Completion, Commissioning and Commercial Operation Sample Clauses

Completion, Commissioning and Commercial Operation. 5.2.1 When the Power Producer fulfils his obligation under the PPA, it shall obtain completion certificate from Nodal Agency. Nodal Agency shall issue separate Completion Certificate for the capacity of Project under Category I and III
AutoNDA by SimpleDocs
Completion, Commissioning and Commercial Operation. 5.2.1 When the Power Producer fulfils his obligation under the PPA, it shall obtain completion certificate from APDCL.

Related to Completion, Commissioning and Commercial Operation

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least thirty (30) days written notice to the SLDC and GUVNL, of the date on which it intends to synchronize the Power Project to the Grid System.

  • Synchronisation Commissioning and Commercial Operation 8.1 The Developer shall provide at least forty (40) days advanced preliminary written notice and at least twenty (20) days advanced final written notice to ESCOM of the date on which it intends to synchronize the Power Project to the Grid System.

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Building Commissioning Services The Owner may provide as a part of its testing services the Building Commissioning services involving the project’s HVAC and exhaust systems, temperature control systems, fire detection and alarm systems, emergency power and lighting system, fire suppression system, security locks and security locking control systems, food service equipment (if applicable), and laundry equipment (if applicable). In the event the Using Agency’s Program specifies additional commissioning services, the Owner shall procure such services as well. The Owner, through its Executive Administrator, may engage an independent Commissioning Authority. It is the intent of this Article that the Commissioning Authority enforce the requirements mentioned herein and certify that the systems and equipment listed all function properly prior to the initiation of each final inspection.

  • Design Development Phase Services 3.3.1 Based on the Owner’s approval of the Schematic Design Documents, and on the Owner’s authorization of any adjustments in the Project requirements and the budget for the Cost of the Work, the Architect shall prepare Design Development Documents for the Owner’s approval. The Design Development Documents shall illustrate and describe the development of the approved Schematic Design Documents and shall consist of drawings and other documents including plans, sections, elevations, typical construction details, and diagrammatic layouts of building systems to fix and describe the size and character of the Project as to architectural, structural, mechanical and electrical systems, and other appropriate elements. The Design Development Documents shall also include outline specifications that identify major materials and systems and establish, in general, their quality levels.

  • Commissioning Commissioning tests of the Interconnection Customer's installed equipment shall be performed pursuant to applicable codes and standards. If the Interconnection Customer is not proceeding under Section 2.3.2, the Utility must be given at least ten (10) Business Days written notice, or as otherwise mutually agreed to by the Parties, of the tests and may be present to witness the commissioning tests.

  • TESTING AND COMMISSIONING 24 Allow for a Lump Sum for testing and commissioning of the entire electrical installation, including the provision of Compliance Certificate. Item Carried to Collection R Section No. 4 Electrical Installation (Provisional) Bill No. 1 Electrical Installation COLLECTION Total Brought Forward from Page No. Carried to Final Summary 76 77 R Amount FINAL SUMMARY Section No Page No 1 Preliminaries 26 2 Alterations (Provisional) 30 3 External Works (Provisional) 73

  • Initial Operation The following requirements shall be satisfied prior to Initial Operation of the Customer Facility:

  • Construction Phase Services 3.1.1 – Basic Construction Services

  • Construction Completion The related Construction shall have been completed substantially in accordance with the related Plans and Specifications, the related Deed and all Applicable Laws, and such Leased Property shall be ready for occupancy and operation. All fixtures, equipment and other property contemplated under the Plans and Specifications to be incorporated into or installed in such Leased Property shall have been substantially incorporated or installed, free and clear of all Liens except for Permitted Liens.