (including an Event of Default) by the other Party under this Agreement shall ...

Related to Occurrence of Force Majeure Event

  • Event of Force Majeure 15.1 Neither Party shall be in breach of the Agreement nor liable for any delay in performing, or failure to perform, any of its obligations under the Agreement if such delay or failure results from an Event of Force Majeure. In such circumstances the affected Party shall be entitled to a reasonable extension of the time for performing such obligations. If the period of delay or non-performance continues for three consecutive months, the Party not affected may terminate the Agreement immediately by giving written notice to the affected Party.

  • Force Majeure Event 16.1 If a Force Majeure Event gives rise to a failure or delay in either party performing any obligation under this Agreement (other than any obligation to make a payment), that obligation will be suspended for the duration of the Force Majeure Event.

  • Events of Force Majeure Neither Party shall be held liable or responsible to the other Party nor be deemed to be in default under, or in breach of any provision of, this Agreement for failure or delay in fulfilling or performing any obligation of this Agreement when such failure or delay is due to force majeure, and without the fault or negligence of the Party so failing or delaying. For purposes of this Agreement, force majeure is defined as causes beyond the control of the Party, including, without limitation, acts of God; acts, regulations, or laws of any government; war; civil commotion; destruction of production facilities or materials by fire, flood, earthquake, explosion or storm; labor disturbances; epidemic; and failure of public utilities or common carriers. In such event Medistem or Licensee, as the case may be, shall immediately notify the other Party of such inability and of the period for which such inability is expected to continue. The Party giving such notice shall thereupon be excused from such of its obligations under this Agreement as it is thereby disabled from performing for so long as it is so disabled and the 30 days thereafter. To the extent possible, each Party shall use reasonable efforts to minimize the duration of any force majeure.

  • Force Majeure Events a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following:

  • Force Majeure If by reason of Force Majeure, either party hereto shall be rendered unable wholly or in part to carry out its obligations under this Agreement then such party shall give notice and full particulars of Force Majeure in writing to the other party within a reasonable time after occurrence of the event or cause relied upon, and the obligation of the party giving such notice, so far as it is affected by such Force Majeure, shall be suspended during the continuance of the inability then claimed, except as hereinafter provided, but for no longer period, and such party shall endeavor to remove or overcome such inability with all reasonable dispatch. Choice of Law The Agreement between the Vendor and TIPS/ESC Region 8 and any addenda or other additions resulting from this procurement process, however described, shall be governed by, construed and enforced in accordance with the laws of the State of Texas, regardless of any conflict of laws principles. Venue, Jurisdiction and Service of Process Any Proceeding arising out of or relating to this procurement process or any contract issued by TIPS resulting from or any contemplated transaction shall be brought in a court of competent jurisdiction in Camp County, Texas and each of the parties irrevocably submits to the exclusive jurisdiction of said court in any such proceeding, waives any objection it may now or hereafter have to venue or to convenience of forum, agrees that all claims in respect of the Proceeding shall be heard and determined only in any such court, and agrees not to bring any proceeding arising out of or relating to this procurement process or any contract resulting from or any contemplated transaction in any other court. The parties agree that either or both of them may file a copy of this paragraph with any court as written evidence of the knowing, voluntary and freely bargained for agreement between the parties irrevocably to waive any objections to venue or to convenience of forum. Process in any Proceeding referred to in the first sentence of this Section may be served on any party anywhere in the world. Venue for any dispute resolution process, other than litigation, between TIPS and the Vendor shall be located in Camp or Xxxxx County, Texas.

  • Notice of Force Majeure If performance is delayed as a result of Force Majeure, the affected party shall provide prompt Notice to the other party and shall be excused from default or delay in performance while such circumstances prevail so long as such party continues to use commercially reasonable efforts to recommence performance as soon as possible.

  • Effect of Force Majeure If either Party is rendered wholly or partially unable to perform its obligations under this Agreement because of a Force Majeure Act, that Party shall be excused from whatever performance is affected by the Force Majeure Act to the extent so affected, provided that:

  • Definition of Force Majeure For the purposes of this section, an event of force majeure shall mean any cause beyond the control of the affected Interconnection Party or Construction Party, including but not restricted to, acts of God, flood, drought, earthquake, storm, fire, lightning, epidemic, war, riot, civil disturbance or disobedience, labor dispute, labor or material shortage, sabotage, acts of public enemy, explosions, orders, regulations or restrictions imposed by governmental, military, or lawfully established civilian authorities, which, in any of the foregoing cases, by exercise of due diligence such party could not reasonably have been expected to avoid, and which, by the exercise of due diligence, it has been unable to overcome. Force majeure does not include (i) a failure of performance that is due to an affected party’s own negligence or intentional wrongdoing; (ii) any removable or remediable causes (other than settlement of a strike or labor dispute) which an affected party fails to remove or remedy within a reasonable time; or (iii) economic hardship of an affected party.

  • MAJEURE 24.1 Neither Partner shall be entitled to bring a claim for a breach of obligations under this Agreement by the other Partner or incur any liability to the other Partner for any losses or damages incurred by that Partner to the extent that a Force Majeure Event occurs and it is prevented from carrying out its obligations by that Force Majeure Event.