Certification for Payment. The contractor or vendor seeking payment from funds issued under this Agreement must declare with each pay request:
AutoNDA by SimpleDocs
Certification for Payment. The contractor or vendor representative seeking payment from funds issued under this agreement must declare with each pay request: I certify to the best of my knowledge and belief that the request is true, complete, and accurate, and the expenditures, disbursements and cash receipts are for the purposes and objectives set forth in the terms and conditions of the Federal award. I am aware that any false, fictitious, or fraudulent information, or the omission of any material fact, may subject me to criminal, civil or administrative penalties for fraud, false statements, false claims or otherwise. (U.S. Code Title 18, Section 1001 and Title 31, Sections 3729-3730 and 3801-3812).
Certification for Payment. CONSULTANT certification for payment shall constitute a representation to the CITY, based on CONSULTANT’s evaluation of the work and on the data comprising the Contractor’s Application for Payment, that, to the best of CONSULTANT’s knowledge, information and belief, the work has progressed to the point indicated and that the quality of the work is in accordance with the construction contract documents. The foregoing representations are subject (1) to an evaluation of the work for conformance with the construction contract documents upon substantial completion, (2) to results of subsequent tests and inspections, (3) to correction of minor deviations from the construction contract documents prior to completion, and (4) to specific qualifications expressed by CONSULTANT. Site visits will not be used to determine the progression of the work, but instead CONSULTANT will discuss, via phone, progress with the CITY Inspectors on the project. • Contract Clarifications: CONSULTANT shall respond to CITY’s questions in writing via email when such questions are necessary to provide clarification to the plans and specifications. Level of effort is limited to two (2) contract clarifications. • Engineering Supplemental Instruction (ESI): CONSULTANT shall generate supplemental drawings and clarifications, as necessary, or as may be requested by the construction contractor or the CITY to clarify the design intent.
Certification for Payment. If required by the Lender after Loan Advances in an aggregate amount of Two Million Dollars ($2,000,000) have been disbursed, the Borrower shall have caused the Contractor to execute and deliver to the Lender an Application and Certification for payment, AIA Document G702 and AIA Document G703 (or suitable substitute), with respect to the work for which a Loan Advance is being requested.

Related to Certification for Payment

  • Application for Payment The form acceptable to Owner that is to be used by the Contractor during the course of the Work in requesting payment from the Owner and that is to be accompanied by such supporting documentation as is required by the Contract Documents.

  • Request for Payment Payment to the Grantee shall be due 30 calendar days following receipt by the City of the Grantee’s fully and accurately completed payment request, using the City’s contract management system. The payment request must be submitted to the City no later than 11:59 p.m. Central Standard Time 25 calendar days following the end of the month covered by the payment request. If the 25th calendar day falls on a weekend or holiday, as outlined in Section 8.24, the deadline to submit the payment request is extended to no later than 11:59 p.m. Central Standard Time of the 1st weekday immediately following the weekend or holiday.

  • Due date for payment The settlement date for each Tax Invoice issued by the Distributor must be the 20th day of the month in which the Tax Invoice is received, or if the 20th day of the month is not a Working Day, the first Working Day after the 20th day. However, if the Distributor fails to send a Tax Invoice to the Trader within 10 Working Days after the last day of the month to which the Tax Invoice relates, the due date for payment is extended by 1 Working Day for each Working Day that the Tax Invoice is late.

  • Release for Payment Upon receipt by the Collateral Custodian of the Servicer’s request for release of documents and receipt in the form annexed hereto as Exhibit M (which certification shall include a statement to the effect that all amounts received in connection with such payment or repurchase have been credited to the Collection Account as provided in this Agreement), the Collateral Custodian shall promptly release the related Required Loan Documents to the Servicer.

  • Class Certification Solely for the purposes of this Settlement, the Parties stipulate and agree to certification of the claims asserted on behalf of Class Members. As such, the Parties stipulate and agree that in order for this Settlement to occur, the Court must certify the Class as defined in this Agreement.

  • Time for Payment Interconnection Customer must provide the additional Security, in a form and with terms as required by Section 212.4, within 15 days after its receipt of Transmission Provider’s notice under this section. The requirement for additional Security under this section shall be treated as a milestone included in the Interconnection Service Agreement pursuant to Section 212.5.

  • Basis for Payment DFPS is not obligated to pay unauthorized costs or to pay more than Grantee’s allowable and incurred costs consistent with 45 CFR 75, Subpart E. Grantee is responsible for submitting invoices in an accurate and timely manner for each service period and for notifying DFPS of a need to expedite payment. DFPS will make reasonable efforts to process all bills received in an accurate and timely manner but does not warrant immediate payment.

  • Applications for Payment 9.3.1 At least ten days before the date for each progress payment established in the State- Contractor Agreement, the Contractor shall submit to the Architect an itemized Application for Payment, notarized if required, supported by such data substantiating the Contractor's right to payment as the State or the Architect may require. The application for payment must, at a minimum, reflect retainage and the required waivers of lien and any other support documentation enumerated elsewhere in the Contract Documents. 9.3.2 Unless otherwise provided in the Contract Documents, payments will be made on account of materials or equipment not incorporated in the Work but delivered and suitably stored at the site and, if approved in advance by the State, payments may similarly be made for materials or equipment suitably stored at some other location agreed upon in writing. Payments for materials or equipment stored on or off the site shall be conditioned upon submission by the Contractor of bills of sale or such other procedures satisfactory to the State to establish the State's title to such materials or equipment or otherwise protect the State's interest, including applicable insurance and transportation to the site for those materials and equipment stored off the site. 9.3.3 The Contractor warrants that title to all Work, materials and equipment covered by an Application for Payment will pass to the State either by incorporation in the construction or upon the receipt of payment by the Contractor, whichever occurs first, free and clear of all liens, claims, security interests or encumbrances, hereinafter referred to in this Article 9 as "liens"; and that no Work, materials or equipment covered by an Application for Payment will have been acquired by the Contractor, or by any other person performing Work at the site or furnishing materials and equipment for the Project, subject to an agreement under which an interest therein or an encumbrance thereon is retained by the seller or otherwise imposed by the Contractor or such other person.

  • CERTIFICATES FOR PAYMENT 9.4.1 The Architect will, within seven days after the receipt of the Contractor's completed Application for Payment, either issue a Certificate for Payment to the State, with a copy to the Contractor, for such amount as the Architect determines is properly due, or notify the Contractor in writing his or her reasons for withholding a Certificate as provided in Subparagraph 9.6.1

  • E-VERIFY CERTIFICATION Pursuant to Executive Order RP-80, Engineer certifies and ensures that for all contracts for services, Engineer shall, to the extent permitted by law, utilize the United States Department of Homeland Security’s E-Verify system during the term of this agreement to determine the eligibility of: 1. All persons employed by Engineer during the term of this agreement to perform duties within the State of Texas; and 2. All persons, including subcontractors, assigned by Engineer to perform work pursuant to this agreement. Violation of this provision constitutes a material breach of this agreement.